LOCAL GOVERNMENT / NETWORK REFRESH

Council SD-WAN
Refresh Planner.

With our council SD-WAN refresh planner, you’ll record your contract and support deadlines, sites and critical dependencies, as well as services you rely on, which our smart builder will then turn into a formal refresh brief, cost schedule and set of supplier questions you can use to procure your next SD-WAN platform.

By Harry Yelland · Written 26 October 2026
Published 4 November 2026 · Research checked 21 October 2026

26planning inputs
32supplier questions
16unpriced cost categories
12migration milestones
01 / YOUR PRIVATE PLAN

Start my council refresh plan

Answers stay in this browser tab until you leave or reset. Download your draft to keep it. Nothing is sent to Netify or suppliers by this on-page planner. Keep sensitive details in council-held attachments.

Council context, services and deadlines

Choose the nation your council is in. This decides which procurement research we show you, and it never assumes England.

Say what type of council you are and which services it is responsible for, for example unitary, county, district, Scottish, Welsh or Northern Irish. Don't assume services such as social care, housing or highways. List only what your council delivers.

Refresh drivers

Select every reason behind this refresh. Most councils have more than one. Pick Unknown if the objectives haven't been agreed.

Tell us where the project is today. We use it to offer you a draft brief or a supplier question set that fits.

Enter the number of sites in scope, or leave it blank if you don't know. A blank means unknown and is never treated as zero.

Enter the date your current network contract ends, if you know it, as YYYY-MM-DD.

Enter the last date you can give notice or commit to an extension. This is often earlier than the end date.

Describe what the current contract covers, such as circuits, the overlay, management, LAN and security. Use plain descriptions and keep contract references out.

Enter the date your main network devices go out of vendor support, if you know it.

Critical service dependencies

Select the services that depend on this network. Only pick services your council delivers.

Say whether any service still relies on PSN or a restricted partner connection. PSN isn't a circuit type, so answer for services and not for links.

Say whether a shared service or a reorganisation affects the network contract, sites or licences. Answer Not applicable if neither applies.

Say whether telecare alarms or building systems use the network or rely on analogue lines. Answer Not applicable if your council has none.

Choose the model you'd prefer to run after migration. Undecided is a valid answer, and we'll show you how the three compare.

Enter the confirmed project budget in pounds, or leave it blank if there isn't one yet. Never enter a typical or estimated figure here.

Enter the term in months you want proposals compared over, so every response covers the same period.

Enter how the project is funded and the VAT basis your finance team will use. Finance decides VAT recovery and accounting treatment.

Record the procurement arrangement, framework and lot your procurement lead has agreed, if any. This is a record of their decision and not a legal determination.

Enter dates your council wants protected, such as payment runs, billing, elections, duty arrangements or committee periods. Enter only what your service owners have agreed.

Classify the site as Council defined essential, Standard or Low impact. The service owner decides, and the class sets how heavily we test failure at the site.

Enter the longest interruption in minutes the service can accept. This is your council's decision, not a supplier's service level.

Describe access, power or permission issues, such as rural coverage, listed buildings, wayleaves or limited backup power. Keep exact addresses out.

Say whether your council has authorised a request for supplier responses. Preparing a draft doesn't need this.

Say whether the exact supplier-facing summary has been prepared and approved. Nothing is released until it is Approved.

Service continuity requirements

Add the services your council actually runs. Do not enter resident details.

Retained dependencies

Unknown stays Keep. A Retire decision without an owner and sign-off evidence also stays Keep.

Cost schedule: your figures, no assumed rates

Confirm each line is included or not applicable. Monthly and overlap periods are chargeable months; annual periods are chargeable years. C11 staff time and C16 contingency stay separate. Enter an explicitly priced allowance for contingency, not a percentage.

C01 / Discovery and design

One project-level charge, with council and supplier effort recorded as separate lines. Which of this effort is bought from suppliers and which is internal staff time?

C02 / Site surveys and permissions

One charge per affected site, including permissions and any civil works. Which sites have access or permission constraints, and who funds exceptional works?

C03 / Appliances and spares

One charge per site or device, purchased. Rental belongs in a recurring line. Will the council buy or rent equipment, and how will it be capitalised?

C04 / Licences

Charge per licence or site, per month. Does the licence include security and support, so nothing is counted twice?

C05 / Primary access circuits

Charge per circuit, per month, with bandwidth, site and contractual availability noted. Are circuits billed monthly, quarterly or annually, and what is the minimum term?

C06 / Backup access circuits

Charge per backup circuit, per month. Is each backup circuit physically diverse from its primary, and is that evidenced?

C07 / Managed operations

Charge per project or site, per month, covering monitoring, changes, support hours and fault ownership. Which operating model does this charge assume?

C08 / Migration and installation

Charge per wave or per site, split into standard installation, exceptional works and rollback effort. Is rollback effort included in the quoted price?

C09 / Dual running

Incremental monthly charge for each overlapping service, for the actual overlap period only. What overlap period has the council actually assumed?

C10 / Incumbent exit charges

One charge per incumbent contract. Is any exit charge already included in dual running?

C11 / Training and council staff time

Hours or days of training and staff time, with cash spend and internal opportunity cost labelled separately. Does finance want internal staff time in the schedule or only in the business case?

C12 / Power LAN and wireless dependencies

One charge per affected site, limited to work the refresh needs. Who funds LAN, power or wireless work that benefits other projects?

C13 / Ongoing support renewals

Annual charge per project or device. Check included licence support first. Is support included in the licence charge, so nothing is counted twice?

C14 / Reorganisation or estate changes

Charge per change, such as adding, removing, assigning or separating a site. Which estate changes does the council expect during the term?

C15 / End of term exit assistance

One charge per project for exports, transition and access removal. Is end-of-term exit assistance priced now or at exit?

C16 / Contingency

A percentage or amount applied to a defined eligible subtotal. What percentage, basis and exclusions does finance want?

Migration milestones

Enter council-supplied durations and dates. No assumed timetable or date calculation is imposed.

MS01 / Estate discovery

Gather the contract, circuit list, asset and licence list and site details. Record what's missing as an open item with an owner. Enter a duration or date only if you know it.

MS02 / Essential-service requirements

Work with service owners to name the applications, agree the interruption each service can accept, and set change windows. These are the council's decisions.

MS03 / Business case and funding

Build the cost schedule from your own figures and supplier quotes. Finance confirms funding, VAT basis and scope assumptions.

MS04 / Procurement route review

Ask the procurement lead to record the route and any notices required. The route is their decision.

MS05 / Supplier process

Run the process your council has approved and keep responses comparable using the same site list, term and responsibilities.

MS06 / Surveys and delivery

Confirm access, permissions and any civil works site by site. Flag rural and difficult-access sites for early survey.

MS07 / Configuration and staging

Review configuration and documentation before any site goes live. Confirm who holds which access roles.

MS08 / Representative pilot

Test normal running and failed-link running with the named council applications. Include an essential-service site and a difficult-access site where you have one.

MS09 / Migration waves

Move sites in waves, each with its own approval, rollback trigger and responsible officer. Avoid your protected dates.

MS10 / Hypercare

Agree who owns incidents, what is monitored and how escalation works while the new service beds in.

MS11 / Incumbent cessation

Stop the old service only after recorded acceptance and dependency sign-off. Show overlap charges until the stop date.

MS12 / Handover and exit readiness

Confirm access, training, exports and the next review date so the next refresh doesn't depend on an inaccessible management tenant.

ILLUSTRATIVE EXAMPLE / NOT A CUSTOMER

A 24-site council refresh.

To show what the planner produces, we've created an example (fictional) English unitary council that's reviewing a 24-site managed network ahead of a confirmed contract expiry. The estate includes civic offices, customer-contact sites, libraries and depots, and the council retains a restricted service connection, uses Microsoft 365 and a hosted revenues-and-benefits application and hasn't yet confirmed its notice period or rural depot mobile backup. Its preferred model is co-managed, and budget rates and service interruption targets haven't been supplied. It isn't a customer, it contains no supplier quotes and it implies no market rates or savings.

Use the example button in the planner ↑
02 / HARRY’S COMPLETE GUIDE

The full manuscript follows, including all tables, examples, tool copy, sources and outstanding questions. Working notes remain attributed to the supplied manuscript.

Council SD-WAN Refresh Planner

By Harry Yelland, 26/10/2026

For /insights/council-sd-wan-refresh/

Many councils come to the end of their network or SD-WAN contracts and often look to change or consolidate tools, however vendor offerings are difficult to compare, and marketing strategies push different metrics and jargon, making each solution seemingly the same as each other. However, at Netify, we not only understand the nuances between each solution but also how councils choose platforms to fit around the services that their residents depend on.

With our council SD-WAN refresh planner, you’ll record your contract and support deadlines, sites and critical dependencies, as well as services you rely on, which our smart builder will then turn into a formal refresh brief, cost schedule and set of supplier questions you can use to procure your next SD-WAN platform.

What you'll get from our refresh planner

  • Council refresh brief: A project summary you can copy and edit to send to different vendors and MSPs.
  • Council refresh cost schedule: A general idea of pricing.
  • Supplier question pack: A set of targeted questions to close potential gaps between your council’s requirements and vendor offerings.

Start my council refresh plan

See what my plan will include

Privacy Disclaimer

We'd recommend reviewing all input details, ensuring any confidential details aren’t included and keeping exact site addresses, network diagrams and security findings out of the planner and in restricted attachments held by your council.

Choose the reason for your refresh

We find that councils rarely refresh their network for one single reason, so we'd recommend selecting everything that applies, as your choices decide which questions the planner asks next and what goes into your statement of objectives.

Trigger

What it means for the council

Next information to request

Contract renewal

The notice date can fall well before the end date, so the real deadline is the date you must commit to an extension or give notice. A renewal is also the moment to settle scope, and Greenwich's October 2026 procurement approval covers managed WAN, LAN, WiFi and firewall services [S01], so decide early what sits inside yours.

End date, notice period and extension options (contract owner).

Hardware end of support

Equipment past its support date turns every fault into a risk the council carries itself, and it sets the latest date you can stay put.

Device support dates and licence expiry (network lead, from the asset list).

Service resilience

One failed site or circuit can stop a named service, therefore the project is judged on the council services that keep running after a failure.

Which services run from which sites, and the interruption each can accept (service owners).

Cloud access

Application access has outgrown a network built around a central site. Enfield's April 2026 award decision ties its network refresh to legacy architecture and cloud connectivity [S02].

Hosted and cloud applications in use, with an owner for each (application owners).

Shared services

A contract that serves more than one authority needs its boundaries drawn before anyone renews it. Cheshire East's May 2025 report asks for separate contracts so that a later split between two councils doesn't force a novation [S26].

Contract holder, who pays and who administers (programme lead and procurement).

Reorganisation

A long contract can outlive the authority that signed it, therefore transfer and separation terms matter from day one [S14]. Apply this only if your council is affected.

Assignment, transfer and separation terms (programme lead and legal).

Identify the council services that must keep working

One of the key places to start is by identifying what your council is accountable for and what responsibilities and services must be upheld for residents. Given that there’s such a vast difference in what’s covered between the likes of a unitary council, a county, a district and a Scottish, Welsh or Northern Irish council, and with each offering different services, all necessary services should be explicitly defined and detailed, as a generic services detail from another council will unlikely be an exact fit for your council’s needs.

To assist with this, we’ve provides the below example prompts to help get you started, though none of these are mandatory so you’re more than welcome to delete any your council doesn't deliver and add the ones it does.

Candidate services include adult and children's services where your council runs them, revenues and benefits, housing and homelessness, customer contact, libraries, depots and civic sites. Out-of-hours duty teams and emergency coordination only belong in the matrix if your council operates them, in which case record the hours they need and the site or remote path they use.

From there, we'd separate office uptime from resident-facing availability. Office uptime tells you staff can reach the network, whereas resident-facing availability tells you a resident can pay, report, apply or be helped. A revenues and benefits team can be fully connected to its office whilst the hosted application behind it is unreachable, which is why office connectivity on its own never proves service continuity.

The maximum acceptable interruption for each service is your decision, agreed with the service owner, so we'd leave it blank until the owner has agreed it. Local Digital's CAF for local government starts by identifying the essential services and critical systems a council relies on [S12], so this matrix doubles as a ready-made input to that work.

Scope is rarely just the WAN. For example, the South Oxfordshire and Vale of White Horse's tender replaces the active network components of their offices and buildings as part of an SD-WAN transition [S03], so check which of your service sites also depend on ageing switching and wireless.

Service

Council responsible?

Service owner

Sites

Hours

Application dependency

Maximum acceptable interruption (council decides)

Acceptance test

Revenues and benefits

Yes / No / Shared

Name or role

Site list

Hours

Hosted application name

Minutes, or Unknown

Named action, e.g. take a payment from the depot

Customer contact

Yes / No / Shared

Name or role

Site list

Hours

Telephony and case system

Minutes, or Unknown

Answer a call with the record on screen

Libraries

Yes / No / Shared

Name or role

Site list

Opening hours

Public access and staff systems

Minutes, or Unknown

Public session and staff session both work

Depots

Yes / No / Shared

Name or role

Site list

Shift pattern

Works and fleet systems

Minutes, or Unknown

Job dispatch works on the backup path

Out-of-hours duty (only if applicable)

Yes / No / Not applicable

Name or role

Site or remote

Duty hours

Duty rota and case access

Minutes, or Unknown

Duty officer reaches the case system

Build the estate and contract inventory

When looking to renew, it’s important to understand what you own, rent and when each contract ends/costs of terminating contracts for your current estate, as this will give you a greater idea of how to proceed in procurement and rollout.

Given the importance, scale and rigidity of a lot of these factors, we often find that this step decides the timetable of a council SD-WAN refresh. To help plan this in, our refresh planner asks for the fields below and lets you answer Known, Unknown, None or Not applicable for each.

Field

What to record

Why it matters

Sites and region

Site type, nation and broad region

Sets scope and survey effort.

Shared-service boundary

Which sites, contracts and licences belong to which authority

A reorganisation or split can move them [S14].

Circuits

Type, supplier and contract reference per circuit

Different circuits end on different dates.

Termination and notice

End date, notice period and extension options

The notice date is usually the true deadline.

Devices and licences

Support end dates and licence terms

Sets the latest date you can stay put.

Exit assistance

What the incumbent must provide at exit

Decides how clean the handover is.

Access and power

Rural access, listed buildings, wayleaves, power, LAN capacity and wireless dependencies

Each one can add a survey, a permission or a civil works cost.

Recommendations on public and restricted information

Can appear in a reviewed supplier summary

Stays in restricted council attachments

Number of sites by tier, nation and broad region

Street addresses and site-level access notes

Contract end quarter or year, if the council approves it

Circuit references and supplier account numbers

Operating model and service categories

Topology diagrams, IP addressing and device serials

Whether a restricted service connection is retained

Security assessments and vulnerability reports

Decide the network boundaries before removing legacy links

Before any legacy circuits are retired, one of the key steps is mapping out what actually relies on them, and we often find that the dependencies which catch councils out are PSN access, partner connections, legacy addressing and allowlists, DNS and identity, Azure-hosted services and shared systems. To help with this, our planner takes you through each of them and records an owner and a decision for every one.

PSN is a good example, as it's a compliance arrangement that sits separately from any circuit type. PSN-connected organisations hold compliance certificates for connection, service provision or connectivity [S11], so retiring a legacy circuit tells you nothing about whether a PSN-dependent service still needs a path. No closure date is published, therefore the only reliable answer comes from the service owner who uses the connection.

Partners need the same attention. Police, health and neighbouring authorities may allowlist your council's address ranges, so a change of addressing can break a connection that nobody on the network team knew existed. Azure is another example, as South Oxfordshire and Vale of White Horse's tender requires security appliances to support site-to-site VPN into Microsoft Azure for each site [S03]. We'd ask where your own cloud and hosted services connect and who owns each connection.

As a rule, we'd recommend that no circuit is removed until the owner of every dependency on it has signed off, and that a security component only goes into the design against a requirement your council has named.

Dependency

Type

Owner

Current path

Decision (Keep, Change, Retire, Unknown)

Sign-off evidence

Restricted service connection

PSN or partner

Service owner and security lead

Described, not diagrammed

Keep until reviewed

Signed dependency review

Hosted revenues and benefits application

Hosted application

Service owner

Described

Change or Unknown

Named application test

Azure-hosted service

Cloud

Application owner

Described

Change or Unknown

Connection test

Partner allowlist on council ranges

Addressing

Network lead

Described

Unknown until partner confirms

Partner confirmation

DNS and identity

Core service

Network and identity leads

Described

Keep or Change

Failover test

How the decision table works

  • Keep: The dependency stays on its current path until reviewed.
  • Change: The dependency moves to the new design after a witnessed test.
  • Retire: Only when the owner confirms nothing depends on it and signs the register.
  • Unknown: Treated as Keep, and an action is created for the owner.

Specify resilience by council service and site

Resilience only means something when it's tied to a service, so for each site we'd ask what has to survive a circuit failure, a power cut or a provider problem, and write the answer in terms of the services your council delivers, such as revenues and benefits, housing support and any duty services.

Three things often get confused in supplier responses, those being response, restoration and application recovery. Response is how fast the supplier acknowledges a fault, restoration is how fast the connection comes back and application recovery is how fast the council service works again, and a quick acknowledgement says very little about the last one.

Diversity needs evidence too, as two provider names on a proposal don't prove two routes and two retail suppliers can share the same duct, exchange or fibre, so we'd ask for physical route and exchange information for each essential site. Mobile backup works the same way, because a coverage map doesn't establish a usable backup and coverage and performance should be measured on site under expected load, and backup power matters as well since mobile backup is no help when the site equipment has no power. Monitoring is part of the answer too, given that Greenwich's procurement approval combines on-site engineers with back-office monitoring and support [S01], so ask your bidders who watches a failed link at the hours your duty services run.

Testing should be proportionate. Local Digital's CAF focuses on essential services and critical systems [S12], and our recommendation is that your site tiers follow the same logic, with essential sites getting the full witnessed test and low impact sites not needing one.

Site tier (council defined)

Evidence to request

Witnessed acceptance test

Essential

Route and exchange diversity, on-site mobile measurement, battery runtime, monitoring hours

Pull the primary link, then lose power, while the named council application runs. Record time to recover and rollback owner.

Standard

Backup design, monitoring hours

Pull the primary link while the named application runs.

Low impact

Documented behaviour on failure

Documented only, unless the service owner asks for more.

Unknown

Tier classification from the service owner

Not scheduled until classified.

Degraded-mode tests to include

  • Primary circuit failure with the named application running.
  • Site power loss, with the stated battery runtime measured.
  • Provider-side failure, simulated with the supplier and the council's change authority present.
  • Return to normal running, confirmed by the service owner.

Plan security and assurance evidence for the refresh

Security teams and service owners need different evidence, and we'd recommend asking for it early to save rework at the RFP stage. Start with segmentation, as a library offering public access, council staff, contractors and building systems such as CCTV all have different trust boundaries, so ask bidders to show how they're separated where they're in scope and how you'd test that at acceptance.

From there, your council should own the administrator accounts that matter, and we'd ask what data is logged, where it's processed, how long it's kept, who at the supplier can see it and what incident evidence you'd receive.

On assurance, it helps to be clear about what a purchase can do. Local Digital's CAF for local government is voluntary, begins with essential services and critical systems and includes an independent assurance review [S12], and by January 2026, 90 councils had completed an assessment with the programme moving to CAF version 4.0 [S13]. Buying a network or a managed service doesn't give you CAF or PSN compliance, but it can produce evidence for the actions in your own CAF plan, so we'd ask your security lead to name those actions before the RFP goes out. If any service still relies on a PSN or restricted partner connection [S11], the service owner and security lead decide what happens to it before design starts.

Finally, we'd involve your DPO early. A data protection impact assessment is needed where processing is likely to be high risk, and the ICO's list includes systematic monitoring of a publicly accessible area on a large scale [S15]. Its guidance is under review following the Data (Use and Access) Act, so if your refresh changes what's logged, inspected or visible to a supplier, ask your DPO to screen it before anything is issued.

Evidence

Ask for

Accountable reviewer

Segmentation

Policy design and acceptance tests for staff, public access, contractor and building-system traffic

Security lead

Privileged access

Role model, multi-factor access reviews and emergency access procedure

Security lead

Logging and inspection

Data-flow summary, retention and supplier access

DPO and security lead

Updates and patches

Who updates what, and how the council is told

Network lead

Incident evidence

Incident workflow, escalation example and log access

Security lead

CAF actions

Evidence mapped to the council's own CAF improvement actions

Security lead

PSN or partner dependencies

Owner-approved transition plan

Service owner and security lead

Build the council refresh cost schedule

A cost schedule only helps if finance can trust it, so we've built our planner to be strict about what counts as a number. It separates your incumbent baseline from the new costs, splits the new costs into one-off, recurring, dual running, surveys, civil works, licences, staff time, training, support, exit and expansion, and gives every line a VAT basis of Excluding VAT, Including VAT, VAT not applicable or Unknown.

Rates either come from your council or from a supplier quote, and if you don't have one it stays unknown, as the planner never fills a gap with a typical figure and a blank is never treated as zero.

We'd also be careful with headline numbers in published decisions. Greenwich's approval carries an estimated £16 million over a term of up to ten years, but it covers managed WAN, LAN, WiFi and firewall services [S01], so it isn't an SD-WAN price or a per-site benchmark. South Oxfordshire and Vale of White Horse's notice displays £0 [S03], which tells you nothing about cost. A tender envelope is never a unit rate.

The whole-term total simply adds the one-off costs, the recurring monthly and annual rates over their chargeable periods and any priced overlap and exit items, with staff time and contingency shown separately. If any required line is missing, the planner shows a priced subtotal and lists what's missing, so it never shows a complete total or a savings percentage built on an incomplete baseline. We'd only compare incumbent and proposed costs across the same estate and the same term, and we'd always keep the priced subtotal on screen beside the list of missing lines, as a total that hides its gaps is the one finance will question. Our contract terms article covers SLA structures and a hidden-cost checklist in general terms [S23].

Completeness warning

This schedule contains unpriced items. Review the missing rates before using a complete project total.

Nominal annual cash flow layout

Cost line

Basis

Year 1

Year 2

Year 3

Later years

One-off lines (C01, C02, C03, C08, C11, C12, C15)

one_off

Unknown

Unknown

Unknown

Unknown

Recurring monthly lines (C04 to C07)

recurring_monthly

Unknown

Unknown

Unknown

Unknown

Recurring annual lines (C13)

recurring_annual

Unknown

Unknown

Unknown

Unknown

Dual running and exit (C09, C10)

overlap_monthly / one_off

Unknown

Unknown

Unknown

Unknown

Optional and contingency (C14, C16)

optional / allowance

Shown separately

Shown separately

Shown separately

Shown separately

Priced subtotal

Calculated from priced lines only

Not complete

Not complete

Not complete

Not complete

The 16 cost categories, with units and the question each one raises for finance, are listed in the cost schedule appendix.

Choose an operating model the council can support

Who runs the network after migration is a staffing decision as much as a technical one, so our planner compares three models against your team size, duty cover and the rate of change you expect. In a council-managed model your team owns operation, in a co-managed model responsibilities are split and written down, and in a fully managed model the supplier runs the service to a specification you set.

We'd recommend starting from honest numbers. A small team with no out-of-hours cover shouldn't pick council-managed for services that run out of hours, and a team that changes policy weekly will find a managed model with charged changes expensive and slow. Whichever you pick, write down who owns each item in the table below, as disputes tend to happen where ownership was assumed, and ask every bidder to respond in the same table so the proposals are like for like.

Responsibility

Council-managed

Co-managed

Fully managed

Council decision

Circuits and access suppliers

Council contracts directly

Named split

Supplier contracts and manages

To enter

Policies and changes

Council writes and changes

Council writes, supplier applies within a change catalogue

Supplier changes to a council-approved standard

To enter

Patches and updates

Council

Named owner per item

Supplier, council notified

To enter

Incidents and escalation

Council raises with each supplier

Shared workflow

Supplier owns end to end

To enter

Out-of-hours cover

Council duty rota

Named split

Supplier

To enter

Subcontractors

Council manages

Disclosed and notified

Supplier discloses and notifies

To enter

Exit exports

Council holds

Joint

Supplier provides on exit

To enter

Shared-service governance (if applicable)

Council

Named per authority

Named per authority

To enter

Where your council shares the network with another authority, the table also needs the governance for each partner and what happens to the contract if a partner leaves [S14].

Set the procurement route with your council team

We'd recommend settling the basics before picking a framework. The planner asks for your nation, procurement arrangement, existing framework and current contract regime first and only then shows route notes, and as your procurement lead decides the route (nothing here is a legal determination) we'd get your procurement officer into the room before the first supplier conversation.

Early market engagement and formal competition are different things. Under the Procurement Act in England, engagement before a tender mustn't give any supplier an unfair advantage, and where an authority engages the market above threshold it either publishes a preliminary market engagement notice or explains in the tender notice why it didn't [S08]. Netify's marketplace supports preparation and engagement, whilst statutory notices, council approvals and your tender portal stay separate.

Published council procurements show how varied the routes are. Greenwich approved an Open Procedure under the Procurement Act 2023 [S01], Cheshire East's report proposes a mini-competition under Network Services 3 Lot 1a [S26], Adur and Worthing's decision is a direct award under the SBS DWS2 framework [S04] and East Riding's tender notice uses a competitive flexible procedure [S05]. Those were chosen for different scopes, so none of them is a route we're recommending.

Network Services 3 (RM6116) is a useful dated example. As at 21 October 2026 it remains a PCR2015 framework, lot 1a covers inter-site connectivity (wide area network) and lot 2a covers intra-site connectivity (local area network), and most lots end on 17 July 2027 with lots 1c and 1d ending on 22 May 2027 [S06]. We'd check your eligibility, whether the lot fits your scope and whether your award and contract start can land before the lot ends.

Scotland, Wales and Northern Ireland each follow their own rules. Devolved Scottish authorities are generally excluded from the Procurement Act [S07], and Scottish public procurement follows the Procurement Reform (Scotland) Act 2014 and the Public Contracts (Scotland) Regulations 2015 [S10]. Welsh authorities should use the Welsh Government's guidance and notice sequencing [S09], and Northern Ireland authorities should confirm applicability with their procurement team, as the Act regulates them with some differences [S07].

Nation

Start here

Reviewer

England

Confirm whether the Act or a legacy framework applies. RM6116 is a legacy framework, so identify lot, eligibility and method.

Council procurement lead

Scotland

Use Scottish procurement legislation and the council's arrangements. Don't apply the English route automatically.

Council procurement lead

Wales

Use Welsh Act guidance and Welsh notice requirements, plus any transitional rules.

Council procurement lead

Northern Ireland

Confirm transferred-authority status and arrangement rules before assuming an English sequence.

Council procurement lead

Questions for your procurement officer

  • Which nation's rules and which arrangement apply to this procurement?
  • Is there an existing framework or contract we must or may use, and until when?
  • Do we need a preliminary market engagement notice before we speak to suppliers?
  • What is the estimated value, and which valuation method will procurement use?
  • Who approves the route and when?

Schedule the pilot and migration around council services

Start from the dates you can't move and work backwards. Put in your contract end date, your notice date and any decision dates, then add the lead times your own council knows, such as committee cycles, procurement approvals and survey access. There isn't a universal migration duration, so the planner doesn't assume one and anything unconfirmed is flagged as such.

Two published examples show why the order matters. Cheshire East's May 2025 report asked for approval to procure a replacement for a contract expiring on 3 February 2026, and notes that a two-year extension would carry at least 31.9% in inflation costs [S26], whilst East Riding's tender notice expects the solution to be live by 1 April 2027 against an estimated contract start of 1 June 2026 [S05]. In both cases the gap between a decision and a working network is what decides whether you need an extension and what it costs.

Then protect the dates that matter locally, which might include revenues and benefits payments, billing runs, elections, out-of-hours duty arrangements and committee or public-access services. The planner only protects what you enter, and if a shared service or reorganisation applies we'd add the transfer and separation dependencies as well, given that continuity through organisational change is what the LGA's reorganisation research centres on [S14].

Plan the pilot to find problems and give the design a proper test, as we think a pilot that only proves the easy sites has proved very little. Include an essential-service site and, where you have one, a difficult-access site, and plan each wave site by site.

Milestone

Owner

Depends on

Council duration or date

Confidence

Acceptance evidence

MS01 Estate discovery

Council network lead

Contract and asset access

Council enters

High, Medium or Low

Inventory with missing information recorded

MS02 Essential-service requirements

Council service owners

Service responsibility scope

Council enters

High, Medium or Low

Application dependencies, interruption targets and change windows

MS03 Business case and funding

Council finance and IT

Comparable cost schedule

Council enters

High, Medium or Low

Approved funding and scope assumptions

MS04 Procurement route review

Council procurement lead

Nation, arrangement and contract regime

Council enters

High, Medium or Low

Recorded route decision and required notices

MS05 Supplier process

Council procurement lead

Approved process and documentation

Council enters

High, Medium or Low

Comparable responses through the authorised route

MS06 Surveys and delivery

Supplier and council estates

Site access, permissions and access design

Council enters

High, Medium or Low

Site delivery dependencies confirmed

MS07 Configuration and staging

Supplier and council network lead

Design and access roles approved

Council enters

High, Medium or Low

Configuration and documentation reviewed

MS08 Representative pilot

Service owners and supplier

Test criteria, rollback and dependencies agreed

Council enters

High, Medium or Low

Witnessed application failover and recovery results

MS09 Migration waves

Council change authority

Pilot acceptance and site readiness

Council enters

High, Medium or Low

Per-wave approval and rollback record

MS10 Hypercare

Supplier and council operations

Wave completion

Council enters

High, Medium or Low

Incident ownership, monitoring and escalation confirmed

MS11 Incumbent cessation

Council contract owner

Service acceptance and dependency sign-off

Council enters

High, Medium or Low

Approved stop dates and final overlap cost

MS12 Handover and exit readiness

Council operations

Accepted service and documentation

Council enters

High, Medium or Low

Access, training, exports and next review date

Acceptance checklist

  • Normal-running and failed-link tests run the named council applications, not just a speed test. Owner: network lead.
  • A representative essential-service site and a difficult-access site are in the pilot where they exist, and rural backup is measured on site. Owner: service owners.
  • A circuit failure, power loss or routing problem has a named response owner and an agreed rollback action. Owner: change authority.
  • The service owner confirms outcomes and the IT team receives usable configuration, documentation and access. Owner: service owners and IT.
  • The old service stops only after recorded acceptance and dependency approval, with overlap charges visible. Owner: contract owner.

Learn from published council refresh programmes

To assist in your own council’s refresh programme, one of the best places to start is to consider other council’s already published programmes (albeit, these will have a slightly different scope and requirement set). We’ve highlighted the below examples, which show councils at different stages, decisions, tenders and outcomes.

  • Greenwich approved procurement of a network managed services contract on 1 October 2026. It covers managed inter-building and intra-building networks, internet and wireless services and firewalls, with on-site engineers and back-office monitoring, and a WAN and LAN hardware refresh is already in train. The estimated £16 million over up to ten years is the whole service envelope, so it isn't an SD-WAN price [S01]. It's an approval, so it shouldn't be read as an award.
  • Enfield awarded a network refresh in April 2026 that addresses legacy architecture and cloud connectivity [S02]. No price or delivery outcome is established, therefore we'd treat it as a pointer to scope only and use it to ask how your business case links architecture, cloud access and resilience.
  • South Oxfordshire and Vale of White Horse published a joint tender on 20 December 2024 for LAN, wireless and security refresh, supporting a transition to SD-WAN. It asks for hardware, five-year licence and support, installation and annual support to be priced separately, and it is now closed with no award shown [S03]. The £0 value on the notice is unusable.

Council

Nation

Stage and date

Scope

What it helps you ask

Adur and Worthing Councils

England

Decision to direct award, 29 September 2026 [S04]

Migrate fibre networking across 22 council sites to SD-WAN over CityFibre using a commercial ISP, under the SBS DWS2 framework

How does the access network sit alongside the SD-WAN service?

East Riding of Yorkshire Council

England

Two tender notices, December 2025, and two award notices, June 2026 [S05, S24, S36, S37]

A Cisco-based SD-WAN solution and, separately, WAN connectivity

Should platform and connectivity be bought together or apart?

Cheshire East Council

England

Council report for decision, 14 May 2025, and award notice, August 2025 [S26, S32]

SD-WAN connectivity for a shared ICT service, via Network Services 3 Lot 1a, with separate contracts to avoid novation if the partners split

How do shared-service ownership and contract transfer shape the contract?

Ten Northern Ireland councils

Northern Ireland

Joint contract notice, 7 April 2022 [S27]

Managed network services including WAN connectivity, firewalls and internet over new fibre, 120 months, open procedure

How do ten authorities define one shared service?

Highland Council

Scotland

Agreement announced, 24 October 2023 [S29]

Network services under the Scottish Wide Area Network framework across over 340 sites, including some of the most challenging locations in Scotland

How do you scope remote and difficult-access sites?

We'd use these to compare what was in scope and what each council chose to buy separately, as they aren't price benchmarks and don't establish that any project succeeded.

Create your council refresh RFP

Once your brief, services, dependencies and cost schedule are in place, the next job is turning them into a council network refresh RFP with supplier questions your bidders can answer like for like. Netify's RFP builder handles the drafting and review, whilst your council keeps the decisions.

Your council-specific export brings together a project title and summary, your council responsibilities, service outcomes, estate scope, timing, dependencies, operating model, the cost response schedule, your chosen questions, unresolved items and a procurement note. Detailed sites, topology, logs and security assessments stay out as restricted attachments, and open items travel with the draft so a missing notice period or an unagreed interruption target stays visible. Questions are labelled as either preliminary engagement, which shape requirements without asking for prices, or RFP questions with priced responses, which ask suppliers to price the same site list, term and responsibilities using your cost schedule.

The builder produces a private draft you can download without an account or publication [S19]. Its checker flags coverage gaps but doesn't certify that an RFP is ready to issue [S19], so the review stays with you. If you're still deciding which providers to approach, Netify's UK public sector comparison covers provider evidence [S22]. Before you issue anything, we'd have service owners check the continuity requirements, finance check the cost schedule, your security lead and DPO check the assurance questions and procurement check the route and the wording of the procurement note, as the procurement responsibility stays with your council, including notices, approvals and your tender portal [S08].

Copy beside the button

Use your council refresh plan to prepare an editable RFP draft. Review the service requirements, cost schedule and unresolved questions with the relevant council teams before you issue it.

Create my council refresh RFP

If your plan doesn't carry across automatically

Copy the brief and question list from your plan into the builder, then add your open items as notes, and your private draft stays with you either way. Our view is that the review works best as one meeting with every team in the room, so that conflicting answers surface before issue

Request supplier responses when your council is ready

Asking for supplier responses is optional, and it comes after you've reviewed your draft. Before anything leaves your council, check the supplier-facing summary line by line and confirm the council's procurement route with your procurement officer. Netify doesn't publish anything automatically and no supplier receives your information unless you approve it. In our view an approach to suppliers should be the last step of the process.

A sourcing request through Netify doesn't replace your procurement strategy, statutory notices, framework process or tender portal, and preliminary engagement must still treat suppliers fairly [S08]. Netify doesn't guarantee bids, and an approach to providers isn't an award route. Suppliers pay Netify when an introduction leads to business, and that doesn't affect how providers are ordered [S19].

Discuss my council refresh with a Netify SD-WAN and SASE expert

When your council is ready, review the sourcing approach and approve the summary and providers that may receive it. Keep sensitive network details in restricted attachments.

Anonymisation checklist

  • Council name and exact dates removed unless your council has approved them.
  • No site addresses, topology diagrams, IP addresses or device serials.
  • No security assessments, vulnerability findings or named staff.
  • Rates and budget excluded unless the council has approved sharing them.
  • Retained restricted-service connections described by category only.
  • An authorised council buyer has approved the summary.

Answer council refresh questions

We still have a PSN connection. Can we retire our legacy links?

Not until the service owner confirms what depends on it. PSN is a compliance and connection arrangement that sits apart from any circuit type, and holding a certificate doesn't tell you whether a service still needs a path [S11]. We'd answer the PSN or restricted partner dependency input in the planner and keep Q03 in your question set.

Our contract ends before our council WAN replacement can be delivered. What do we do?

Price the bridge before you choose it. Cheshire East's May 2025 report on a contract expiring in February 2026 notes that a two-year extension would carry at least 31.9% in inflation costs [S26], and dual running adds more on top. Enter your end date, notice date and extension options, then price the overlap and any delayed delivery with Q21.

We might be reorganised. Should the contract allow for that?

Yes, if reorganisation applies to your council, so ask for transfer, separation and assignment terms and what they cost [S14]. Cheshire East's report seeks separate contracts to avoid novation if its two partners split [S26], which is a good example of planning for it up front. We'd set the shared service or reorganisation input to Yes or Unknown, which adds Q04, Q05 and Q22.

How do we keep library public access separate from CCTV and building systems?

Ask for the segmentation design and an acceptance test for each trust boundary. Where CCTV monitors a publicly accessible area your DPO should screen the change, as large-scale systematic monitoring of public areas is a high-risk processing example in the ICO's DPIA guidance [S15]. Include Q10 and ask your DPO to review it.

What if mobile backup is poor at a rural depot?

Measure it on the site, under load, before you accept the design, as a coverage map doesn't establish a usable backup and backup power matters too. Highland Council's 2023 agreement covers over 340 sites including some of the most challenging locations in Scotland [S29], which shows how wide difficult-access estates can get. Add the site access and power input, a survey line in C02 and Q08 and Q09.

Where will our data be processed and who at the supplier can see it?

Ask for a data-flow summary covering what's collected, where it's processed, how long it's kept and who at the supplier can see it. Your DPO decides whether a DPIA is needed [S15], so add Q13 and send the answer to them and your security lead.

We want a co-managed service. How do we keep control?

Write the split down item by item and ask every bidder to respond in the same table. We'd pay particular attention to which changes your team can make and which are charged or need supplier approval. Choosing Co managed in the planner adds Q15 and Q17 and the responsibility matrix.

We don't have a confirmed budget. Can we still go to market?

You can prepare and engage, but we wouldn't use a headline figure as a budget. Greenwich's estimated £16 million covers managed WAN, LAN, WiFi and firewall services over up to ten years [S01], so it isn't a benchmark for a WAN refresh. Leave the budget input blank and the cost schedule shows a Priced subtotal with the missing lines listed.

We're a Scottish council. Does the English route apply?

Not automatically. Devolved Scottish authorities are generally excluded from the Procurement Act [S07] and Scottish public procurement runs on its own legislation and handbook [S10]. Highland Council's 2023 agreement used the Scottish Wide Area Network framework [S29]. Select Scotland as your nation and ask your procurement lead to approve the route.

Do telecare alarms affect our network plan?

They can, if your council's services include them. Analogue telecare that isn't upgraded may become unreliable or stop working during the digital phone switchover, which is due to complete by January 2027 [S17, S16], and a network upgrade doesn't make an analogue device safe. Set the telecare input to Yes or Unknown, which adds Q30 and a device-owner assessment before any affected cutover.

Can we use Network Services 3 for a refresh?

It might suit some councils, though only your procurement lead can say. As at 21 October 2026 it's a PCR2015 framework, lot 1a covers WAN and lot 2a covers LAN, and most lots end on 17 July 2027 [S06]. Record the framework and lot in the procurement route input and ask procurement to confirm eligibility.

Will Netify publish our requirement or approach suppliers for us?

Not unless you approve it. The RFP builder lets you download a private draft without an account or publication [S19], and optional supplier responses only follow your review and don't replace your own procurement process. Keep the supplier-facing summary input at Not prepared until your buyer approves it.

Illustrative council scenario

To show what the planner produces, we've created an example (fictional) English unitary council that's reviewing a 24-site managed network ahead of a confirmed contract expiry. The estate includes civic offices, customer-contact sites, libraries and depots, and the council retains a restricted service connection, uses Microsoft 365 and a hosted revenues-and-benefits application and hasn't yet confirmed its notice period or rural depot mobile backup. Its preferred model is co-managed, and budget rates and service interruption targets haven't been supplied. It isn't a customer, it contains no supplier quotes and it implies no market rates or savings.

Illustrative council scenario. Output one, council refresh brief

We are planning a 24-site council SD-WAN refresh with a co-managed operating model. The scope includes civic, customer-contact, library and depot locations. Suppliers will need to explain continuity for our named council applications, retained restricted-service connectivity, public-access separation and rural-site backup. We need an itemised transition and operating cost schedule, a representative pilot and an agreed responsibility matrix. Contract notice terms, service interruption targets and backup surveys remain to be confirmed.

Illustrative council scenario. Output two, information to confirm

Missing item

Owner

Effect on the plan

Notice period

Contract owner

Delivery plan cannot assume an available extension

Restricted-service scope

Service owner and security lead

Retain path until approved dependency review

Rural backup performance

Network lead and supplier

Survey and test before accepting design

Application interruption target

Relevant service owners

Agree target and test before pilot approval

Cost rates

Finance and procurement

Show unpriced schedule without a whole-term total

Illustrative council scenario. Output three, supplier question pack

The initial set is Q02, Q03, Q06, Q09, Q10, Q15, Q17, Q20, Q23, Q24, Q25 and Q26. Two scope-sensitive additions are proposed because the scenario uses Microsoft 365, a hosted application and rural depots with mobile backup, those being Q11 (applications) and Q08 (backup power). The reference numbers are working references only and aren't live question-bank IDs.

Ref

Area

Supplier question

Evidence requested

Q02

Continuity

Explain how revenues and benefits applications and agreed out-of-hours duty services will continue during each migration wave.

Application dependency map and service-owner sign-off plan.

Q03

Dependencies

Identify retained PSN and partner connections and how they will coexist with the proposed design.

Connectivity dependencies and owner-approved transition plan.

Q06

Resilience

Demonstrate physical diversity for the proposed primary and backup links at each essential site.

Route and exchange information subject to controlled disclosure.

Q09

Rural access

Validate mobile backup availability and performance at rural depots or other difficult sites.

Site survey and tests under expected load.

Q10

Segmentation

Show how council staff library public access contractors CCTV and building systems are isolated where in scope.

Policy design and segmentation acceptance tests.

Q15

Operations

State who owns a fault spanning circuit appliance cloud policy and third-party application.

RACI incident workflow and escalation example.

Q17

Changes

State which changes the council can make and which are charged or subject to supplier approval.

Change catalogue permissions service windows and charges.

Q20

Costs

Price the same site list, term and service responsibilities using the council's cost schedule.

Itemised one-off recurring and optional charges in GBP with VAT basis.

Q23

Delivery

Provide a dependency-led plan around the council's listed elections, payments and change restrictions.

Milestones dependencies owner and lead-time assumptions.

Q24

Pilot

Propose a representative pilot including an essential-service site and a difficult access site where appropriate.

Pilot selection rationale and acceptance evidence.

Q25

Rollback

State rollback triggers responsible officers and the last reversible point for each cutover.

Runbook and witnessed recovery test.

Q26

Exit

Describe configuration and log exports licence ownership access revocation and transition assistance at exit.

Exit plan format and priced assistance.

Q08 (proposed addition)

Resilience

Describe backup power capacity maintenance and recovery for the specified sites.

Power dependencies runtime basis and test schedule.

Q11 (proposed addition)

Applications

Confirm performance and routing for the council's named Azure, Microsoft 365 and retained hosted applications.

Application test results under normal and degraded connectivity.

Illustrative council scenario. Output four, cost schedule and milestones

No rates have been supplied, so every line is unpriced and the schedule shows no whole-term total.

Line

Category

Unit

Quantity

Rate

VAT basis

C01

Discovery and design

One project-level charge, with council and supplier effort recorded as separate lines

Unknown

Unknown

Unknown

C02

Site surveys and permissions

One charge per affected site, including permissions and any civil works

Unknown

Unknown

Unknown

C03

Appliances and spares

One charge per site or device, purchased

Unknown

Unknown

Unknown

C04

Licences

Charge per licence or site, per month

Unknown

Unknown

Unknown

C05

Primary access circuits

Charge per circuit, per month, with bandwidth, site and contractual availability noted

Unknown

Unknown

Unknown

C06

Backup access circuits

Charge per backup circuit, per month

Unknown

Unknown

Unknown

C07

Managed operations

Charge per project or site, per month, covering monitoring, changes, support hours and fault ownership

Unknown

Unknown

Unknown

C08

Migration and installation

Charge per wave or per site, split into standard installation, exceptional works and rollback effort

Unknown

Unknown

Unknown

C09

Dual running

Incremental monthly charge for each overlapping service, for the actual overlap period only

Unknown

Unknown

Unknown

C10

Incumbent exit charges

One charge per incumbent contract

Unknown

Unknown

Unknown

C11

Training and council staff time

Hours or days of training and staff time, with cash spend and internal opportunity cost labelled separately

Unknown

Unknown

Unknown

C12

Power LAN and wireless dependencies

One charge per affected site, limited to work the refresh needs

Unknown

Unknown

Unknown

C13

Ongoing support renewals

Annual charge per project or device

Unknown

Unknown

Unknown

C14

Reorganisation or estate changes

Charge per change, such as adding, removing, assigning or separating a site

Unknown

Unknown

Unknown

C15

End of term exit assistance

One charge per project for exports, transition and access removal

Unknown

Unknown

Unknown

C16

Contingency

A percentage or amount applied to a defined eligible subtotal

Unknown

Unknown

Unknown

Priced subtotal

Not available. No lines are priced.

This schedule contains unpriced items. Review the missing rates before using a complete project total.

Proposed milestones are the 12 dependency-led steps in section M11. In this scenario the contract expiry is confirmed but its date and the notice period are for the council to enter, so every duration and target date shows Council enters and the plan flags the notice period as unconfirmed.

Illustrative council scenario. Carrying the plan into the RFP builder

  • Copy the brief above into the project summary. Keep the five open items with their owners as notes.
  • Select the 12 questions and the two proposed additions, labelling each as early engagement or priced RFP.
  • Attach the cost schedule as the response format and keep the restricted-service scope, site list and topology as restricted attachments held by the council.
  • Review with service owners, finance, the security lead, the DPO and procurement before anything is issued.

Changed-input examples. Illustrative council scenarios, not real customers

Changed input A. A Scottish council

  • Input changed. Council nation is Scotland (I01).
  • Rule that fires. R02 shows Scottish procurement references and asks the procurement lead to approve the route. The English route example and the Procurement Act notice sequence are hidden from the route-to-market note.
  • Evidence action added. Route approval. Owner, council procurement lead. Effect, no route is described in the brief until confirmed.
  • Milestone changed. MS04 now depends on Scottish arrangements and council approval.
  • Questions. The initial question set doesn't change. Any joint procurement with an English authority is flagged for procurement review, because the Act applies in its entirety to a joint award [S07].

Changed input B. A shared-service authority facing reorganisation

  • Input changed. Shared service or reorganisation dependency is Yes (I12).
  • Rule that fires. R05 adds Q04, Q05 and Q22 to the question set.
  • Evidence actions added. Contract holder and transfer terms (programme lead and legal). Ownership of sites and licences (shared-service lead). Effect, no assumption about which authority signs.
  • Cost schedule changed. C14, reorganisation or estate changes, becomes a required line and shows as missing until priced.
  • Operating model changed. The responsibility matrix gains a filled shared-service governance row, and MS04 and MS05 wait for programme lead sign-off.

Changed input C. A rural council with unknown backup coverage and a continuity constraint

  • Inputs changed. Site access and power constraints describe rural coverage (I22), and an essential depot has no agreed interruption target (I21).
  • Rule that fires. R08 asks the service owner to agree acceptable interruption and a witnessed application test before this site enters a migration wave.
  • Questions changed. Q08 and Q09 move to the top of the set and Q06 and Q07 apply to the essential depot. Q24 requires a difficult-access site in the pilot.
  • Cost schedule changed. C02 surveys and C06 backup circuits become required lines.
  • Evidence action added. Mobile backup performance. Owner, network lead and supplier. Effect, survey and test before accepting design.

Tool copy

Buttons and difficult-state messages

Situation or control

Copy

Primary button

Start my council refresh plan

Supporting button

See what my plan will include

Persistent next-step button

Create my council refresh RFP

Optional button, after draft review

Discuss supplier responses for my council refresh [ROBERT TO CONFIRM destination and workflow]

Draft-only option

Keep my draft private

Contract date unknown

Your contract deadline is unconfirmed. Ask the contract owner for the end date, notice period and any extension options.

PSN answer unknown

Confirm which services still depend on PSN or a restricted partner connection before planning to remove legacy links.

Missing cost rate

This schedule contains unpriced items. Review the missing rates before using a complete project total.

Essential service without a test

Ask the service owner to agree acceptable interruption and a witnessed application test before this site enters a migration wave.

Publication not approved

Keep preparing your private draft. Review the supplier-facing summary and your council's procurement route before requesting responses.

Accessibility rule

Every status is written in words, never by colour alone. No readiness percentage, cyber rating, compliance score, supplier fit score or ready-to-procure badge is shown.

Planner inputs

ID and label

Allowed answers

Explanation

If unknown

I01 Council nation

England, Scotland, Wales, Northern Ireland, Unknown

Choose the nation your council is in. This decides which procurement research we show you, and it never assumes England.

Nation unconfirmed. Ask your procurement lead to confirm your nation and procurement arrangement before you rely on any route notes.

I02 Council type and responsibilities

Council supplied

Say what type of council you are and which services it is responsible for, for example unitary, county, district, Scottish, Welsh or Northern Irish. Don't assume services such as social care, housing or highways. List only what your council delivers.

Responsibilities unconfirmed. Ask which services are in scope with your service owners, so the plan doesn't include services another authority delivers.

I03 Refresh drivers

Renewal, End of support, Resilience, Cloud access, Shared services, Reorganisation, Other, Unknown

Select every reason behind this refresh. Most councils have more than one. Pick Unknown if the objectives haven't been agreed.

Objectives unconfirmed. Agree the reasons for the refresh with your project sponsor. Until then, the plan keeps an objective-confirmation action open.

I04 Project stage

Discovery, Business case, Market engagement, RFP preparation, Procurement underway, Unknown

Tell us where the project is today. We use it to offer you a draft brief or a supplier question set that fits.

Project stage unknown. We'll show the discovery output, which is a safe starting point at any stage.

I05 Sites in scope

0 or greater, blank means unknown

Enter the number of sites in scope, or leave it blank if you don't know. A blank means unknown and is never treated as zero.

Site count unconfirmed. Leave it blank and add a site inventory action to your list. We won't estimate it for you.

I06 Contract end date

Council supplied YYYY-MM-DD

Enter the date your current network contract ends, if you know it, as YYYY-MM-DD.

Your contract deadline is unconfirmed. Ask the contract owner for the end date, notice period and any extension options.

I07 Contract notice date

Council supplied YYYY-MM-DD

Enter the last date you can give notice or commit to an extension. This is often earlier than the end date.

Notice date unknown. Ask the contract owner for the notice terms, and treat the contract as having an earlier unconfirmed deadline.

I08 Existing service and contract scope

Council supplied

Describe what the current contract covers, such as circuits, the overlay, management, LAN and security. Use plain descriptions and keep contract references out.

Contract scope unconfirmed. Ask the incumbent for its service schedule so you can compare like with like.

I09 Device support expiry

Council supplied YYYY-MM-DD

Enter the date your main network devices go out of vendor support, if you know it.

Support end date unknown. Ask for the asset and licence inventory so we can show the hardware risk date.

I10 Critical service dependencies

Revenues and benefits, Housing, Adult services, Childrens services, Contact centre, Libraries, Depots, Other, Unknown

Select the services that depend on this network. Only pick services your council delivers.

Critical services unconfirmed. Ask service owners to confirm what depends on the network before design approval.

I11 PSN or restricted partner dependency

Yes, No, Unknown, Not applicable

Say whether any service still relies on PSN or a restricted partner connection. PSN isn't a circuit type, so answer for services and not for links.

Confirm which services still depend on PSN or a restricted partner connection before planning to remove legacy links.

I12 Shared service or reorganisation dependency

Yes, No, Unknown, Not applicable

Say whether a shared service or a reorganisation affects the network contract, sites or licences. Answer Not applicable if neither applies.

Dependency unconfirmed. Ask the programme lead and legal team whether sites, licences or contracts could transfer or separate.

I13 Telecare alarm or building system dependency

Yes, No, Unknown, Not applicable

Say whether telecare alarms or building systems use the network or rely on analogue lines. Answer Not applicable if your council has none.

Dependency unconfirmed. Ask the relevant service owner to assess alarms and building systems before any affected site is cut over.

I14 Preferred operating model

Council managed, Co managed, Fully managed, Undecided

Choose the model you'd prefer to run after migration. Undecided is a valid answer, and we'll show you how the three compare.

Operating model undecided. We'll add comparison questions so suppliers respond to the same responsibility table.

I15 Available project budget GBP

0 or greater, blank means unknown

Enter the confirmed project budget in pounds, or leave it blank if there isn't one yet. Never enter a typical or estimated figure here.

Budget unconfirmed. Keep it blank. The cost schedule will show a priced subtotal and won't pretend to be a complete total.

I16 Evaluation term months

Positive integer, council supplied

Enter the term in months you want proposals compared over, so every response covers the same period.

Term not set. Without an equal term, no whole-term total or comparison is shown.

I17 Funding and VAT basis

Council finance supplied

Enter how the project is funded and the VAT basis your finance team will use. Finance decides VAT recovery and accounting treatment.

Funding and VAT basis unconfirmed. Ask your finance lead before cost figures are used in a business case.

I18 Procurement arrangement and route

Council procurement supplied

Record the procurement arrangement, framework and lot your procurement lead has agreed, if any. This is a record of their decision and not a legal determination.

Route unconfirmed. Procurement review is needed before any route is described in your brief.

I19 Council blackout dates

Council supplied

Enter dates your council wants protected, such as payment runs, billing, elections, duty arrangements or committee periods. Enter only what your service owners have agreed.

Blackout dates unconfirmed. Ask each service owner which periods they protect before the migration plan is drafted.

I20 Site service tier

Council defined essential, Standard, Low impact, Unknown

Classify the site as Council defined essential, Standard or Low impact. The service owner decides, and the class sets how heavily we test failure at the site.

Site tier unknown. Ask the service owner to classify the site before it enters a migration wave.

I21 Council maximum acceptable interruption minutes

0 or greater, council supplied

Enter the longest interruption in minutes the service can accept. This is your council's decision, not a supplier's service level.

Ask the service owner to agree acceptable interruption and a witnessed application test before this site enters a migration wave.

I22 Site access and power constraints

Council supplied

Describe access, power or permission issues, such as rural coverage, listed buildings, wayleaves or limited backup power. Keep exact addresses out.

Constraints unconfirmed. Add a survey action for the site before design is agreed.

I23 Cost line unit rate GBP

0 or greater, blank means unknown

Enter a unit rate in pounds that your council has approved or a supplier has quoted. Leave it blank if you don't have one.

This schedule contains unpriced items. Review the missing rates before using a complete project total.

I24 Cost line rate evidence

Quote reference date scope and VAT basis

Record the quote reference, date, scope, billing basis, term, inclusions, exclusions and VAT basis for the rate.

Evidence missing. The rate is labelled an unverified assumption until someone reviews it.

I25 Authority to seek responses

Not requested, Pending review, Approved by council

Say whether your council has authorised a request for supplier responses. Preparing a draft doesn't need this.

Keep preparing your private draft. Review the supplier-facing summary and your council's procurement route before requesting responses.

I26 Supplier-facing summary approval

Not prepared, Under review, Approved

Say whether the exact supplier-facing summary has been prepared and approved. Nothing is released until it is Approved.

Keep preparing your private draft. Review the supplier-facing summary and your council's procurement route before requesting responses.

Decision rule messages

Rule

Trigger

Message

Do not infer

R01

Nation is unknown

Your nation is unconfirmed. Ask your council procurement lead to confirm your nation and procurement arrangement. No route is suggested until they do.

Do not suggest a final route.

R02

Nation is Scotland

You've selected Scotland, so we're showing Scottish procurement references. Ask your procurement lead to confirm the route your council approves.

Do not default to the Procurement Act route for English councils.

R03

Nation is Wales or Northern Ireland

You've selected Wales or Northern Ireland, so we're showing the review instruction for your nation. Ask your procurement lead to confirm applicable rules, because an English notice sequence may not apply.

No automatic English notice sequence.

R04

PSN dependency is Yes or Unknown

Confirm which services still depend on PSN or a restricted partner connection before planning to remove legacy links. Question Q03 has been added to your set.

Do not recommend retiring that connection.

R05

Shared-service or reorganisation dependency is Yes or Unknown

A shared service or reorganisation may affect this contract. Questions on ownership, transfer, separation and contract change have been added. Ask your programme lead and procurement team to review them.

No assumed whole-UK reorganisation requirement.

R06

Telecare dependency is Yes or Unknown

Telecare or building systems may depend on this network. Ask the device owner for a dependency assessment before any affected site is cut over. A network change doesn't make an analogue device safe.

No assurance that SD-WAN fixes analogue device risks.

R07

Contract or notice deadline is missing

Your contract deadline is unconfirmed. Ask the contract owner for the end date, notice period and any extension options.

No promised migration completion date.

R08

An essential-service site has no acceptable interruption or acceptance test

Ask the service owner to agree acceptable interruption and a witnessed application test before this site enters a migration wave.

No ready-to-issue claim.

R09

A cost quantity rate term or required line is missing

This schedule contains unpriced items. Review the missing rates before using a complete project total.

No complete budget total or savings percentage.

R10

Council has not approved supplier-facing summary

Keep preparing your private draft. Review the supplier-facing summary and your council's procurement route before requesting responses.

Do not publish or approach suppliers.

R11

Evidence is search-only missing or out of date

Internal editorial rule, not shown to users. Keep this item as a research lead and confirm it against the full page before using any detail from it.

Exclude from published factual claims and supplier scoring.

R12

User has not confirmed an operating model

You haven't confirmed an operating model. We've added responsibility comparison questions so every bidder answers in the same table.

No inferred fully managed preference.

Supplier question pack

Ref and area

Supplier question

Evidence requested

Council reason

Applies when

Use

Q01 Estate

Confirm coverage and delivery dependencies for each council site without substituting assumed access availability.

Site-by-site coverage and survey exceptions.

Rural depots and civic buildings can have different access constraints.

All council refresh projects. Site list required.

Early market engagement and priced RFP

Q02 Continuity

Explain how revenues and benefits applications and agreed out-of-hours duty services will continue during each migration wave.

Application dependency map and service-owner sign-off plan.

Office connectivity alone does not prove resident-service continuity.

All council refresh projects. The duty-service element applies only where the council runs out-of-hours duty services.

Early market engagement and priced RFP

Q03 Dependencies

Identify retained PSN and partner connections and how they will coexist with the proposed design.

Connectivity dependencies and owner-approved transition plan.

Do not remove a required restricted-service path.

When PSN or restricted partner dependency is Yes or Unknown (I11).

Early market engagement and priced RFP

Q04 Shared services

Explain responsibility boundaries across participating councils and how permissions and reporting remain separate.

Responsibility matrix and administration model.

Shared infrastructure must preserve each council's accountability.

When shared service is Yes or Unknown (I12).

Early market engagement and priced RFP

Q05 Reorganisation

Explain how sites licences data access and contracts can transfer or separate during the stated reorganisation.

Transition assumptions transfer restrictions and charges.

A long-term service may outlast the present authority structure.

When reorganisation is Yes or Unknown (I12). Do not apply to councils not affected.

Early market engagement and priced RFP

Q06 Resilience

Demonstrate physical diversity for the proposed primary and backup links at each essential site.

Route and exchange information subject to controlled disclosure.

Two retail suppliers may share a failure domain.

Sites classed as council defined essential (I20).

Early market engagement and priced RFP

Q07 Resilience

Propose and witness a circuit failure test against the council's stated maximum service interruption.

Test method application probes and pass fail results.

Failover must preserve the named council service.

Sites classed as council defined essential, with an interruption target entered (I21).

Priced RFP

Q08 Resilience

Describe backup power capacity maintenance and recovery for the specified sites.

Power dependencies runtime basis and test schedule.

Mobile backup cannot help when site equipment has no power.

Where sites have mobile backup, rural or difficult access, or limited power.

Early market engagement and priced RFP

Q09 Rural access

Validate mobile backup availability and performance at rural depots or other difficult sites.

Site survey and tests under expected load.

Coverage maps do not establish usable backup service.

Where rural or difficult-access sites are in scope (I22).

Early market engagement and priced RFP

Q10 Segmentation

Show how council staff library public access contractors CCTV and building systems are isolated where in scope.

Policy design and segmentation acceptance tests.

Public access and operational systems have different trust boundaries.

Where libraries, public access, CCTV or building systems are in scope.

Early market engagement and priced RFP

Q11 Applications

Confirm performance and routing for the council's named Azure, Microsoft 365 and retained hosted applications.

Application test results under normal and degraded connectivity.

Supplier dashboard health does not establish usable council applications.

Where Azure, Microsoft 365 or retained hosted applications are in scope.

Priced RFP

Q12 Identity

Explain access administration and emergency access arrangements for council and supplier staff.

Role model MFA access reviews and break glass procedure.

Council retains accountable control of privileged access.

All council refresh projects.

Early market engagement and priced RFP

Q13 Logging

State what user and network data is collected where it is processed retention and supplier access.

Data-flow summary retention controls and processor information.

Security lead and DPO need evidence for the actual processing.

All council refresh projects.

Early market engagement and priced RFP

Q14 Assurance

Provide the evidence requested by our security team for the council CAF improvement actions in scope.

Control evidence linked to council actions and evidence owners.

A product purchase does not deliver organisational assurance.

Where the council has CAF improvement actions that this project could evidence.

Priced RFP

Q15 Operations

State who owns a fault spanning circuit appliance cloud policy and third-party application.

RACI incident workflow and escalation example.

Avoid incidents passed between contracted parties.

Co managed or fully managed models (I14), and Undecided.

Early market engagement and priced RFP

Q16 Operations

Describe monitoring and support during the council's specified out-of-hours service periods.

Support coverage and escalation commitments with exclusions.

Duty services may run outside office hours.

Where the council runs out-of-hours duty services.

Early market engagement and priced RFP

Q17 Changes

State which changes the council can make and which are charged or subject to supplier approval.

Change catalogue permissions service windows and charges.

A co-managed offer must preserve the council's needed authority.

Co managed or fully managed models (I14), and Undecided.

Early market engagement and priced RFP

Q18 Service levels

Separate incident response restoration and resolution commitments by priority and service boundary.

Contractual service schedule with measurement and exclusions.

Fast acknowledgement does not establish fast recovery.

All council refresh projects.

Priced RFP

Q19 Service levels

Explain credit calculations caps claim deadlines and planned maintenance exclusions.

Applicable contract wording and example claim calculation.

Marketing uptime percentages are not a complete contractual comparison.

Priced RFP stage only.

Priced RFP

Q20 Costs

Price the same site list, term and service responsibilities using the council's cost schedule.

Itemised one-off recurring and optional charges in GBP with VAT basis.

Enables finance to compare equal scope.

Priced RFP stage only. Requires the council's cost schedule.

Priced RFP

Q21 Costs

State overlap charges termination charges installation dependencies and delayed-delivery costs.

Priced transition schedule with assumptions.

Dual running can erase an apparent annual saving.

Priced RFP stage, and any early engagement where an incumbent is being replaced.

Priced RFP

Q22 Costs

State indexation review dates minimum commitments and costs to add remove or transfer sites.

Commercial formula worked example and change charges.

Estate consolidation and reorganisation can alter costs.

Priced RFP stage. Priority where estate consolidation or reorganisation is expected.

Priced RFP

Q23 Delivery

Provide a dependency-led plan around the council's listed elections, payments and change restrictions.

Milestones dependencies owner and lead-time assumptions.

Protect council-specific service windows.

All council refresh projects. Uses the council's blackout dates (I19).

Early market engagement and priced RFP

Q24 Pilot

Propose a representative pilot including an essential-service site and a difficult access site where appropriate.

Pilot selection rationale and acceptance evidence.

A straightforward office pilot can miss the highest risks.

All council refresh projects. Difficult-access site only where one exists.

Early market engagement and priced RFP

Q25 Rollback

State rollback triggers responsible officers and the last reversible point for each cutover.

Runbook and witnessed recovery test.

Council service owners must know when to stop a change.

All council refresh projects.

Priced RFP

Q26 Exit

Describe configuration and log exports licence ownership access revocation and transition assistance at exit.

Exit plan format and priced assistance.

The next refresh must not depend on an inaccessible management tenant.

All council refresh projects.

Early market engagement and priced RFP

Q27 Evidence

Provide comparable council references distinguishing your contracted scope from partner-delivered work.

Named references dates estate scope and permission for checks.

A generic public-sector logo does not establish relevant delivery.

Priced RFP stage only.

Priced RFP

Q28 Subcontractors

Identify who supplies and supports the access network and any management subcontractors.

Supply chain roles escalation and change notification commitments.

Council needs a clear chain of accountability.

Co managed or fully managed models (I14), and any incumbent with subcontractors.

Early market engagement and priced RFP

Q29 Training

Describe handover training, documentation and the council's ongoing staffing responsibilities.

Training plan operating documentation and role expectations.

A small council team must be able to operate the agreed model.

Co managed or fully managed models (I14), and Undecided.

Early market engagement and priced RFP

Q30 Telecare

Identify any affected telecare alarms and building systems and your scope of testing alongside their service owner.

Separate dependency assessment and device-owner test approval.

Network migration does not prove device compatibility or safety.

When telecare or building systems are Yes or Unknown (I13).

Early market engagement and priced RFP

Q31 Accessibility

Describe accessibility of the management portal reports and support routes used by council staff.

Accessibility evidence and known limitations.

Council users need usable interfaces and alternative formats.

All council refresh projects where staff use a supplier portal.

Early market engagement and priced RFP

Q32 Sustainability

State equipment reuse secure disposal energy and site-visit assumptions relevant to this project.

Project-specific evidence and priced options.

Council sustainability assessment should use actual delivery assumptions.

Where the council's sustainability assessment will use this project's data.

Priced RFP

Cost schedule appendix

Amounts are blank in every category because no defensible published rate exists. A blank means unknown and is never treated as zero. A rate needs a date, scope, billing basis, term, inclusions, exclusions and VAT basis.

Line

Category and basis

Unit definition

Included

Question for finance

C01

Discovery and design (one_off)

One project-level charge, with council and supplier effort recorded as separate lines.

Include council and supplier effort separately.

Which of this effort is bought from suppliers and which is internal staff time?

C02

Site surveys and permissions (one_off)

One charge per affected site, including permissions and any civil works.

Include rural access listed buildings wayleaves and civil works where relevant.

Which sites have access or permission constraints, and who funds exceptional works?

C03

Appliances and spares (one_off)

One charge per site or device, purchased. Rental belongs in a recurring line.

Separate purchases from rental included in recurring charges.

Will the council buy or rent equipment, and how will it be capitalised?

C04

Licences (recurring_monthly)

Charge per licence or site, per month.

Check security and support inclusions to avoid double counting.

Does the licence include security and support, so nothing is counted twice?

C05

Primary access circuits (recurring_monthly)

Charge per circuit, per month, with bandwidth, site and contractual availability noted.

Record bandwidth site and contractual availability.

Are circuits billed monthly, quarterly or annually, and what is the minimum term?

C06

Backup access circuits (recurring_monthly)

Charge per backup circuit, per month.

Do not imply shared infrastructure is physically diverse.

Is each backup circuit physically diverse from its primary, and is that evidenced?

C07

Managed operations (recurring_monthly)

Charge per project or site, per month, covering monitoring, changes, support hours and fault ownership.

Align monitoring changes support hours and fault ownership.

Which operating model does this charge assume?

C08

Migration and installation (one_off)

Charge per wave or per site, split into standard installation, exceptional works and rollback effort.

Separate standard installation exceptional works and rollback effort.

Is rollback effort included in the quoted price?

C09

Dual running (overlap_monthly)

Incremental monthly charge for each overlapping service, for the actual overlap period only.

Use actual overlap period and only incremental costs not counted elsewhere.

What overlap period has the council actually assumed?

C10

Incumbent exit charges (one_off)

One charge per incumbent contract.

Do not add full old-service cost again if already in dual running.

Is any exit charge already included in dual running?

C11

Training and council staff time (one_off)

Hours or days of training and staff time, with cash spend and internal opportunity cost labelled separately.

Keep cash spend and internal opportunity cost separately labelled.

Does finance want internal staff time in the schedule or only in the business case?

C12

Power LAN and wireless dependencies (one_off)

One charge per affected site, limited to work the refresh needs.

Only include work required by the council refresh scope.

Who funds LAN, power or wireless work that benefits other projects?

C13

Ongoing support renewals (recurring_annual)

Annual charge per project or device. Check included licence support first.

Check included licence support before adding another charge.

Is support included in the licence charge, so nothing is counted twice?

C14

Reorganisation or estate changes (optional)

Charge per change, such as adding, removing, assigning or separating a site.

State additions removals assignment and separation assumptions.

Which estate changes does the council expect during the term?

C15

End of term exit assistance (one_off)

One charge per project for exports, transition and access removal.

Price exports transition and access removal.

Is end-of-term exit assistance priced now or at exit?

C16

Contingency (allowance)

A percentage or amount applied to a defined eligible subtotal.

Council finance chooses basis percentage and exclusions.

What percentage, basis and exclusions does finance want?

Source references

Sources were re-opened on 21 October 2026 unless a note says otherwise. Sources not cited in the page copy are listed so the workbook and manuscript can be cross-checked.

ID

Title

Publisher

Published

Review basis

Link

S01

Council network managed services procurement

Royal Borough of Greenwich

1 October 2026

Full page reviewed

https://greenwich.moderngov.co.uk/mgDecisionDetails.aspx?IId=7504&Opt=1

S02

WAN infrastructure modernisation decision

London Borough of Enfield

16 April 2026

Full page reviewed

https://enfield.moderngov.co.uk/ieDecisionDetails.aspx?Id=517

S03

Provision of LAN and Wireless Networks

Contracts Finder and South Oxfordshire District Council

20 December 2024

Full page reviewed

https://www.contractsfinder.service.gov.uk/Notice/430ff243-60db-4b5b-8b02-0ec745ae1399

S04

Gigabit Phase 3 WAN Solution decision

Adur and Worthing Councils

Search extract only

https://democracy.adur-worthing.gov.uk/ieDecisionDetails.aspx?ID=1459

S05

SD WAN Solution notice 081392 2025

Find a Tender and East Riding of Yorkshire Council

Search extract only

https://www.find-tender.service.gov.uk/Notice/081392-2025/PDF

S06

Network Services 3 RM6116

Government Commercial Agency

Full page reviewed

https://www.gca.gov.uk/agreements/RM6116

S07

Devolved Contracting Authorities guidance

Cabinet Office

15 April 2026

Full page reviewed

https://www.gov.uk/government/publications/procurement-act-2023-guidance-documents-plan-phase/guidance-devolved-contracting-authorities-html

S08

Preliminary Market Engagement guidance

Cabinet Office

13 July 2026

Full page reviewed

https://www.gov.uk/government/publications/procurement-act-2023-guidance-documents-define-phase/guidance-preliminary-market-engagement-html

S09

Procurement Act guidance collection

Welsh Government

Full page reviewed

https://www.gov.wales/procurement-act-2023-guidance-documents

S10

Scottish procurement policy handbook

Scottish Government

Search result reviewed

https://www.gov.scot/publications/scottish-procurement-policy-handbook/

S11

Public Services Network compliance

Cabinet Office

Full page reviewed

https://www.gov.uk/guidance/public-services-network-psn-compliance

S12

CAF for local government

MHCLG Local Digital

Full page reviewed

https://www.localdigital.gov.uk/cyber/cyber-assessment-framework-for-local-government/

S13

Local government CAF plans for 2026

MHCLG Local Digital

14 January 2026

Full page reviewed

https://www.localdigital.gov.uk/news/our-2026-plans-to-strengthen-cyber-resilience-in-local-government-through-the-cyber-assessment-framework/

S14

Reorganisation cyber digital data and technology considerations

Local Government Association

6 May 2025

Full page reviewed

https://www.local.gov.uk/publications/local-government-reorganisation-cyber-digital-data-and-technology-considerations

S15

When do we need to do a DPIA

Information Commissioners Office

Full page reviewed

https://ico.org.uk/for-organisations/uk-gdpr-guidance-and-resources/accountability-and-governance/data-protection-impact-assessments-dpias/when-do-we-need-to-do-a-dpia/

S16

Moving landlines to digital technologies

DSIT

28 May 2025

Full page reviewed

https://www.gov.uk/guidance/moving-landlines-to-digital-technologies

S17

Telecare and digital switchover guidance for housing providers

DHSC

8 October 2026

Full page reviewed

https://www.gov.uk/government/publications/telecare-and-the-digital-switchover-guidance-for-housing-providers

S18 (not cited)

Public sector website accessibility requirements

Government Digital Service

Full page reviewed

https://www.gov.uk/guidance/accessibility-requirements-for-public-sector-websites-and-apps

S19

Current Netify RFP builder

Netify

Full page reviewed

https://netify.co.uk/sase-sd-wan-rfp-builder/

S20 (not cited)

Netify Market Record

Netify

Full page reviewed

https://netify.co.uk/sase/opportunities/board/

S21 (not cited)

How the Netify marketplace works

Netify

Full page reviewed

https://netify.co.uk/sase/how-it-works/

S22

UK public sector provider comparison

Netify

Full page reviewed

https://netify.co.uk/sase/best/sd-wan-sase-providers-for-uk-public-sector/

S23

SASE and SD-WAN contract terms

Netify

Inventory reference only

https://netify.co.uk/insights/sase-and-sd-wan-contract-terms-explained-deployment-timelines-slas-licensing-models-and-hidden-costs/

S24

Wide Area Network (WAN) Connectivity tender notice 082060-2025

East Riding of Yorkshire Council (Find a Tender)

11 December 2025

Full page reviewed

https://www.find-tender.service.gov.uk/Notice/082060-2025

S25 (not cited)

Supply and maintenance of an SD WAN Solution planned procurement notice 069198-2025

East Riding of Yorkshire Council (Find a Tender)

29 October 2025

Full page reviewed

https://www.find-tender.service.gov.uk/Notice/069198-2025

S26

Software Defined Wide Area Network (SD Wan) Connectivity Procurement, Council report C/6/25-26

Cheshire East Council

14 May 2025

Full page reviewed

https://moderngov.cheshireeast.gov.uk/documents/s124405/Report.pdf

S27

Northern Ireland Councils Network Services contract notice 009419-2022

Armagh City, Banbridge and Craigavon Borough Council and nine partner councils (Find a Tender)

7 April 2022

Full page reviewed

https://www.find-tender.service.gov.uk/Notice/009419-2022

S28 (not cited)

Northern Ireland Councils Network Services change notice 014671-2022

Armagh City, Banbridge and Craigavon Borough Council and nine partner councils (Find a Tender)

25 May 2022

Full page reviewed

https://www.find-tender.service.gov.uk/Notice/014671-2022

S29

The Highland Council and BT sign multi-year network services agreement

The Highland Council

24 October 2023

Full page reviewed

https://www.highland.gov.uk/news/article/15644/the-highland-council-and-bt-sign-multi-year-network-services-agreement

S30 (not cited)

Public Sector Broadband Aggregation (PSBA) 3 preliminary market engagement notice

Welsh Government (Find a Tender)

11 June 2025

Full page reviewed

https://www.find-tender.service.gov.uk/Notice/032577-2025

S31 (not cited)

eir evo signs 7m contract with NI local councils

fibreprovider.net (trade press reporting a supplier announcement)

10 January 2023

Full page reviewed

https://fibreprovider.net/news/eir-evo-signs-ps7m-contract-ni-local-councils

S32

Software-Defined Wide Area Network (SD WAN) contract award notice 047572-2025

Cheshire East Council (Find a Tender)

11 August 2025

Full page reviewed

https://www.find-tender.service.gov.uk/Notice/047572-2025

S33 (not cited)

Core Infrastructure and Wired/Wireless Networking dynamic purchasing system notice 024646-2024

Caerphilly County Borough Council with Welsh Government and the 22 Welsh local authorities (Find a Tender)

6 August 2024

Full page reviewed

https://www.find-tender.service.gov.uk/Notice/024646-2024

S34 (not cited)

Public Sector Broadband Aggregation (PSBA) 3 preliminary market engagement notice 031685-2025 (earlier version)

Welsh Government (Find a Tender)

11 June 2025

Full page reviewed

https://www.find-tender.service.gov.uk/Notice/031685-2025

S35 (not cited)

Commercial, contract and supplier considerations during reorganisation

Local Digital

15 October 2026

Full page reviewed

https://www.localdigital.gov.uk/resources/commercial-contract-and-supplier-considerations-during-reorganisation/

S36

SD WAN Solution contract award notice 056210-2026

East Riding of Yorkshire Council (Find a Tender)

15 June 2026

Full page reviewed

https://www.find-tender.service.gov.uk/Notice/056210-2026

S37

Wide Area Network (WAN) Connectivity contract award notice 056223-2026

East Riding of Yorkshire Council (Find a Tender)

15 June 2026

Full page reviewed

https://www.find-tender.service.gov.uk/Notice/056223-2026

Outstanding questions

Ref

Owner

Area

Question

Status

OQ01

Robert

Product

Which parts of the planner (inputs, live outputs, printable outputs) will exist at launch? The copy is written as a step-by-step planner with live outputs and printable versions.

Open

OQ02

Robert

Product

What exactly carries forward from the planner into the RFP builder? The page says the builder has no council-specific pack or confirmed prefill. M13 uses a copy-and-paste fallback and does not promise prefill.

Open

OQ03

Robert

Product

What is the real destination and workflow for the optional supplier-response step, and is the button wording Discuss supplier responses for my council refresh acceptable? The copy is marked [ROBERT TO CONFIRM] and should not go live until confirmed.

Open

OQ04

Robert

Conflict

On 21 Oct 2026 the live Netify board page is headed as a live marketplace, says 18 opportunities are genuinely open and lists recently closed and awarded notices. The brief says it presents a Market Record with no approved outcome records. The manuscript makes no claim about the board either way.

Open

OQ05

Robert

Conflict

The how-it-works page describes a private project with work-email sign-in and does not mention downloads, whereas the RFP builder says no account or publication is needed to download a draft. Copy follows the RFP builder only.

Open

OQ06

Robert

Disclosure

Confirm Netify's approved supplier fee disclosure wording. M14 uses the RFP builder line Suppliers pay Netify when an introduction leads to business, which does not affect how providers are ordered.

Open

OQ07

Robert

Question bank

Map Q01 to Q32 to the governed bank (T10). No live question IDs were invented. Harry proposes applicability conditions, early engagement or priced RFP labels and response formats, and tightened wording on 10 rows (apostrophes only).

Open

OQ08

Robert

Publication

Confirm the final public title and address (/insights/council-sd-wan-refresh/). The M01 heading in Page modules was changed from SD WAN to SD-WAN for consistency with the H1.

Open

OQ09

Harry

Evidence

Enfield's own decision page could not be re-opened (the council site blocks automated fetching). Manuscript wording is limited to the brief's description. Open it in a browser and confirm the decision date (workbook shows 16 April for the source and 17 April for the case), decision maker, term and route. A third-party mirror of the record was glanced at but is not used or cited.

Closed. Unable to source. Enfield's decision page blocks automated access. Wording stays at the brief's description and the case is marked for a manual check by the council or a browser review before publication

OQ10

Harry

Evidence

The listed Network Services 3 URL is blocked to automated fetching and redirects to https://www.gca.gov.uk/agreements/RM6116, where the content was verified. Consider replacing the source URL with the gca.gov.uk address.

Open

OQ11

Harry

Evidence gap

Reviewed research found no Welsh council WAN or SD-WAN decision or award. Two Welsh items were added as context only. Caerphilly's joint dynamic purchasing system notice (S33) covers all 22 authorities for broad networking and Welsh Government's PSBA 3 planning notice (S34) is an estimate. The research also reports that Bridgend's schools strategy says its schools use PSBA, but that is not a procurement record and we have not opened it. Result, 7 verified council records across England, Scotland and Northern Ireland, and a Wales gap that still needs a council award or call-off record.

Closed. Unable to source a Welsh council WAN or SD-WAN award or decision. Wales is recorded as an evidence gap

OQ12

Harry

Evidence

For the ten Northern Ireland councils no council award notice has been found on Find a Tender (the 2022 contract notice and change notice link to nothing newer). The award is reported only in supplier-attributed trade press (S31), so CASE07 stays at contract notice stage. Check eTendersNI directly.

Closed. Unable to source a council award notice. CASE07 stays at contract notice stage and no award claim is made

OQ13

Harry

Evidence

The Adur and Worthing decision page, rechecked on 21 Oct 2026, still shows status For Determination with call-in, effective from 7 Oct 2026. It doesn't say whether the call-in period passed, so implementation and signature are not claimed. Confirm with the council. The page does not describe a shared-service arrangement, so it is not used as the shared-service case.

Closed. Unable to source confirmation of the call-in outcome or signature. The page still shows For Determination, so no implementation claim is made

OQ14

Harry

Evidence

East Riding's award notices are verified (S36, S37), with the supplier and value for each. The tender notice 081392-2025 still shows two deadlines, 23 Jan 2026 in the structured field and 9 Jan 2026 in the procedure text, and the notice gives no reason for the edit, so both are reported. Delivery is not verified.

Closed. Award notices verified (S36, S37). Deadline conflict in the tender notice is reported as shown, with no reason given

OQ15

Harry

Evidence

Cheshire East's award notice 047572-2025 (S32) is verified, Virgin Media Ltd, GBP900,408 excluding VAT, concluded 7 Aug 2025. Still unverified, whether the Capita contract was extended beyond 3 Feb 2026, the matching Cheshire West and Chester outcome and delivery.

Closed. Award verified (S32). Unable to source a Capita extension decision, the Cheshire West and Chester outcome or delivery, so none is claimed

OQ16

Harry

Evidence

The research read the LGA PDF only to printed page 27 and did not reach the novation passage. Contract transfer and novation points are cited to the separate Local Digital page (S35), not the LGA report. Open the full PDF before attributing network-specific points to it.

Closed. Unable to source the novation passage in the LGA PDF. Transfer and novation points are cited to the Local Digital page (S35)

OQ17

Harry

Recheck

Date-check immediately before handover. Network Services 3 lot dates, PSN page, CAF wording, telecare and landline guidance, the Welsh guidance page (it shows an update date of Aug 2025 but lists some guidance titles dated Sept 2026) and the later PSBA3 notice version dated 16 June 2026.

Open. Next review recommended 1 month before publication

OQ18

Finance and Harry

Cost

No defensible published unit rate was found. Published figures are single contract values (Adur and Worthing decision, Cheshire East and East Riding award notices), a procurement estimate (Northern Ireland councils), a broad service envelope (Greenwich) and a national aggregation estimate (PSBA3). All rate fields are left blank.

Closed. No action unless a quote is supplied

OQ19

Robert

Product

Does the planner store answers, keep them in-session only, or save to a project? M01 says only that the plan is a private draft and that nothing is published or sent to suppliers without approval.

Open

OQ20

Robert

Structure

Where should the Illustrative council scenario sit? It is currently written as a separate section reached from the See what my plan will include button.

Open

OQ21

Robert

Accessibility

The planner copy follows the no colour-only warnings rule and avoids forced time limits. Netify is not a public body, so no accessibility compliance claim is made. Confirm the build meets WCAG 2.2 AA as an aim.

Open

OQ22

Harry

Citations

The brief lists S02 against M11 and S20 and S21 against M14. No sentence in the copy relies on them. Propose removing those three links or giving them a supporting claim.

Open

OQ23

Robert

Scenario

Confirm the optional scope-sensitive additions Q08 and Q11 for the worked example, and whether the changed-input examples should appear on the page or only in the manuscript.

Open

03 / COMPLETE SOURCE WORKBOOK

Every sheet. Every record.

All 17 original sheets are retained below and in Neon. Assignment, delivery and open-question notes are source material, not operating instructions or supplier commitments. Empty amounts remain unknown.

Lists / 40 records
field_groupallowed_valuemeaning
council_nationEnglandNation is not sufficient to determine every procurement arrangement.
council_nationScotlandNation is not sufficient to determine every procurement arrangement.
council_nationWalesNation is not sufficient to determine every procurement arrangement.
council_nationNorthern IrelandNation is not sufficient to determine every procurement arrangement.
council_nationUnknownNation is not sufficient to determine every procurement arrangement.
evidence_review_basisFull page reviewedOnly full verified relevant evidence can support a published factual claim.
evidence_review_basisSearch extract onlyOnly full verified relevant evidence can support a published factual claim.
evidence_review_basisSearch result reviewedOnly full verified relevant evidence can support a published factual claim.
evidence_review_basisInventory reference onlyOnly full verified relevant evidence can support a published factual claim.
fact_statusVerified public factKeep facts recommendations and examples distinguishable.
fact_statusEditorial recommendationKeep facts recommendations and examples distinguishable.
fact_statusCouncil suppliedKeep facts recommendations and examples distinguishable.
fact_statusSupplier quotedKeep facts recommendations and examples distinguishable.
fact_statusIllustrative exampleKeep facts recommendations and examples distinguishable.
fact_statusUnknownKeep facts recommendations and examples distinguishable.
answer_stateKnownUnknown and not applicable are different states; zero is a known numeric value.
answer_stateUnknownUnknown and not applicable are different states; zero is a known numeric value.
answer_stateNot applicableUnknown and not applicable are different states; zero is a known numeric value.
author_statusBrief suppliedApproval belongs to the relevant editor or council owner.
author_statusIn progressApproval belongs to the relevant editor or council owner.
author_statusReady for editorial reviewApproval belongs to the relevant editor or council owner.
author_statusRequires verificationApproval belongs to the relevant editor or council owner.
author_statusApprovedApproval belongs to the relevant editor or council owner.
cost_basisone_offDo not sum unlike billing periods without conversion.
cost_basisrecurring_monthlyDo not sum unlike billing periods without conversion.
cost_basisrecurring_annualDo not sum unlike billing periods without conversion.
cost_basisoverlap_monthlyDo not sum unlike billing periods without conversion.
cost_basisoptionalDo not sum unlike billing periods without conversion.
cost_basisallowanceDo not sum unlike billing periods without conversion.
visibilityPublic referencePublish only the approved supplier summary; public source data is separate from live council entries.
visibilityPrivate projectPublish only the approved supplier summary; public source data is separate from live council entries.
visibilityRestricted reviewPublish only the approved supplier summary; public source data is separate from live council entries.
visibilityApproved supplier summaryPublish only the approved supplier summary; public source data is separate from live council entries.
claim_review_statusVerified against full source on 21 Oct 2026Proposed addition. The claim was checked against the full source page.
claim_review_statusEditorial recommendation, not a source claimProposed addition. Netify advice informed by, but not stated in, the source.
claim_review_statusRe-check in browser before publication (primary page could not be re-opened)Proposed addition. Automated retrieval was blocked.
claim_review_statusNot cited in manuscript copy. Research basis onlyProposed addition. Link kept from the brief with no supported sentence.
rfp_stage_useEarly market engagement and priced RFPProposed addition. Suits both stages.
rfp_stage_usePriced RFPProposed addition. Only meaningful when suppliers price responses.
rfp_stage_useEarly market engagementProposed addition. Shapes requirements and asks for no prices.
Sources / 37 records
source_idtitlepublisherurlpublished_datechecked_datereview_basisusable_scope
S01Council network managed services procurementRoyal Borough of Greenwichhttps://greenwich.moderngov.co.uk/mgDecisionDetails.aspx?IId=7504&Opt=12026-10-01T12:00:002026-10-21T12:00:00Full page reviewedDecision approves procurement covering WAN LAN WiFi and firewalls; associated hardware refresh. Estimated GBP16m over maximum 10 years is a broad service envelope, not an SD-WAN price. Recheck 21 Oct 2026. Decision title Procurement of Network Managed Services Contract. Route shown is an Open Procedure under the Procurement Act 2023, initial term 5 years with options to extend for up to 5 more. The WAN/LAN hardware refresh is described as in train rather than procured under this item. The page records an approval, not an award, shows no named supplier or site count, does not name a decision maker and does not state a VAT basis.
S02WAN infrastructure modernisation decisionLondon Borough of Enfieldhttps://enfield.moderngov.co.uk/ieDecisionDetails.aspx?Id=5172026-04-16T12:00:002026-10-20T12:00:00Full page reviewedDecision to award a network refresh addressing legacy architecture and cloud connectivity. No verified price or delivery outcome in the reviewed decision. Recheck 21 Oct 2026. The primary page could not be re-opened because the council site blocks automated fetching, so manuscript wording is limited to the description above. Open it in a browser and confirm decision date (workbook shows 16 and 17 April 2026), decision maker, term and route before publication.
S03Provision of LAN and Wireless NetworksContracts Finder and South Oxfordshire District Councilhttps://www.contractsfinder.service.gov.uk/Notice/430ff243-60db-4b5b-8b02-0ec745ae13992024-12-20T12:00:002026-10-21T12:00:00Full page reviewedJoint South Oxfordshire and Vale of White Horse procurement. LAN wireless and security refresh supports SD-WAN transition. Source GBP0 value is unusable as a cost benchmark. Recheck 21 Oct 2026. Notice closed. Term 10 Feb 2025 to 9 Feb 2030. Open procedure (below threshold). Scope includes switching, Wi-Fi 6E access points, security devices and migration to a Zero-Trust-Network using SD-WAN, with site-to-site VPN into Microsoft Azure for each site. Bidders were asked to price hardware per site, 5-year enterprise licence and support, installation and configuration per site and ongoing annual support. No award is shown.
S04Gigabit Phase 3 WAN Solution decisionAdur and Worthing Councilshttps://democracy.adur-worthing.gov.uk/ieDecisionDetails.aspx?ID=14592026-09-29T12:00:002026-10-21T12:00:00Full page reviewedDecision HofT&D/035/26-27, 29 Sep 2026, effective 7 Oct 2026, Head of Technology & Design. Migrate fibre networking across 22 council sites from current bespoke service arrangements to SD-WAN over the CityFibre network using a commercial ISP. Supplier KHIPU Networks Ltd. GBP129,918.43 plus VAT over 3 years via the SBS DWS2 framework direct award. Stated reasons, cost reduction against current services and renewal of equipment and leased space. Page status shows For Determination, key decision, call-in applies, so confirm implementation before publication. A shared-service arrangement is not described. A single contract value, not a unit rate or per-site benchmark.
S05SD WAN Solution notice 081392 2025Find a Tender and East Riding of Yorkshire Councilhttps://www.find-tender.service.gov.uk/Notice/081392-2025/PDF2025-12-10T12:00:002026-10-21T12:00:00Full page reviewedTender notice UK4, 2025/S 000-081392, East Riding of Yorkshire Council, ref 2502-26, published 10 Dec 2025 (edited). Partner sought to deliver a Cisco-based SD WAN solution. Estimated value GBP3,000,000 excluding VAT, competitive flexible procedure, price 70% and quality 30%. Estimated contract period 1 Jun 2026 to 1 Aug 2031 with the solution live by 1 Apr 2027. Estimated award decision 5 May 2026. No award found. The notice shows two different tender deadlines (9 Jan and 23 Jan 2026). A procurement estimate, not a unit rate.
S06Network Services 3 RM6116Government Commercial Agencyhttps://redirect.webprod.crowncommercial.gov.uk/agreements/RM6116Unknown / not supplied2026-10-21T12:00:00Full page reviewedFramework remains under PCR2015. Lot 1a covers WAN; lot 2a covers LAN. Most lots end 17 July 2027; lots 1c and 1d end 22 May 2027. Eligibility lot scope and route need council procurement confirmation. Recheck 21 Oct 2026 at https://www.gca.gov.uk/agreements/RM6116 because the listed URL is blocked to automated fetching and redirects there. Lot 1a Inter Site Connectivity (Wider Area Network) / Data Access Services. Lot 2a Intra Site Connectivity (Local Area Network) / Local Connectivity Services. Extended by 24 months on 12 Mar 2025. Crown Commercial Service became Government Commercial Agency on 1 Apr 2026. The page lists UK public sector access without addressing Scotland, Wales or Northern Ireland eligibility.
S07Devolved Contracting Authorities guidanceCabinet Officehttps://www.gov.uk/government/publications/procurement-act-2023-guidance-documents-plan-phase/guidance-devolved-contracting-authorities-html2026-04-15T12:00:002026-10-21T12:00:00Full page reviewedNation and arrangement matter. Devolved Scottish authorities are generally excluded from the Act; Welsh and Northern Ireland differences and cross-border arrangements require care. Recheck 21 Oct 2026. Updated 15 April 2026. Devolved Scottish authorities are generally excluded (para 24). Welsh and Northern Ireland authorities are regulated by the Act with some differences (para 16). Cross-border arrangements follow the rules of the authority that set them up.
S08Preliminary Market Engagement guidanceCabinet Officehttps://www.gov.uk/government/publications/procurement-act-2023-guidance-documents-define-phase/guidance-preliminary-market-engagement-html2026-07-13T12:00:002026-10-21T12:00:00Full page reviewedUse engagement to develop requirements without unfair supplier advantage. Council procurement officer determines notices and process.
S09Procurement Act guidance collectionWelsh Governmenthttps://www.gov.wales/procurement-act-2023-guidance-documents2024-08-12T12:00:002026-10-21T12:00:00Full page reviewedUse Welsh guidance and notice sequencing for devolved Welsh authorities rather than copying English route wording. Recheck 21 Oct 2026. Page last updated 15 Aug 2025 but lists some guidance titles dated September 2026, so verify the page and the individual guidance dates before publication.
S10Scottish procurement policy handbookScottish Governmenthttps://www.gov.scot/publications/scottish-procurement-policy-handbook/2024-05-07T12:00:002026-10-21T12:00:00Full page reviewedUse Scottish public procurement rules and council procurement approval. Do not route Scottish councils automatically into an English process. Recheck 21 Oct 2026. Handbook published 7 May 2024. Covers the Procurement Reform (Scotland) Act 2014 and Public Contracts (Scotland) Regulations 2015. States it isn't legal advice and applies to devolved Scottish contracting authorities without naming local authorities specifically.
S11Public Services Network complianceCabinet Officehttps://www.gov.uk/guidance/public-services-network-psn-complianceUnknown / not supplied2026-10-21T12:00:00Full page reviewedPSN-connected organisations have connection and service obligations. Historical guidance is not evidence of a universal closure date; validate live dependencies with the service owner. Recheck 21 Oct 2026. The visible last-updated date on the page is 16 March 2016. It lists connection, service provision and connectivity certificate types and carries no closure or transition date.
S12CAF for local governmentMHCLG Local Digitalhttps://www.localdigital.gov.uk/cyber/cyber-assessment-framework-for-local-government/2025-06-24T12:00:002026-10-21T12:00:00Full page reviewedAssess essential services and critical systems. Page describes voluntary organisational assessment and independent assurance; buying SD-WAN does not confer CAF or PSN compliance. Recheck 21 Oct 2026. Page metadata last modified 24 June 2025. The CAF for local government is described as voluntary and as not replacing PSN.
S13Local government CAF plans for 2026MHCLG Local Digitalhttps://www.localdigital.gov.uk/news/our-2026-plans-to-strengthen-cyber-resilience-in-local-government-through-the-cyber-assessment-framework/2026-01-14T12:00:002026-10-21T12:00:00Full page reviewedJanuary 2026 update supersedes older pilot-only descriptions. Recheck current version and applicability before publication. Recheck 21 Oct 2026. 14 Jan 2026 update. CAF launched Oct 2024, 90 councils had completed an assessment, CAF version 4.0 and a web application are planned. It sets no mandatory requirements.
S14Reorganisation cyber digital data and technology considerationsLocal Government Associationhttps://www.local.gov.uk/publications/local-government-reorganisation-cyber-digital-data-and-technology-considerations2025-05-06T12:00:002026-10-21T12:00:00Full page reviewedResearch covers organisational transition and continuity. Apply reorganisation branch only where relevant; do not imply every UK council is reorganising. Recheck 21 Oct 2026. Only the publication landing page was reviewed, which describes research based on interviews with officers in 17 councils. The linked PDF report wasn't opened, so contract, network and shared-service specifics are not sourced here.
S15When do we need to do a DPIAInformation Commissioners Officehttps://ico.org.uk/for-organisations/uk-gdpr-guidance-and-resources/accountability-and-governance/data-protection-impact-assessments-dpias/when-do-we-need-to-do-a-dpia/2025-10-13T12:00:002026-10-21T12:00:00Full page reviewedDPIA depends on processing likely to create high risk. Ask DPO to assess logs inspection and supplier access. Guidance is flagged under review following Data Use and Access Act changes. Recheck 21 Oct 2026. Page date from metadata.
S16Moving landlines to digital technologiesDSIThttps://www.gov.uk/guidance/moving-landlines-to-digital-technologies2025-05-28T12:00:002026-10-21T12:00:00Full page reviewedIndustry migration is scheduled by January 2027. Inventory dependent alarms and equipment. Do not equate digital telephony with universal copper broadband retirement. Recheck 21 Oct 2026. States PSTN is being switched off by industry by January 2027.
S17Telecare and digital switchover guidance for housing providersDHSChttps://www.gov.uk/government/publications/telecare-and-the-digital-switchover-guidance-for-housing-providers2026-10-08T12:00:002026-10-21T12:00:00Full page reviewedEngland housing-provider guidance published 8 October 2026. Apply only to relevant council services. SD-WAN does not itself make analogue telecare safe. Recheck 21 Oct 2026. Guidance is for housing providers in England and doesn't mention local authorities.
S18Public sector website accessibility requirementsGovernment Digital Servicehttps://www.gov.uk/guidance/accessibility-requirements-for-public-sector-websites-and-apps2018-05-09T12:00:002026-10-21T12:00:00Full page reviewedUseful procurement and usability reference for council interfaces and downloadable material. Do not misdescribe Netify as a public body or claim certification. Recheck 21 Oct 2026. Requirement is WCAG 2.2 AA and an accessibility statement for public sector bodies. The page doesn't say it applies to private companies, so no accessibility compliance claim is made for Netify.
S19Current Netify RFP builderNetifyhttps://netify.co.uk/sase-sd-wan-rfp-builder/Unknown / not supplied2026-10-21T12:00:00Full page reviewedCurrent page allows private draft and download without account or publication. Optional responses follow review. Council-specific pack and seamless prefill need confirmation before promised. Recheck 21 Oct 2026. Page states No account or publication needed to download, Your identity stays private, You review and approve what suppliers receive, Suppliers pay Netify when an introduction leads to business and That does not affect how providers are ordered, and that the checker does not certify that an RFP is ready to issue. It doesn't mention councils.
S20Netify Market RecordNetifyhttps://netify.co.uk/sase/opportunities/board/Unknown / not supplied2026-10-21T12:00:00Full page reviewedAt review the public board presents a Market Record and says no approved outcome records are published. It is not evidence of a busy live tender board. CONFLICT at recheck 21 Oct 2026. The live page is headed as a live marketplace, says 18 opportunities are genuinely open, and lists recently closed and awarded notices. It does not use the term Market Record. This differs from the description above. Copy makes no claim about the board. Robert to confirm current wording.
S21How the Netify marketplace worksNetifyhttps://netify.co.uk/sase/how-it-works/Unknown / not supplied2026-10-21T12:00:00Full page reviewedOlder copy conflicts with current RFP builder and board about downloads and marketplace activity. Use only to identify questions for Robert; do not repeat unconfirmed claims. Recheck 21 Oct 2026. Page describes a four-step flow, a private project, work-email confirmation, optional formal RFP and supplier fees paid on introductions leading to business. It doesn't mention downloads. Copy follows S19 only.
S22UK public sector provider comparisonNetifyhttps://netify.co.uk/sase/best/sd-wan-sase-providers-for-uk-public-sector/Unknown / not supplied2026-10-21T12:00:00Full page reviewedExisting provider-discovery page. Link to it for provider evidence; do not recreate the ranking on the refresh planner. Recheck 21 Oct 2026. Page covers UK public sector including local government in its scope but has no council section.
S23SASE and SD-WAN contract termsNetifyhttps://netify.co.uk/insights/sase-and-sd-wan-contract-terms-explained-deployment-timelines-slas-licensing-models-and-hidden-costs/2026-09-21T12:00:002026-10-21T12:00:00Full page reviewedExisting general contract-terms article identified during inventory; Harry must re-open relevant sections before linking. Council page applies terms to council service continuity. Recheck 21 Oct 2026. Article by Harry Yelland, 21 Sep 2026. Sections on SLAs, licensing models and a hidden-cost checklist including dual running and early termination. Fixed phase durations in the article are not reused in the council planner.
S24Wide Area Network (WAN) Connectivity tender notice 082060-2025East Riding of Yorkshire Council (Find a Tender)https://www.find-tender.service.gov.uk/Notice/082060-20252025-12-11T12:00:002026-10-21T12:00:00Full page reviewedTender notice UK4 under the Procurement Act 2023, 2025/S 000-082060. Estimated value GBP1,350,000 excluding VAT. Scope refers to a Software Defined Wide Area Network. Tender deadline 23 Jan 2026 and estimated award 5 May 2026. No award found. A procurement estimate, not a unit rate.
S25Supply and maintenance of an SD WAN Solution planned procurement notice 069198-2025East Riding of Yorkshire Council (Find a Tender)https://www.find-tender.service.gov.uk/Notice/069198-20252025-10-29T12:00:002026-10-21T12:00:00Full page reviewedPlanned procurement notice UK3. Council requires a partner to deliver and maintain a Cisco based SD WAN Solution. No value stated. Not an award.
S26Software Defined Wide Area Network (SD Wan) Connectivity Procurement, Council report C/6/25-26Cheshire East Councilhttps://moderngov.cheshireeast.gov.uk/documents/s124405/Report.pdf2025-05-14T12:00:002026-10-21T12:00:00Full page reviewedCouncil report for decision, 14 May 2025. Seeks approval to procure SD-WAN connectivity for all council sites through a mini-competition under Network Services 3 Lot 1a. Current Capita contract expires 3 Feb 2026. A two-year extension would carry at least 31.9% inflation costs. Expected cost GBP1m to GBP3.4m across two authorities is an estimate range. Seeks separate contracts to avoid novation when Cheshire East and Cheshire West and Chester separate under the Hybrid ICT (Gemini) programme. Outcome not verified. A later committee item (27 Nov 2025, The Future Model for ICT) lists no award.
S27Northern Ireland Councils Network Services contract notice 009419-2022Armagh City, Banbridge and Craigavon Borough Council and nine partner councils (Find a Tender)https://www.find-tender.service.gov.uk/Notice/009419-20222022-04-07T12:00:002026-10-21T12:00:00Full page reviewedF02 contract notice, 7 Apr 2022. Joint procurement by ten councils. Managed network services including WAN connectivity, network management, content filtering, firewalls and internet over new fibre partly funded by DCMS LFFN and RGC. Open procedure, 120 months, estimated GBP8,000,000 excluding VAT, no lots. A procurement estimate, not a unit rate.
S28Northern Ireland Councils Network Services change notice 014671-2022Armagh City, Banbridge and Craigavon Borough Council and nine partner councils (Find a Tender)https://www.find-tender.service.gov.uk/Notice/014671-20222022-05-25T12:00:002026-10-21T12:00:00Full page reviewedF14 change notice. Moves tender deadline from 9 June 2022 to 23 June 2022. No award shown.
S29The Highland Council and BT sign multi-year network services agreementThe Highland Councilhttps://www.highland.gov.uk/news/article/15644/the-highland-council-and-bt-sign-multi-year-network-services-agreement2023-10-24T12:00:002026-10-21T12:00:00Full page reviewedCouncil news release, 24 Oct 2023. Multi-year network services agreement with BT under the Scottish Wide Area Network framework covering over 340 sites, nearly 200 schools and new fibre at over 100 sites, including some of the most challenging locations in Scotland. Value and term not stated. SD-WAN is not mentioned. Cited benefits (financial savings, greater resilience) are the council's stated expectations, not verified outcomes.
S30Public Sector Broadband Aggregation (PSBA) 3 preliminary market engagement noticeWelsh Government (Find a Tender)https://www.find-tender.service.gov.uk/Notice/032577-20252025-06-11T12:00:002026-10-21T12:00:00Full page reviewedUK2 preliminary market engagement notice, archived version dated 16 Jun 2025. Fully managed WAN services (MPLS, SD-WAN, Ethernet, Internet, mobile data) for public sector sites across Wales, over 110 organisations and almost 5,000 sites. A later version dated 16 Jun 2026 exists and was not reviewed. Not a council project record. The GBP700m excluding VAT estimate is a national aggregation envelope and is not a benchmark.
S31eir evo signs 7m contract with NI local councilsfibreprovider.net (trade press reporting a supplier announcement)https://fibreprovider.net/news/eir-evo-signs-ps7m-contract-ni-local-councils2023-01-10T12:00:002026-10-21T12:00:00Full page reviewedSupplier-attributed trade report of a ten-year GBP7m contract for almost 600 council sites with eir evo UK. Not a council source. Excluded from public claims until a council award notice or minute is found.
S32Software-Defined Wide Area Network (SD WAN) contract award notice 047572-2025Cheshire East Council (Find a Tender)https://www.find-tender.service.gov.uk/Notice/047572-20252025-08-11T12:00:002026-10-21T12:00:00Full page reviewedContract award notice. Contract concluded 7 Aug 2025, supplier Virgin Media Ltd, 3 tenders received, total value GBP900,408 excluding VAT, route CCS Network Services 3 Lot 1a, options 2 x 12 months or 24 months. Award notice only, not evidence of delivery.
S33Core Infrastructure and Wired/Wireless Networking dynamic purchasing system notice 024646-2024Caerphilly County Borough Council with Welsh Government and the 22 Welsh local authorities (Find a Tender)https://www.find-tender.service.gov.uk/Notice/024646-20242024-08-06T12:00:002026-10-21T12:00:00Full page reviewedJoint DPS under the Public Contracts Regulations 2015. Lot 1 covers core infrastructure and wired/wireless networking and lists CPV 32430000 Wide area network among many codes. Stated validity 16 Sep 2024 to 31 Jul 2026 with a right to extend or shorten. Broader than a WAN or SD-WAN refresh and shows no council award.
S34Public Sector Broadband Aggregation (PSBA) 3 preliminary market engagement notice 031685-2025 (earlier version)Welsh Government (Find a Tender)https://www.find-tender.service.gov.uk/Notice/031685-20252025-06-11T12:00:002026-10-21T12:00:00Full page reviewedEarlier version of a UK2 notice, published 11 Jun 2025. Estimated value GBP700m excluding VAT, estimated dates 3 Oct 2028 to 3 Oct 2033, fully managed WAN services across MPLS, SD-WAN and other options, and continuity during transition from the current PSBA service. Planning estimate, not an award and not evidence of council call-offs.
S35Commercial, contract and supplier considerations during reorganisationLocal Digitalhttps://www.localdigital.gov.uk/resources/commercial-contract-and-supplier-considerations-during-reorganisation/2026-10-15T12:00:002026-10-21T12:00:00Full page reviewedDescribes simple and tri-party transfer, host arrangements, novation, disaggregation and inter-authority agreements, and lists network and hosting services among common high-risk contracts. No date is displayed on the page, the date is from page metadata. Cite this page, not the LGA PDF, for transfer and novation points.
S36SD WAN Solution contract award notice 056210-2026East Riding of Yorkshire Council (Find a Tender)https://www.find-tender.service.gov.uk/Notice/056210-20262026-06-15T12:00:002026-10-21T12:00:00Full page reviewedUK6 contract award notice under the Procurement Act 2023, published 15 Jun 2026. Supplier Specialist Computer Centres PLC, GBP1,415,000 excluding VAT (GBP1,698,000 including VAT), contract dates 26 Jun 2026 to 31 Jul 2031, 3 tenders received. A UK7 contract details notice 063312-2026 was published on 6 Jul 2026 with the same supplier and value. Award notice only, not evidence of delivery.
S37Wide Area Network (WAN) Connectivity contract award notice 056223-2026East Riding of Yorkshire Council (Find a Tender)https://www.find-tender.service.gov.uk/Notice/056223-20262026-06-15T12:00:002026-10-21T12:00:00Full page reviewedUK6 contract award notice under the Procurement Act 2023, published 15 Jun 2026. Supplier KCOM Group Limited, GBP785,000 excluding VAT (GBP942,000 including VAT), contract dates 26 Jun 2026 to 31 Jul 2031, 5 tenders received. The two figures are excluding and including VAT, not a range. Award notice only, not evidence of delivery.
Assignment / 16 records
instructiondetail
Your taskHarry: write the council refresh page and complete this research workbook. Follow the Word brief. Do not build or configure the database.
PurposeHelp a UK council define its network refresh, prepare a cost schedule and continue into the Netify RFP builder.
Primary destinationhttps://netify.co.uk/sase-sd-wan-rfp-builder/
Read firstDelivery tasks and Page modules define the assignment. Complete the draft-copy columns and record evidence gaps.
Record layoutOne row per record. Preserve IDs and snake_case headers. Do not merge data cells or renumber IDs after sorting.
Colour keyPale amber cells are input or writing fields. Unknown numeric values remain blank. Do not fill them with zero or invented rates.
Verified evidenceS01 S02 S03 have reviewed public project pages. S04 S05 are search-only leads held for verification. Other source review bases are explicit.
Private informationThis editorial workbook contains public reference material and templates. Do not enter resident records credentials topology or live sensitive council information.
Cost scheduleThe sheet is an unpriced category template, not a working cost estimator or market price database. Robert will implement any calculation after methodology review.
Proposed contentInputs rules questions output templates and handoff fields are proposals for review. They do not assert live product functionality or existing database schema.
Evidence joinsEvidence links stores one relationship per row. Module source_ids lists are reader aids only. Record source locations in that relationship when completing claims.
Publications and supplier requestsDo not promise automatic publication, guaranteed bids or a compliant council tender process. Robert must confirm the supplier response destination.
Final handoverReturn the finished Word manuscript and this completed workbook. Keep proposals, verified facts, illustrative examples and unresolved claims separate.
Research dateResearch checked 20 October 2026. Recheck time-sensitive procurement guidance frameworks and product claims before publication.
Handover statusCompleted 26 October 2026 by Harry. Word manuscript and this workbook are for Robert's review. Outstanding questions are on the Open questions sheet and in the Delivery tasks open_items column.
Proposed additionsColumns and the Open questions sheet added by Harry are not in the supplied layout. Each is listed in the Field dictionary with Proposed addition in validation_rule, and each needs Robert's mapping decision before any import.
RFP handoff / 14 records
handoff_idfield_namewhat_to_supplydisclosure_ruledestinationcarry_forward_statusdraft_contentresearch_blocker
H01project_titleCouncil SD-WAN refresh plus council-approved descriptorCan appear in reviewed summaryhttps://netify.co.uk/sase-sd-wan-rfp-builder/Proposed mapping for product confirmation24-site council SD-WAN refresh, co-managed (Illustrative council scenario)Robert to confirm field mapping and carry-forward behaviour (S19).
H02sectorLocal government and council typeCan appear in reviewed summaryhttps://netify.co.uk/sase-sd-wan-rfp-builder/Proposed mapping for product confirmationLocal government. English unitary council. [Illustrative council scenario]Robert to confirm sector options in the builder. S19 lists government as a sector.
H03geographyNation and approved broad regionsReview for identification riskhttps://netify.co.uk/sase-sd-wan-rfp-builder/Proposed mapping for product confirmationEngland. Broad region to be approved by the council. [Illustrative council scenario]None for Harry. Council approves region.
H04objectivesCouncil-approved drivers and service outcomesCan appear in reviewed summaryhttps://netify.co.uk/sase-sd-wan-rfp-builder/Proposed mapping for product confirmationKeep named resident-facing services running through the contract expiry. Retain restricted-service connectivity until reviewed. Separate public access from operational systems. Agree a co-managed responsibility schedule. [Illustrative council scenario]None.
H05estate_summarySite count tiers and scoped responsibilitiesAggregate only after reviewhttps://netify.co.uk/sase-sd-wan-rfp-builder/Proposed mapping for product confirmation24 sites across civic offices, customer-contact sites, libraries and depots. Site-level detail held as a restricted attachment. [Illustrative council scenario]Robert to confirm whether site-count tiers exist in the builder.
H06timingApproved renewal and delivery milestonesExact dates may identify buyerhttps://netify.co.uk/sase-sd-wan-rfp-builder/Proposed mapping for product confirmationContract expiry confirmed (date entered by the council). Notice period unconfirmed. [Illustrative council scenario]Exact dates may identify the buyer, so the council decides what is released.
H07constraintsRetained services change windows and shared-service boundariesRemove sensitive technical detailhttps://netify.co.uk/sase-sd-wan-rfp-builder/Proposed mapping for product confirmationRetained restricted-service connection. Microsoft 365 and a hosted revenues-and-benefits application. Library public-access separation. Rural depot mobile backup unconfirmed. Change windows to be set by service owners. [Illustrative council scenario]None.
H08operating_modelCouncil managed co managed fully managed or undecidedCan appear after reviewhttps://netify.co.uk/sase-sd-wan-rfp-builder/Proposed mapping for product confirmationCo-managed, with a responsibility matrix to be agreed. [Illustrative council scenario]None.
H09commercial_scheduleCost categories assumptions term and response formatRates and detailed budget private unless approvedhttps://netify.co.uk/sase-sd-wan-rfp-builder/Proposed mapping for product confirmationCost schedule categories C01 to C16 with VAT basis and term to be entered by the council. No rates supplied. Suppliers to respond using the council's schedule. [Illustrative council scenario]Robert to confirm whether the builder can carry a cost response schedule.
H10questionsSelected Q IDs plus council additions and evidence requestsReview before supplier releasehttps://netify.co.uk/sase-sd-wan-rfp-builder/Proposed mapping for product confirmationQ02, Q03, Q06, Q09, Q10, Q15, Q17, Q20, Q23, Q24, Q25, Q26. Proposed scope-sensitive additions Q08 and Q11. These are working references only, not live question-bank IDs. [Illustrative council scenario]Robert to map to the governed bank (T10).
H11open_itemsMissing evidence named owner and required decisionInternal work list by defaulthttps://netify.co.uk/sase-sd-wan-rfp-builder/Proposed mapping for product confirmationNotice period (contract owner). Restricted-service scope (service owner and security lead). Rural backup performance (network lead and supplier). Application interruption targets (service owners). Cost rates (finance and procurement). [Illustrative council scenario]None.
H12procurement_noteNation arrangement proposed route and review statusCouncil-approved version onlyhttps://netify.co.uk/sase-sd-wan-rfp-builder/Proposed mapping for product confirmationNation, England. Arrangement and route, to be confirmed by the council procurement lead. No route has been selected. Review status, pending. [Illustrative council scenario]Council-approved version only. Robert to confirm wording.
H13source_contextOriginating page module IDs and source referencesRetain for context; no sensitive analytics payloadhttps://netify.co.uk/sase-sd-wan-rfp-builder/Proposed mapping for product confirmationModules M01 to M15. Sources S06, S08, S11, S12 and S19. [Illustrative council scenario]Robert to confirm no sensitive analytics payload is attached.
H14restricted_attachmentsDetailed sites topology logs and security assessmentsNever automatically publichttps://netify.co.uk/sase-sd-wan-rfp-builder/Proposed mapping for product confirmationSite list, topology, logs, security assessments and restricted-service scope, held by the council and never released automatically. [Illustrative council scenario]None.
Route notes / 4 records
route_idnationresearch_notereview_ownersource_idstatusdate_checkednext_review_action
P01EnglandEngland. Confirm whether the procurement uses the Procurement Act 2023 or a legacy framework. Published English council examples show different routes, being an Open Procedure under the Act (Greenwich, decision of 1 October 2026), a mini-competition under Network Services 3 Lot 1a (Cheshire East, report of 14 May 2025), a framework direct award (Adur and Worthing, decision of 29 September 2026) and a competitive flexible procedure (East Riding, tender notice of 10 December 2025). RM6116 is a legacy PCR2015 framework. As at 21 October 2026 lot 1a covers inter-site connectivity (WAN), lot 2a covers intra-site connectivity (LAN), most lots end on 17 July 2027 and lots 1c and 1d end on 22 May 2027. The agreement was extended by 24 months on 12 March 2025. Eligibility, lot fit and call-off method need council procurement confirmation. Engagement before a tender must avoid unfair advantage and, above threshold, a preliminary market engagement notice is published or its absence explained in the tender notice (Cabinet Office guidance updated 13 July 2026).Council procurement leadS06Draft research note, ready for editorial review2026-10-21T12:00:00Council procurement lead to review. Re-check dated references one month before publication.
P02ScotlandScotland. Devolved Scottish authorities are generally excluded from the Procurement Act 2023 (Cabinet Office guidance, updated 15 April 2026). Use the Scottish Procurement Policy Handbook (published 7 May 2024), which covers the Procurement Reform (Scotland) Act 2014 and the Public Contracts (Scotland) Regulations 2015, and the council's own approvals. The handbook isn't legal advice and doesn't name local authorities specifically. A joint award with a regulated authority applies the Act in its entirety. Highland Council announced a 2023 network services agreement under the Scottish Wide Area Network framework (24 October 2023). Do not route a Scottish council into an English process by default.Council procurement leadS10Draft research note, ready for editorial review2026-10-21T12:00:00Council procurement lead to review. Re-check dated references one month before publication.
P03WalesWales. The Procurement Act 2023 applies to devolved Welsh authorities with Welsh Ministers' regulations (the Procurement (Wales) Regulations 2024). Use the Welsh Government guidance collection for notice sequencing (Notice sequencing and flowcharts, 16 June 2025), PME (4 December 2024) and transitional arrangements (11 July 2024). Cross-border arrangements follow the rules of the authority that set up the arrangement, so confirm which regime applies if using an English framework. Welsh Government's Public Sector Broadband Aggregation 3 preliminary market engagement notice (11 June 2025) covers WAN services for public sector sites in Wales and is a national route to review with the council procurement lead. Its value envelope is not a council cost benchmark. Check the later notice version dated 16 June 2026.Council procurement leadS09Draft research note, ready for editorial review2026-10-21T12:00:00Council procurement lead to review. Re-check dated references one month before publication.
P04Northern IrelandNorthern Ireland. Transferred Northern Ireland authorities are regulated by the Procurement Act 2023 with some differences from England (Cabinet Office guidance, updated 15 April 2026). Confirm transferred-authority status and arrangement rules with council procurement and capture applicability, rather than assuming an English sequence. Ten Northern Ireland councils published a joint open-procedure contract notice for managed network services including WAN connectivity on 7 April 2022, with a change notice on 25 May 2022.Council procurement leadS07Draft research note, ready for editorial review2026-10-21T12:00:00Council procurement lead to review. Re-check dated references one month before publication.
Page modules / 15 records
module_idheadingtarget_wordscouncil_decisionwriting_assignmentrequired_assetuser_outputsource_idseditorial_statusmanuscript_copy
M01Plan your council SD-WAN refresh180Where do I start and what will I leave with?Write the opening around contract expiry, legacy equipment and continuity of resident services. Name heads of IT, network managers and procurement leads. Promise a draft brief, cost schedule and supplier questions. Explain that unknown answers can be retained.Opening copy, 3 result labels, primary button and short privacy explanation.Start a council refresh plan.S19Ready for editorial reviewOPENING COPY At Netify, we built this planner to help your council prepare its SD-WAN refresh around the services residents depend on. Record your contract deadlines, sites and critical dependencies, then build a refresh brief, cost schedule and supplier questions. Keep unknowns visible and take your draft into Netify's RFP builder when you are ready. Your network contract has an end date, your equipment has a support date, and somewhere between the two sit the services your residents rely on. We built this planner for heads of IT, network managers and procurement leads who need to turn that into a council SD-WAN refresh that can actually be delivered. You'll start with your nation, the services your council is responsible for and any dates you already know, and after that you can add services, sites, dependencies, costs and migration constraints at your own pace. If you don't know an answer, leave it as unknown and it stays on your list of things to chase, with a suggested owner, so moving on never loses anything. WHAT YOU'LL LEAVE WITH - Council refresh brief. A project summary you can copy and edit. - Information to confirm. The gaps, who should close them and what each one holds up. - Council refresh cost schedule. What is priced, what isn't and what finance still needs to supply. Alongside those, you get a supplier question pack that is built from your answers and tied to your council's own services and evidence needs. BUTTONS - Primary button. Start my council refresh plan - Supporting button. See what my plan will include (opens the illustrative council scenario) - Persistent next-step button, shown once there is useful output. Create my council refresh RFP SHORT PRIVACY EXPLANATION Your plan is a private draft, so nothing is published and no supplier receives anything unless you review and approve it. We'd recommend keeping exact site addresses, network diagrams and security findings out of the planner and in restricted attachments held by your council.
M02Choose the reason for your refresh300What is driving our project?Provide routes for contract renewal, hardware end of support, service resilience, cloud access, shared services and reorganisation. Give one council consequence and the next information request for each. Allow multiple triggers.Trigger selector with explanatory copy and next actions.A statement of objectives and unresolved dependencies.S01;S02;S14Requires verificationMost council refreshes have more than one trigger, so select everything that applies. Your choices decide which questions the planner asks next and what goes into your statement of objectives. Trigger | What it means for the council | Next information to request Contract renewal | The notice date can fall well before the end date, so the real deadline is the date you must commit to an extension or give notice. A renewal is also the moment to settle scope, and Greenwich's October 2026 procurement approval covers managed WAN, LAN, WiFi and firewall services [S01], so decide early what sits inside yours. | End date, notice period and extension options (contract owner). Hardware end of support | Equipment past its support date turns every fault into a risk the council carries itself, and it sets the latest date you can stay put. | Device support dates and licence expiry (network lead, from the asset list). Service resilience | One failed site or circuit can stop a named service, therefore the project is judged on the council services that keep running after a failure. | Which services run from which sites, and the interruption each can accept (service owners). Cloud access | Application access has outgrown a network built around a central site. Enfield's April 2026 award decision ties its network refresh to legacy architecture and cloud connectivity [S02]. | Hosted and cloud applications in use, with an owner for each (application owners). Shared services | A contract that serves more than one authority needs its boundaries drawn before anyone renews it. Cheshire East's May 2025 report asks for separate contracts so that a later split between two councils doesn't force a novation [S26]. | Contract holder, who pays and who administers (programme lead and procurement). Reorganisation | A long contract can outlive the authority that signed it, therefore transfer and separation terms matter from day one [S14]. Apply this only if your council is affected. | Assignment, transfer and separation terms (programme lead and legal). You can also add Other, or answer Unknown and keep going. Where two triggers pull against each other, such as renewal timing and a pending reorganisation, the planner keeps both and flags the conflict for the programme lead. In our view that tension is the most useful thing on the page, so we'd always recommend leaving it visible. WHAT YOU LEAVE WITH A short statement of objectives, for example "Renewal and cloud access, with the shared-service dependency unresolved", plus the list of dependencies still to settle and who owns each.
M03Identify the council services that must keep working500Which services can tolerate which interruption?Work from adult and childrens services where applicable, revenues and benefits, housing and homelessness, customer contact, libraries, depots and civic sites. Identify responsibility differences between councils. Separate resident-facing availability from office uptime. Include out-of-hours duty teams and emergency coordination only where applicable.Service-to-site matrix with service owner, hours, application dependency, maximum acceptable interruption and acceptance test.Council-owned continuity requirements per service.S12;S03Ready for editorial reviewStart with what your council is accountable for. A unitary council, a county, a district and a Scottish, Welsh or Northern Irish council carry different services, and some sit with a shared service or another authority. The examples below are prompts, so delete any your council doesn't deliver and add the ones it does. Candidate services include adult and children's services where your council runs them, revenues and benefits, housing and homelessness, customer contact, libraries, depots and civic sites. Out-of-hours duty teams and emergency coordination only belong in the matrix if your council operates them, in which case record the hours they need and the site or remote path they use. From there, we'd separate office uptime from resident-facing availability. Office uptime tells you staff can reach the network, whereas resident-facing availability tells you a resident can pay, report, apply or be helped. A revenues and benefits team can be fully connected to its office whilst the hosted application behind it is unreachable, which is why office connectivity on its own never proves service continuity. The maximum acceptable interruption for each service is your decision, agreed with the service owner, so we'd leave it blank until the owner has agreed it. Local Digital's CAF for local government starts by identifying the essential services and critical systems a council relies on [S12], so this matrix doubles as a ready-made input to that work. Scope is rarely just the WAN. South Oxfordshire and Vale of White Horse's tender replaces the active network components of their offices and buildings as part of an SD-WAN transition [S03], so check which of your service sites also depend on ageing switching and wireless. Service | Council responsible? | Service owner | Sites | Hours | Application dependency | Maximum acceptable interruption (council decides) | Acceptance test Revenues and benefits | Yes / No / Shared | Name or role | Site list | Hours | Hosted application name | Minutes, or Unknown | Named action, e.g. take a payment from the depot Customer contact | Yes / No / Shared | Name or role | Site list | Hours | Telephony and case system | Minutes, or Unknown | Answer a call with the record on screen Libraries | Yes / No / Shared | Name or role | Site list | Opening hours | Public access and staff systems | Minutes, or Unknown | Public session and staff session both work Depots | Yes / No / Shared | Name or role | Site list | Shift pattern | Works and fleet systems | Minutes, or Unknown | Job dispatch works on the backup path Out-of-hours duty (only if applicable) | Yes / No / Not applicable | Name or role | Site or remote | Duty hours | Duty rota and case access | Minutes, or Unknown | Duty officer reaches the case system WHAT YOU LEAVE WITH Council-owned continuity requirements for each service. Any essential service without an agreed interruption target and acceptance test goes straight onto your list of information to confirm.
M04Build the estate and contract inventory450What do we own and when can we change it?Specify sites, region, shared-service boundaries, circuits, termination dates, notice periods, extension options, device support dates, licences and exit assistance. Include rural access, listed buildings, wayleaves, power, LAN capacity and wireless dependencies. Distinguish unknown, none and not applicable.Inventory field descriptions and public versus restricted examples.Gap list and an evidence request for the incumbent.S03;S14Ready for editorial reviewAt Netify, we see this as the step that most often decides the timetable of a council SD-WAN refresh. You can't choose a date until you know what you own, what you rent, when each contract can end and what it costs to leave, so the planner asks for the fields below and lets you answer Known, Unknown, None or Not applicable for each. These answers mean different things. Unknown means nobody has checked, None means you checked and there isn't one (no extension option, for example) and Not applicable means the question doesn't apply to that site. The planner keeps them apart and only Unknown goes onto your chase list. If you only complete one field properly, we believe it should be the notice period. Field | What to record | Why it matters Sites and region | Site type, nation and broad region | Sets scope and survey effort. Shared-service boundary | Which sites, contracts and licences belong to which authority | A reorganisation or split can move them [S14]. Circuits | Type, supplier and contract reference per circuit | Different circuits end on different dates. Termination and notice | End date, notice period and extension options | The notice date is usually the true deadline. Devices and licences | Support end dates and licence terms | Sets the latest date you can stay put. Exit assistance | What the incumbent must provide at exit | Decides how clean the handover is. Access and power | Rural access, listed buildings, wayleaves, power, LAN capacity and wireless dependencies | Each one can add a survey, a permission or a civil works cost. Costs follow the same structure. South Oxfordshire and Vale of White Horse asked bidders to price hardware per site, five-year licence and support, installation and configuration per site, and ongoing annual support separately [S03]. We'd recommend capturing yours the same way from the start. Public and restricted information Can appear in a reviewed supplier summary | Stays in restricted council attachments Number of sites by tier, nation and broad region | Street addresses and site-level access notes Contract end quarter or year, if the council approves it | Circuit references and supplier account numbers Operating model and service categories | Topology diagrams, IP addressing and device serials Whether a restricted service connection is retained | Security assessments and vulnerability reports WHAT YOU LEAVE WITH A gap list and a ready-to-send evidence request for the incumbent. It asks for the service schedule, circuit list with termination dates, asset and licence list with support dates, notice and extension terms, exit assistance terms and current monthly charges.
M05Decide the network boundaries before removing legacy links450What can move now and what must remain?Use actual council dependency questions: PSN access, partner connections, legacy addressing and allowlists, DNS and identity, Azure-hosted services and shared systems. Explain that PSN is not MPLS and that application dependencies must be signed off before circuits are removed. Mention security components only against an identified council requirement.Dependency map template and keep change retire decision table.Approved dependency register or actions to resolve unknowns.S11;S03Ready for editorial reviewBefore any circuit goes, you need to know what depends on it. The planner takes you through the dependencies that catch councils out, those being PSN access, partner connections, legacy addressing and allowlists, DNS and identity, Azure-hosted services and shared systems. PSN is a good example, as it's a compliance arrangement that sits separately from any circuit type. PSN-connected organisations hold compliance certificates for connection, service provision or connectivity [S11], so retiring a legacy circuit tells you nothing about whether a PSN-dependent service still needs a path. No closure date is published, therefore the only reliable answer comes from the service owner who uses the connection. Partners need the same attention. Police, health and neighbouring authorities may allowlist your council's address ranges, so a change of addressing can break a connection that nobody on the network team knew existed. Azure is another example, as South Oxfordshire and Vale of White Horse's tender requires security appliances to support site-to-site VPN into Microsoft Azure for each site [S03]. We'd ask where your own cloud and hosted services connect and who owns each connection. We'd only put a security component into the design against a council requirement you've named, and if nobody can say which requirement a component meets, we'd recommend leaving it out of the brief until someone can. No circuit should be removed until the owner of every dependency on it has signed off, and that's the rule the planner enforces on your register. Dependency | Type | Owner | Current path | Decision (Keep, Change, Retire, Unknown) | Sign-off evidence Restricted service connection | PSN or partner | Service owner and security lead | Described, not diagrammed | Keep until reviewed | Signed dependency review Hosted revenues and benefits application | Hosted application | Service owner | Described | Change or Unknown | Named application test Azure-hosted service | Cloud | Application owner | Described | Change or Unknown | Connection test Partner allowlist on council ranges | Addressing | Network lead | Described | Unknown until partner confirms | Partner confirmation DNS and identity | Core service | Network and identity leads | Described | Keep or Change | Failover test How the decision table works - Keep. The dependency stays on its current path until reviewed. - Change. The dependency moves to the new design after a witnessed test. - Retire. Only when the owner confirms nothing depends on it and signs the register. - Unknown. Treated as Keep, and an action is created for the owner. WHAT YOU LEAVE WITH An approved dependency register, or a list of actions to resolve each unknown with a named owner.
M06Specify resilience by council service and site450What must survive a circuit power or provider failure?Connect resilience to continuity of revenues and benefits, housing support and agreed duty services. Ask for physical route and exchange diversity, mobile coverage measured on site, battery runtime, monitoring and degraded-mode tests. Two provider names do not prove diversity. Distinguish response, restoration and application recovery.Site-tier template and witnessed failover acceptance tests.Service-specific resilience questions and evidence requests.S12;S01Ready for editorial reviewResilience only means something when it is tied to a service. For each site, ask what has to survive a circuit failure, a power cut or a provider problem, and write the answer in terms of revenues and benefits, housing support and any duty services your council has agreed to run. Three things get confused in supplier responses, so the planner keeps them apart. Response is how fast the supplier acknowledges a fault, restoration is how fast the connection comes back and application recovery is how fast the council service works again. A quick acknowledgement says very little about the last of those. Diversity needs evidence as well. Two provider names on a proposal don't prove two routes, as two retail suppliers can share the same duct, exchange or fibre, so we'd ask for physical route and exchange information for each essential site, with controlled disclosure if the supplier considers it sensitive. Mobile backup needs the same evidence. A coverage map doesn't establish a usable backup, therefore ask for coverage and performance measured on site, under expected load. Backup power matters too, as mobile backup is no help when the site equipment has no power, so ask for runtime, maintenance and recovery for each specified site. Monitoring is part of the answer. Greenwich's procurement approval combines on-site engineers with back-office monitoring and support [S01], so ask your bidders who watches a failed link at the hours your duty services run, and what they do about it. Testing should be proportionate. Local Digital's CAF focuses on essential services and critical systems [S12], and your site tiers should follow the same logic. Our recommendation is that council-defined essential sites get the full witnessed test, and that low impact sites don't need one. Site tier (council defined) | Evidence to request | Witnessed acceptance test Essential | Route and exchange diversity, on-site mobile measurement, battery runtime, monitoring hours | Pull the primary link, then lose power, while the named council application runs. Record time to recover and rollback owner. Standard | Backup design, monitoring hours | Pull the primary link while the named application runs. Low impact | Documented behaviour on failure | Documented only, unless the service owner asks for more. Unknown | Tier classification from the service owner | Not scheduled until classified. Degraded-mode tests to include - Primary circuit failure with the named application running. - Site power loss, with the stated battery runtime measured. - Provider-side failure, simulated with the supplier and the council's change authority present. - Return to normal running, confirmed by the service owner. WHAT YOU LEAVE WITH Service-specific resilience questions and evidence requests, ready to carry into your RFP.
M07Plan security and assurance evidence for the refresh400What evidence do security and service owners need?Connect segmentation to public library access, council staff, contractors and building systems. Cover administrator access, council-owned accounts, logs, inspection, update ownership and incident evidence. Explain council CAF and PSN dependencies locally. Invite DPO screening where monitoring or data processing changes.Assurance evidence checklist with accountable reviewers.Questions for the security lead and DPO.S11;S12;S13;S15Ready for editorial reviewSecurity and service owners need different evidence, and asking for it early saves rework at the RFP stage. Start with segmentation. A library offering public access, council staff, contractors and building systems such as CCTV have different trust boundaries, so ask bidders to show how they're separated where they're in scope, and how you'd test that at acceptance. Then cover control. The council should own the administrator accounts that matter, with a role model, multi-factor access reviews and an emergency access procedure. We'd ask what data is logged, where it is processed, how long it is kept, who at the supplier can see it, who updates the platform and what incident evidence you'd receive. On assurance, it helps to be clear about what a purchase can do. Local Digital's CAF for local government is voluntary, begins with essential services and critical systems, and includes an independent assurance review [S12]. By January 2026, 90 councils had completed an assessment, and the programme is moving to CAF version 4.0 and a web application [S13]. Buying a network or a managed service doesn't give you CAF or PSN compliance, but it can produce evidence for the actions in your own CAF plan, which is why we'd ask your security lead to name those actions before the RFP goes out. PSN stays a local question. If any service still relies on a PSN or restricted partner connection [S11], the service owner and security lead decide what happens to it, and that decision comes before design. Finally, we'd involve your DPO early. A data protection impact assessment is needed where processing is likely to be high risk, and the ICO's list includes systematic monitoring of a publicly accessible area on a large scale [S15]. Its guidance is under review following the Data (Use and Access) Act. If your refresh changes what is logged, inspected or visible to a supplier, ask the DPO to screen it before you issue anything. Evidence | Ask for | Accountable reviewer Segmentation | Policy design and acceptance tests for staff, public access, contractor and building-system traffic | Security lead Privileged access | Role model, multi-factor access reviews and emergency access procedure | Security lead Logging and inspection | Data-flow summary, retention and supplier access | DPO and security lead Updates and patches | Who updates what, and how the council is told | Network lead Incident evidence | Incident workflow, escalation example and log access | Security lead CAF actions | Evidence mapped to the council's own CAF improvement actions | Security lead PSN or partner dependencies | Owner-approved transition plan | Service owner and security lead WHAT YOU LEAVE WITH A short list of questions for the security lead and for the DPO.
M08Build the council refresh cost schedule500What are the full costs and when will they fall?Separate incumbent baseline, one-off project costs, future recurring costs, dual running, surveys, civil works, licences, staff time, training, support, exit and expansion. Show monthly versus annual units and VAT basis. Compare equal scope and term. Make all rates council-supplied or quote-sourced; missing rates stay unknown.Itemised schedule, nominal annual cash flow and completeness warning.Cost schedule suitable for finance review with assumptions.S03;S01Ready for editorial reviewA cost schedule only helps if finance can trust it, so the planner is strict about what counts as a number. It separates the incumbent baseline from the new costs, and splits the new costs into one-off project costs, future recurring costs, dual running, surveys, civil works, licences, staff time, training, support, exit and expansion. Monthly and annual charges stay in their own units, and every line carries a VAT basis of Excluding VAT, Including VAT, VAT not applicable or Unknown. Rates are either supplied by your council or taken from a supplier quote, with the date, scope, billing basis, term, inclusions, exclusions and VAT basis recorded against them. If you don't have a rate, it stays unknown. The planner never fills a gap with a typical figure and a blank is never treated as zero. Be careful with headline numbers in published decisions. Greenwich's approval carries an estimated £16 million over a term of up to ten years, but it covers managed WAN, LAN, WiFi and firewall services [S01], so it isn't an SD-WAN price or a per-site benchmark. South Oxfordshire and Vale of White Horse's notice displays £0 [S03], which tells you nothing about cost. A tender envelope is never a unit rate. The whole-term nominal total is calculated in plain terms as follows. Add the one-off costs, add each monthly recurring rate multiplied by its chargeable months, add each annual recurring rate multiplied by its chargeable years and add any explicitly priced overlap and exit items. Indexation only enters with a stated method and date. Internal staff time is shown separately from cash costs, and contingency is shown separately from the subtotal it is calculated on. If any required line is missing, the planner shows a Priced subtotal and lists what's missing. It doesn't show a complete total, and it doesn't calculate a savings percentage from an incomplete baseline or from a baseline with different scope or term. We'd only compare incumbent and proposed costs across the same estate and the same term, and we'd always keep the priced subtotal on screen beside the list of missing lines, as a total that hides its gaps is the one finance will question. Finance decides VAT recovery and accounting treatment, and procurement valuation is a separate review. Netify's contract terms article covers SLA structures and a hidden-cost checklist in general terms [S23], and this planner applies the same thinking to council services. COMPLETENESS WARNING Copy: This schedule contains unpriced items. Review the missing rates before using a complete project total. NOMINAL ANNUAL CASH FLOW LAYOUT Cost line | Basis | Year 1 | Year 2 | Year 3 | Later years One-off lines (C01, C02, C03, C08, C11, C12, C15) | one_off | Unknown | Unknown | Unknown | Unknown Recurring monthly lines (C04 to C07) | recurring_monthly | Unknown | Unknown | Unknown | Unknown Recurring annual lines (C13) | recurring_annual | Unknown | Unknown | Unknown | Unknown Dual running and exit (C09, C10) | overlap_monthly / one_off | Unknown | Unknown | Unknown | Unknown Optional and contingency (C14, C16) | optional / allowance | Shown separately | Shown separately | Shown separately | Shown separately Priced subtotal | Calculated from priced lines only | Not complete | Not complete | Not complete | Not complete The 16 cost categories, with units and the question each one raises for finance, are listed in the cost schedule appendix. WHAT YOU LEAVE WITH A cost schedule suitable for finance review, with assumptions, missing items and VAT basis visible.
M09Choose an operating model the council can support350Who will run the network after migration?Compare council-managed, co-managed and fully managed responsibilities using council staffing, duty cover and change needs. Name ownership for circuits, policies, patches, incidents, subcontractors and exit exports. Include shared-service governance and contract transfer considerations where relevant.Responsibility matrix and same-scope supplier response format.A proposed responsibility schedule for the RFP.S01;S14Ready for editorial reviewWho runs the network after migration is a staffing decision as much as a technical one, so the planner compares three models against your team size, duty cover and the rate of change you expect. In a council-managed model your team owns operation and supplier input is limited to circuits and hardware. In a co-managed model responsibilities are split and written down, and in a fully managed model the supplier runs the service to a specification you set. We'd recommend starting from honest numbers. A small team with no out-of-hours cover shouldn't pick council-managed for services that run out of hours, and a team that changes policy weekly will find a managed model with charged changes expensive and slow. Whichever model you pick, write down who owns each item below, as disputes happen where ownership was assumed. Greenwich's approval pairs on-site engineers with back-office monitoring [S01], which shows how much an operating model can include. Responsibility | Council-managed | Co-managed | Fully managed | Council decision Circuits and access suppliers | Council contracts directly | Named split | Supplier contracts and manages | To enter Policies and changes | Council writes and changes | Council writes, supplier applies within a change catalogue | Supplier changes to a council-approved standard | To enter Patches and updates | Council | Named owner per item | Supplier, council notified | To enter Incidents and escalation | Council raises with each supplier | Shared workflow | Supplier owns end to end | To enter Out-of-hours cover | Council duty rota | Named split | Supplier | To enter Subcontractors | Council manages | Disclosed and notified | Supplier discloses and notifies | To enter Exit exports | Council holds | Joint | Supplier provides on exit | To enter Shared-service governance (if applicable) | Council | Named per authority | Named per authority | To enter Ask every bidder to respond in the same table so that the proposals are like for like. Where your council shares the network with another authority, the table also needs the governance for each partner and what happens to the contract if a partner leaves [S14]. WHAT YOU LEAVE WITH A proposed responsibility schedule you can attach to your RFP.
M10Set the procurement route with your council team500What route can this council use?Ask nation, procurement arrangement, existing framework and current contract regime before suggesting research. Explain early market engagement versus formal competition. Include Network Services 3 as a dated example with relevant lots and eligibility checks. Treat Scotland separately and add Welsh and Northern Ireland review routes. The Netify marketplace supports preparation and engagement; statutory notices and council approvals remain separate.Nation-specific route notes and procurement officer review questions.A route-to-market note for approval, with unresolved decisions.S06;S07;S08;S09;S10Ready for editorial reviewWe'd recommend settling the basics before picking a framework. The planner asks for your nation, procurement arrangement, existing framework and current contract regime first, and only then shows route notes. Your procurement lead decides the route and nothing here is a legal determination, so we'd suggest getting your procurement officer into the room before the first supplier conversation. Early market engagement and formal competition are different things. Under the Procurement Act in England, engagement before a tender must not give any supplier an unfair advantage, and where an authority engages the market above threshold it either publishes a preliminary market engagement notice or explains in the tender notice why it didn't [S08]. Netify's marketplace supports preparation and engagement, whilst statutory notices, council approvals and your tender portal stay separate. Published council procurements show how varied the routes are. Greenwich approved an Open Procedure under the Procurement Act 2023 [S01]. Cheshire East's report proposes a mini-competition under Network Services 3 Lot 1a [S26]. Adur and Worthing's decision is a direct award under the SBS DWS2 framework [S04]. East Riding's tender notice uses a competitive flexible procedure [S05]. These choices were made for different scopes, so none of them is a route we're recommending. Network Services 3 (RM6116) is a useful dated example. As at 21 October 2026 it remains a PCR2015 framework. Lot 1a covers inter-site connectivity (wide area network) and lot 2a covers intra-site connectivity (local area network). Most lots end on 17 July 2027 and lots 1c and 1d end on 22 May 2027 [S06]. We'd check your eligibility, whether the lot fits your scope, how a call-off would run and whether your award and contract start can land before the lot ends. Scotland needs its own research. Devolved Scottish authorities are generally excluded from the Procurement Act [S07], and Scottish public procurement follows the Procurement Reform (Scotland) Act 2014 and the Public Contracts (Scotland) Regulations 2015 [S10]. Welsh authorities should use the Welsh Government's guidance and notice sequencing [S09]. Northern Ireland authorities should confirm applicability with their procurement team, as the Act regulates them with some differences [S07]. Where an arrangement is set up by an authority in another nation, cross-border rules can change which regime applies [S07]. Nation | Start here | Reviewer England | Confirm whether the Act or a legacy framework applies. RM6116 is a legacy framework, so identify lot, eligibility and method. | Council procurement lead Scotland | Use Scottish procurement legislation and the council's arrangements. Don't apply the English route automatically. | Council procurement lead Wales | Use Welsh Act guidance and Welsh notice requirements, plus any transitional rules. | Council procurement lead Northern Ireland | Confirm transferred-authority status and arrangement rules before assuming an English sequence. | Council procurement lead Questions for your procurement officer - Which nation's rules and which arrangement apply to this procurement? - Is there an existing framework or contract we must or may use, and until when? - Do we need a preliminary market engagement notice before we speak to suppliers? - What is the estimated value, and which valuation method will procurement use? - Who approves the route and when? WHAT YOU LEAVE WITH A route-to-market note for approval, with unresolved decisions listed.
M11Schedule the pilot and migration around council services500How do we change the network without losing essential services?Work backwards from actual contract and decision dates, with council-owned lead times. Include discovery, approval, supplier selection, surveys, circuit delivery, staging, representative pilot, waves, rollback, hypercare and exit. Protect locally identified elections, billing runs, benefits payments, duty services and committee access. No fixed universal migration duration.Milestone planner and acceptance checklist with owners.An indicative dependency-led plan with unconfirmed dates flagged.S02;S03;S14Ready for editorial reviewStart from the dates you can't move and work backwards. Put in your contract end date, your notice date and any decision dates, then add the lead times your own council knows, such as committee cycles, procurement approvals and survey access. The planner doesn't assume a migration duration, as there isn't a universal one, so every duration and date is entered by your council and anything unconfirmed is flagged as such. Two published examples show why the order matters. Cheshire East's May 2025 report asked for approval to procure a replacement for a contract expiring on 3 February 2026, and notes that a two-year extension would carry at least 31.9% in inflation costs [S26]. East Riding's tender notice expects the solution to be live by 1 April 2027 against an estimated contract start of 1 June 2026 [S05]. In both cases the interval between a decision and a working network is what decides whether you need an extension, and what it costs. Then protect the dates that matter locally. Ask service owners which periods they treat as blackout, which might include revenues and benefits payments, billing runs, elections, out-of-hours duty arrangements and committee or public-access services. The planner doesn't assume a national election date or a universal change freeze, so it only protects what you enter. If a shared service or reorganisation applies, add the transfer and separation dependencies as well, given that continuity through organisational change is what the LGA's reorganisation research centres on [S14]. Plan the pilot to find problems and give the design a proper test. We think a pilot that only proves the easy sites has proved very little, so include an essential-service site and, where you have one, a difficult-access site. South Oxfordshire and Vale of White Horse's tender asks for installation and configuration per site as a priced line [S03], which is a good reminder to plan each wave site by site. Milestone | Owner | Depends on | Council duration or date | Confidence | Acceptance evidence MS01 Estate discovery | Council network lead | Contract and asset access | Council enters | High, Medium or Low | Inventory with missing information recorded MS02 Essential-service requirements | Council service owners | Service responsibility scope | Council enters | High, Medium or Low | Application dependencies, interruption targets and change windows MS03 Business case and funding | Council finance and IT | Comparable cost schedule | Council enters | High, Medium or Low | Approved funding and scope assumptions MS04 Procurement route review | Council procurement lead | Nation, arrangement and contract regime | Council enters | High, Medium or Low | Recorded route decision and required notices MS05 Supplier process | Council procurement lead | Approved process and documentation | Council enters | High, Medium or Low | Comparable responses through the authorised route MS06 Surveys and delivery | Supplier and council estates | Site access, permissions and access design | Council enters | High, Medium or Low | Site delivery dependencies confirmed MS07 Configuration and staging | Supplier and council network lead | Design and access roles approved | Council enters | High, Medium or Low | Configuration and documentation reviewed MS08 Representative pilot | Service owners and supplier | Test criteria, rollback and dependencies agreed | Council enters | High, Medium or Low | Witnessed application failover and recovery results MS09 Migration waves | Council change authority | Pilot acceptance and site readiness | Council enters | High, Medium or Low | Per-wave approval and rollback record MS10 Hypercare | Supplier and council operations | Wave completion | Council enters | High, Medium or Low | Incident ownership, monitoring and escalation confirmed MS11 Incumbent cessation | Council contract owner | Service acceptance and dependency sign-off | Council enters | High, Medium or Low | Approved stop dates and final overlap cost MS12 Handover and exit readiness | Council operations | Accepted service and documentation | Council enters | High, Medium or Low | Access, training, exports and next review date Acceptance checklist - Normal-running and failed-link tests run the named council applications, not just a speed test. Owner: network lead. - A representative essential-service site and a difficult-access site are in the pilot where they exist, and rural backup is measured on site. Owner: service owners. - A circuit failure, power loss or routing problem has a named response owner and an agreed rollback action. Owner: change authority. - The service owner confirms outcomes and the IT team receives usable configuration, documentation and access. Owner: service owners and IT. - The old service stops only after recorded acceptance and dependency approval, with overlap charges visible. Owner: contract owner. WHAT YOU LEAVE WITH An indicative, dependency-led plan with unconfirmed dates flagged.
M12Learn from published council refresh programmes400What comparable scopes should we investigate?Write concise source-linked examples of Greenwich, Enfield and South Oxfordshire with Vale of White Horse. Distinguish decision, tender and proven outcome. Add other nations and rural or shared-service cases through further primary research. Do not infer delivery success, savings or supplier quality from a notice.At least 6 verified council project records across at least 3 nations if evidence is available; record gaps openly.Comparable scope examples, never a per-site price benchmark.S01;S02;S03;S04;S05Requires verificationAt Netify, we'd use published programmes to understand scope. Each of the examples below sits at a different stage, and a decision, a tender and a delivered outcome are three different things, so none of them tells you whether a project worked, what it saved or how good the supplier was. Greenwich approved procurement of a network managed services contract on 1 October 2026. It covers managed inter-building and intra-building networks, internet and wireless services and firewalls, with on-site engineers and back-office monitoring, and a WAN and LAN hardware refresh is already in train. The estimated £16 million over up to ten years is the whole service envelope, so it isn't an SD-WAN price [S01]. It's an approval, so it shouldn't be read as an award. Enfield awarded a network refresh in April 2026 that addresses legacy architecture and cloud connectivity [S02]. No price or delivery outcome is established, therefore we'd treat it as a pointer to scope only and use it to ask how your business case links architecture, cloud access and resilience. South Oxfordshire and Vale of White Horse published a joint tender on 20 December 2024 for LAN, wireless and security refresh, supporting a transition to SD-WAN. It asks for hardware, five-year licence and support, installation and annual support to be priced separately, and it is now closed with no award shown [S03]. The £0 value on the notice is unusable. Council | Nation | Stage and date | Scope | What it helps you ask Adur and Worthing Councils | England | Decision to direct award, 29 September 2026 [S04] | Migrate fibre networking across 22 council sites to SD-WAN over CityFibre using a commercial ISP, under the SBS DWS2 framework | How does the access network sit alongside the SD-WAN service? East Riding of Yorkshire Council | England | Two tender notices, December 2025, and two award notices, June 2026 [S05, S24, S36, S37] | A Cisco-based SD-WAN solution and, separately, WAN connectivity | Should platform and connectivity be bought together or apart? Cheshire East Council | England | Council report for decision, 14 May 2025, and award notice, August 2025 [S26, S32] | SD-WAN connectivity for a shared ICT service, via Network Services 3 Lot 1a, with separate contracts to avoid novation if the partners split | How do shared-service ownership and contract transfer shape the contract? Ten Northern Ireland councils | Northern Ireland | Joint contract notice, 7 April 2022 [S27] | Managed network services including WAN connectivity, firewalls and internet over new fibre, 120 months, open procedure | How do ten authorities define one shared service? Highland Council | Scotland | Agreement announced, 24 October 2023 [S29] | Network services under the Scottish Wide Area Network framework across over 340 sites, including some of the most challenging locations in Scotland | How do you scope remote and difficult-access sites? We'd use these to compare what was in scope and what each council chose to buy separately, as they aren't price benchmarks and don't establish that any project succeeded.
M13Create your council refresh RFP300How do I turn these decisions into supplier questions?Explain the council-specific export, unresolved items and attachments. Use the existing RFP builder for drafting and review. Separate questions for preliminary engagement from an RFP with priced responses. Tell users what to review before issue and what remains their procurement responsibility.Copyable brief, question selections and builder CTA.An editable RFP draft at the specified Netify destination.S19;S08Requires verificationOnce your brief, services, dependencies and cost schedule are in place, the next job is turning them into a council network refresh RFP with supplier questions your bidders can answer like for like. Netify's RFP builder handles the drafting and review, and your council keeps the decisions. Your council-specific export brings together a project title and summary, your council responsibilities, broad geography, service outcomes, estate scope, timing, dependencies, operating model, the cost response schedule, your chosen questions, unresolved items and a procurement note. Detailed sites, topology, logs and security assessments stay out of it as restricted attachments, and open items travel with the draft so that a missing notice period or an unagreed interruption target stays visible. Questions come in two kinds. Questions for preliminary engagement help you shape requirements and don't ask for prices, whereas questions for an RFP with priced responses ask suppliers to price the same site list, term and responsibilities using your cost schedule. The planner labels each question so you can keep the two apart. The builder produces a private draft you can download without an account or publication [S19]. Its checker flags coverage gaps but doesn't certify that an RFP is ready to issue [S19], so the review is yours. If you're still deciding which providers to approach, Netify's UK public sector comparison covers provider evidence [S22]. Before you issue anything, we'd have service owners check the continuity requirements, finance check the cost schedule, the security lead and DPO check the assurance questions, and procurement check the route and the wording of the procurement note. The procurement responsibility stays with your council, including notices, approvals and your tender portal [S08]. COPY BESIDE THE BUTTON Copy: Use your council refresh plan to prepare an editable RFP draft. Review the service requirements, cost schedule and unresolved questions with the relevant council teams before you issue it. [Button] Create my council refresh RFP IF YOUR PLAN DOESN'T CARRY ACROSS AUTOMATICALLY Copy the brief and question list from your plan into the builder, then add your open items as notes, and your private draft stays with you either way. Our view is that the review works best as one meeting with every team in the room, so that conflicting answers surface before issue. [ROBERT TO CONFIRM: carry-forward behaviour. This fallback line is the safe default.] COPYABLE BRIEF AND QUESTION SELECTIONS The brief template is in the illustrative council scenario below. The question selections come from the supplier question pack, with each question's council reason and the evidence requested.
M14Request supplier responses when your council is ready220Can we seek responses without losing control of our information?Describe review of the proposed supplier-facing summary and the council procurement route before optional sourcing. Use cautious wording consistent with the live destination. No automatic publication, guaranteed bids, automatic award or claims of statutory compliance. Provide a draft-only alternative.Optional response CTA, confirmation text and anonymisation checklist.A buyer-approved sourcing request or retained private draft.S19;S20;S21Requires verificationAsking for supplier responses is optional, and it comes after you've reviewed your draft. Before anything leaves your council, check the supplier-facing summary line by line and confirm the council's procurement route with your procurement officer. Netify doesn't publish anything automatically and no supplier receives your information unless you approve it. In our view an approach to suppliers should be the last step of the process. A sourcing request through Netify doesn't replace your procurement strategy, statutory notices, framework process or tender portal, and preliminary engagement must still treat suppliers fairly [S08]. Netify doesn't guarantee bids, and an approach to providers isn't an award route. Suppliers pay Netify when an introduction leads to business, and that doesn't affect how providers are ordered [S19]. [ROBERT TO CONFIRM: approved fee disclosure wording and the actual supplier-response destination and workflow before this section goes live.] OPTIONAL BUTTON [Button] Discuss supplier responses for my council refresh Copy: When your council is ready, review the sourcing approach and approve the summary and providers that may receive it. Keep sensitive network details in restricted attachments. CONFIRMATION TEXT Copy: You've approved this summary for the providers you selected. Your private draft, cost schedule and restricted attachments stay with your council. [ROBERT TO CONFIRM wording] ANONYMISATION CHECKLIST - Council name and exact dates removed unless your council has approved them. - No site addresses, topology diagrams, IP addresses or device serials. - No security assessments, vulnerability findings or named staff. - Rates and budget excluded unless the council has approved sharing them. - Retained restricted-service connections described by category only. - An authorised council buyer has approved the summary. DRAFT-ONLY ALTERNATIVE Copy: Keep preparing your private draft. Review the supplier-facing summary and your council's procurement route before requesting responses. [Button] Keep my draft private
M15Answer council refresh questions650What difficult questions are still stopping a decision?Write 10 to 12 short answers grounded in council scenarios. Include retained PSN, contract expiry before delivery, reorganisation, libraries and CCTV separation, rural backup, data location, co-management, budget uncertainty, Scottish routes, telecare dependencies and publication boundaries. Every answer ends with an action, evidence request or tool entry.Question-led answers with source links and relevant planner section.A resolved question or next evidence request.S06;S07;S11;S14;S17;S19Ready for editorial reviewQ. We still have a PSN connection. Can we retire our legacy links? A. Not until the service owner confirms what depends on it. PSN is a compliance and connection arrangement that sits apart from any circuit type, and holding a certificate doesn't tell you whether a service still needs a path [S11]. Action. Answer the PSN or restricted partner dependency input in the planner, and keep Q03 in your question set. Section M05. Q. Our contract ends before our council WAN replacement can be delivered. What do we do? A. Price the bridge before you choose it. Cheshire East's May 2025 report on a contract expiring in February 2026 notes that a two-year extension would carry at least 31.9% in inflation costs [S26], and dual running adds more. Action. Enter your end date, notice date and extension options, then price overlap and delayed delivery with Q21. Section M11. Q. We might be reorganised. Should the contract allow for that? A. Yes, if reorganisation applies to your council. Ask for transfer, separation and assignment terms and what they cost [S14]. Cheshire East's report seeks separate contracts to avoid novation if the two partners split [S26]. Action. Set the shared service or reorganisation input to Yes or Unknown, which adds Q04, Q05 and Q22. Section M09. Q. How do we keep library public access separate from CCTV and building systems? A. Ask for the segmentation design and an acceptance test for each trust boundary. Where CCTV monitors a publicly accessible area, your DPO should screen the change, as large-scale systematic monitoring of public areas is a high-risk processing example in the ICO's DPIA guidance [S15]. Action. Include Q10 and ask the DPO to review. Section M07. Q. What if mobile backup is poor at a rural depot? A. Measure it on the site, under load, before you accept the design. A coverage map doesn't establish a usable backup, and backup power matters too. Highland Council's 2023 agreement covers over 340 sites including some of the most challenging locations in Scotland [S29], which shows how wide difficult-access estates can be. Action. Add the site access and power input, a survey line in C02, and Q08 and Q09. Section M06. Q. Where will our data be processed and who at the supplier can see it? A. Ask for a data-flow summary covering what is collected, where it is processed, retention and supplier access. Your DPO decides whether a DPIA is needed [S15]. Action. Add Q13 and send the answer to your DPO and security lead. Section M07. Q. We want a co-managed service. How do we keep control? A. Write the split down item by item and ask every bidder to respond in the same table. We'd pay particular attention to which changes your team can make and which are charged or need supplier approval. Action. Choose Co managed in the planner, which adds Q15 and Q17 and the responsibility matrix. Section M09. Q. We don't have a confirmed budget. Can we still go to market? A. You can prepare and engage, but we wouldn't use a headline figure as a budget. Greenwich's estimated £16 million covers managed WAN, LAN, WiFi and firewall services over up to ten years [S01], so it isn't a benchmark for a WAN refresh. Action. Leave the budget input blank and the cost schedule will show a Priced subtotal with missing lines. Section M08. Q. We're a Scottish council. Does the English route apply? A. Not automatically. Devolved Scottish authorities are generally excluded from the Procurement Act [S07], and Scottish public procurement runs on its own legislation and handbook [S10]. Highland Council's 2023 agreement used the Scottish Wide Area Network framework [S29]. Action. Select Scotland as your nation and ask your procurement lead to approve the route. Section M10. Q. Do telecare alarms affect our network plan? A. They can, if your council's services include them. Analogue telecare that isn't upgraded may become unreliable or stop working during the digital phone switchover, which is due to complete by January 2027 [S17, S16]. A network upgrade doesn't make an analogue device safe. Action. Set the telecare input to Yes or Unknown, which adds Q30 and a device-owner assessment before any affected cutover. Section M05. Q. Can we use Network Services 3 for a refresh? A. It might suit some councils, and only your procurement lead can say. As at 21 October 2026 it's a PCR2015 framework, lot 1a covers WAN and lot 2a covers LAN, and most lots end on 17 July 2027 [S06]. Action. Record the framework and lot in the procurement route input and ask procurement to confirm eligibility. Section M10. Q. Will Netify publish our requirement or approach suppliers for us? A. Not unless you approve it. The RFP builder lets you download a private draft without an account or publication [S19]. Optional supplier responses follow your review, and they don't replace your own procurement process. Action. Keep the supplier-facing summary input at Not prepared until your buyer approves it. Section M14.
Cost schedule / 16 records
cost_item_idcategorycharge_basisquantity_unitquantityunit_rate_gbpmonths_or_yearsvat_basisrate_source_refcouncil_noterecord_statusunit_definitionfinance_questionrate_evidence_note
C01Discovery and designone_offProjectUnknown / not suppliedUnknown / not suppliedUnknown / not suppliedUnknownUnknown / not suppliedInclude council and supplier effort separately.Unpriced templateOne project-level charge, with council and supplier effort recorded as separate lines.Which of this effort is bought from suppliers and which is internal staff time?Record date, scope, billing basis, term, inclusions, exclusions and VAT basis.
C02Site surveys and permissionsone_offPer affected siteUnknown / not suppliedUnknown / not suppliedUnknown / not suppliedUnknownUnknown / not suppliedInclude rural access listed buildings wayleaves and civil works where relevant.Unpriced templateOne charge per affected site, including permissions and any civil works.Which sites have access or permission constraints, and who funds exceptional works?Record date, scope, billing basis, term, inclusions, exclusions and VAT basis. Separate standard surveys from exceptional works.
C03Appliances and sparesone_offPer site or deviceUnknown / not suppliedUnknown / not suppliedUnknown / not suppliedUnknownUnknown / not suppliedSeparate purchases from rental included in recurring charges.Unpriced templateOne charge per site or device, purchased. Rental belongs in a recurring line.Will the council buy or rent equipment, and how will it be capitalised?Record date, scope, billing basis, term, inclusions, exclusions and VAT basis. State whether purchased or rented.
C04Licencesrecurring_monthlyPer licence or siteUnknown / not suppliedUnknown / not suppliedUnknown / not suppliedUnknownUnknown / not suppliedCheck security and support inclusions to avoid double counting.Unpriced templateCharge per licence or site, per month.Does the licence include security and support, so nothing is counted twice?Record date, scope, billing basis, term, inclusions, exclusions and VAT basis. Convert annual licences to months before summing.
C05Primary access circuitsrecurring_monthlyPer circuitUnknown / not suppliedUnknown / not suppliedUnknown / not suppliedUnknownUnknown / not suppliedRecord bandwidth site and contractual availability.Unpriced templateCharge per circuit, per month, with bandwidth, site and contractual availability noted.Are circuits billed monthly, quarterly or annually, and what is the minimum term?Record date, scope, billing basis, term, inclusions, exclusions and VAT basis. Note bandwidth and site.
C06Backup access circuitsrecurring_monthlyPer circuitUnknown / not suppliedUnknown / not suppliedUnknown / not suppliedUnknownUnknown / not suppliedDo not imply shared infrastructure is physically diverse.Unpriced templateCharge per backup circuit, per month.Is each backup circuit physically diverse from its primary, and is that evidenced?Record date, scope, billing basis, term, inclusions, exclusions and VAT basis. Do not assume shared infrastructure is diverse.
C07Managed operationsrecurring_monthlyProject or siteUnknown / not suppliedUnknown / not suppliedUnknown / not suppliedUnknownUnknown / not suppliedAlign monitoring changes support hours and fault ownership.Unpriced templateCharge per project or site, per month, covering monitoring, changes, support hours and fault ownership.Which operating model does this charge assume?Record date, scope, billing basis, term, inclusions, exclusions and VAT basis. State support hours.
C08Migration and installationone_offPer wave or siteUnknown / not suppliedUnknown / not suppliedUnknown / not suppliedUnknownUnknown / not suppliedSeparate standard installation exceptional works and rollback effort.Unpriced templateCharge per wave or per site, split into standard installation, exceptional works and rollback effort.Is rollback effort included in the quoted price?Record date, scope, billing basis, term, inclusions, exclusions and VAT basis.
C09Dual runningoverlap_monthlyPer overlapping serviceUnknown / not suppliedUnknown / not suppliedUnknown / not suppliedUnknownUnknown / not suppliedUse actual overlap period and only incremental costs not counted elsewhere.Unpriced templateIncremental monthly charge for each overlapping service, for the actual overlap period only.What overlap period has the council actually assumed?Record date, scope, billing basis, term, inclusions, exclusions and VAT basis. Count only costs not already in recurring lines.
C10Incumbent exit chargesone_offPer contractUnknown / not suppliedUnknown / not suppliedUnknown / not suppliedUnknownUnknown / not suppliedDo not add full old-service cost again if already in dual running.Unpriced templateOne charge per incumbent contract.Is any exit charge already included in dual running?Record date, scope, billing basis, term, inclusions, exclusions and VAT basis. Do not add the full old-service cost again.
C11Training and council staff timeone_offHours or daysUnknown / not suppliedUnknown / not suppliedUnknown / not suppliedUnknownUnknown / not suppliedKeep cash spend and internal opportunity cost separately labelled.Unpriced templateHours or days of training and staff time, with cash spend and internal opportunity cost labelled separately.Does finance want internal staff time in the schedule or only in the business case?Record date, scope, billing basis, term, inclusions, exclusions and VAT basis. Label cash and opportunity cost separately.
C12Power LAN and wireless dependenciesone_offPer affected siteUnknown / not suppliedUnknown / not suppliedUnknown / not suppliedUnknownUnknown / not suppliedOnly include work required by the council refresh scope.Unpriced templateOne charge per affected site, limited to work the refresh needs.Who funds LAN, power or wireless work that benefits other projects?Record date, scope, billing basis, term, inclusions, exclusions and VAT basis.
C13Ongoing support renewalsrecurring_annualProject or deviceUnknown / not suppliedUnknown / not suppliedUnknown / not suppliedUnknownUnknown / not suppliedCheck included licence support before adding another charge.Unpriced templateAnnual charge per project or device. Check included licence support first.Is support included in the licence charge, so nothing is counted twice?Record date, scope, billing basis, term, inclusions, exclusions and VAT basis. Convert to a common period before summing.
C14Reorganisation or estate changesoptionalPer changeUnknown / not suppliedUnknown / not suppliedUnknown / not suppliedUnknownUnknown / not suppliedState additions removals assignment and separation assumptions.Unpriced templateCharge per change, such as adding, removing, assigning or separating a site.Which estate changes does the council expect during the term?Record date, scope, billing basis, term, inclusions, exclusions and VAT basis. Optional lines are never included in the priced subtotal by default.
C15End of term exit assistanceone_offProjectUnknown / not suppliedUnknown / not suppliedUnknown / not suppliedUnknownUnknown / not suppliedPrice exports transition and access removal.Unpriced templateOne charge per project for exports, transition and access removal.Is end-of-term exit assistance priced now or at exit?Record date, scope, billing basis, term, inclusions, exclusions and VAT basis.
C16ContingencyallowanceDefined eligible subtotalUnknown / not suppliedUnknown / not suppliedUnknown / not suppliedUnknownUnknown / not suppliedCouncil finance chooses basis percentage and exclusions.Unpriced templateA percentage or amount applied to a defined eligible subtotal.What percentage, basis and exclusions does finance want?State the eligible subtotal, percentage and exclusions. Never include in the subtotal it is calculated on.
RFP questions / 32 records
question_idareasupplier_questionevidence_requestedcouncil_reasonapplies_whenexisting_question_idmapping_statusauthor_statusplanner_sectionrfp_stage_useresponse_formatharry_review_note
Q01EstateConfirm coverage and delivery dependencies for each council site without substituting assumed access availability.Site-by-site coverage and survey exceptions.Rural depots and civic buildings can have different access constraints.All council refresh projects. Site list required.Unknown / not suppliedRobert to confirm existing bank matchReady for editorial reviewM04Early market engagement and priced RFPSite-by-site schedule with exceptionsApplies_when made explicit (supplied value was All council refresh projects).
Q02ContinuityExplain how revenues and benefits applications and agreed out-of-hours duty services will continue during each migration wave.Application dependency map and service-owner sign-off plan.Office connectivity alone does not prove resident-service continuity.All council refresh projects. The duty-service element applies only where the council runs out-of-hours duty services.Unknown / not suppliedRobert to confirm existing bank matchReady for editorial reviewM03Early market engagement and priced RFPNarrative plus wave-by-wave service continuity tableApplies_when made explicit (supplied value was All council refresh projects).
Q03DependenciesIdentify retained PSN and partner connections and how they will coexist with the proposed design.Connectivity dependencies and owner-approved transition plan.Do not remove a required restricted-service path.When PSN or restricted partner dependency is Yes or Unknown (I11).Unknown / not suppliedRobert to confirm existing bank matchReady for editorial reviewM05Early market engagement and priced RFPDependency table plus transition narrativeApplies_when made explicit (supplied value was All council refresh projects).
Q04Shared servicesExplain responsibility boundaries across participating councils and how permissions and reporting remain separate.Responsibility matrix and administration model.Shared infrastructure must preserve each council's accountability.When shared service is Yes or Unknown (I12).Unknown / not suppliedRobert to confirm existing bank matchReady for editorial reviewM09Early market engagement and priced RFPResponsibility matrix per participating councilCouncil_reason apostrophe fix only; applies_when made explicit (supplied value was All council refresh projects).
Q05ReorganisationExplain how sites licences data access and contracts can transfer or separate during the stated reorganisation.Transition assumptions transfer restrictions and charges.A long-term service may outlast the present authority structure.When reorganisation is Yes or Unknown (I12). Do not apply to councils not affected.Unknown / not suppliedRobert to confirm existing bank matchReady for editorial reviewM02Early market engagement and priced RFPNarrative plus list of transfer restrictions and chargesApplies_when made explicit (supplied value was All council refresh projects).
Q06ResilienceDemonstrate physical diversity for the proposed primary and backup links at each essential site.Route and exchange information subject to controlled disclosure.Two retail suppliers may share a failure domain.Sites classed as council defined essential (I20).Unknown / not suppliedRobert to confirm existing bank matchReady for editorial reviewM06Early market engagement and priced RFPPer-site route and exchange statementApplies_when made explicit (supplied value was All council refresh projects).
Q07ResiliencePropose and witness a circuit failure test against the council's stated maximum service interruption.Test method application probes and pass fail results.Failover must preserve the named council service.Sites classed as council defined essential, with an interruption target entered (I21).Unknown / not suppliedRobert to confirm existing bank matchReady for editorial reviewM06Priced RFPTest plan with pass and fail criteriaSupplier_question apostrophe fixes only; applies_when made explicit (supplied value was All council refresh projects).
Q08ResilienceDescribe backup power capacity maintenance and recovery for the specified sites.Power dependencies runtime basis and test schedule.Mobile backup cannot help when site equipment has no power.Where sites have mobile backup, rural or difficult access, or limited power.Unknown / not suppliedRobert to confirm existing bank matchReady for editorial reviewM06Early market engagement and priced RFPPer-site power statement with test scheduleApplies_when made explicit (supplied value was All council refresh projects).
Q09Rural accessValidate mobile backup availability and performance at rural depots or other difficult sites.Site survey and tests under expected load.Coverage maps do not establish usable backup service.Where rural or difficult-access sites are in scope (I22).Unknown / not suppliedRobert to confirm existing bank matchReady for editorial reviewM06Early market engagement and priced RFPPer-site survey result and load testApplies_when made explicit (supplied value was All council refresh projects).
Q10SegmentationShow how council staff library public access contractors CCTV and building systems are isolated where in scope.Policy design and segmentation acceptance tests.Public access and operational systems have different trust boundaries.Where libraries, public access, CCTV or building systems are in scope.Unknown / not suppliedRobert to confirm existing bank matchReady for editorial reviewM07Early market engagement and priced RFPSegmentation design plus acceptance testsApplies_when made explicit (supplied value was All council refresh projects).
Q11ApplicationsConfirm performance and routing for the council's named Azure, Microsoft 365 and retained hosted applications.Application test results under normal and degraded connectivity.Supplier dashboard health does not establish usable council applications.Where Azure, Microsoft 365 or retained hosted applications are in scope.Unknown / not suppliedRobert to confirm existing bank matchReady for editorial reviewM05Priced RFPApplication test results tableSupplier_question apostrophe fixes only; applies_when made explicit (supplied value was All council refresh projects).
Q12IdentityExplain access administration and emergency access arrangements for council and supplier staff.Role model MFA access reviews and break glass procedure.Council retains accountable control of privileged access.All council refresh projects.Unknown / not suppliedRobert to confirm existing bank matchReady for editorial reviewM07Early market engagement and priced RFPRole model and procedure summaryWording unchanged.
Q13LoggingState what user and network data is collected where it is processed retention and supplier access.Data-flow summary retention controls and processor information.Security lead and DPO need evidence for the actual processing.All council refresh projects.Unknown / not suppliedRobert to confirm existing bank matchReady for editorial reviewM07Early market engagement and priced RFPData-flow summaryWording unchanged.
Q14AssuranceProvide the evidence requested by our security team for the council CAF improvement actions in scope.Control evidence linked to council actions and evidence owners.A product purchase does not deliver organisational assurance.Where the council has CAF improvement actions that this project could evidence.Unknown / not suppliedRobert to confirm existing bank matchReady for editorial reviewM07Priced RFPEvidence mapped to named council actionsApplies_when made explicit (supplied value was All council refresh projects).
Q15OperationsState who owns a fault spanning circuit appliance cloud policy and third-party application.RACI incident workflow and escalation example.Avoid incidents passed between contracted parties.Co managed or fully managed models (I14), and Undecided.Unknown / not suppliedRobert to confirm existing bank matchReady for editorial reviewM09Early market engagement and priced RFPRACI table plus incident exampleApplies_when made explicit (supplied value was All council refresh projects).
Q16OperationsDescribe monitoring and support during the council's specified out-of-hours service periods.Support coverage and escalation commitments with exclusions.Duty services may run outside office hours.Where the council runs out-of-hours duty services.Unknown / not suppliedRobert to confirm existing bank matchReady for editorial reviewM06Early market engagement and priced RFPSupport coverage table with exclusionsSupplier_question apostrophe fixes only; applies_when made explicit (supplied value was All council refresh projects).
Q17ChangesState which changes the council can make and which are charged or subject to supplier approval.Change catalogue permissions service windows and charges.A co-managed offer must preserve the council's needed authority.Co managed or fully managed models (I14), and Undecided.Unknown / not suppliedRobert to confirm existing bank matchReady for editorial reviewM09Early market engagement and priced RFPChange catalogue with permissions and chargesSupplier_question apostrophe fixes only; council_reason apostrophe fix only; applies_when made explicit (supplied value was All council refresh projects).
Q18Service levelsSeparate incident response restoration and resolution commitments by priority and service boundary.Contractual service schedule with measurement and exclusions.Fast acknowledgement does not establish fast recovery.All council refresh projects.Unknown / not suppliedRobert to confirm existing bank matchReady for editorial reviewM06Priced RFPService schedule table by priorityWording unchanged.
Q19Service levelsExplain credit calculations caps claim deadlines and planned maintenance exclusions.Applicable contract wording and example claim calculation.Marketing uptime percentages are not a complete contractual comparison.Priced RFP stage only.Unknown / not suppliedRobert to confirm existing bank matchReady for editorial reviewM08Priced RFPContract wording plus worked claim exampleApplies_when made explicit (supplied value was All council refresh projects).
Q20CostsPrice the same site list, term and service responsibilities using the council's cost schedule.Itemised one-off recurring and optional charges in GBP with VAT basis.Enables finance to compare equal scope.Priced RFP stage only. Requires the council's cost schedule.Unknown / not suppliedRobert to confirm existing bank matchReady for editorial reviewM08Priced RFPCouncil cost schedule completed in GBP with VAT basisSupplier_question apostrophe fixes only; applies_when made explicit (supplied value was All council refresh projects).
Q21CostsState overlap charges termination charges installation dependencies and delayed-delivery costs.Priced transition schedule with assumptions.Dual running can erase an apparent annual saving.Priced RFP stage, and any early engagement where an incumbent is being replaced.Unknown / not suppliedRobert to confirm existing bank matchReady for editorial reviewM08Priced RFPPriced transition scheduleApplies_when made explicit (supplied value was All council refresh projects).
Q22CostsState indexation review dates minimum commitments and costs to add remove or transfer sites.Commercial formula worked example and change charges.Estate consolidation and reorganisation can alter costs.Priced RFP stage. Priority where estate consolidation or reorganisation is expected.Unknown / not suppliedRobert to confirm existing bank matchReady for editorial reviewM08Priced RFPFormula, worked example and change chargesApplies_when made explicit (supplied value was All council refresh projects).
Q23DeliveryProvide a dependency-led plan around the council's listed elections, payments and change restrictions.Milestones dependencies owner and lead-time assumptions.Protect council-specific service windows.All council refresh projects. Uses the council's blackout dates (I19).Unknown / not suppliedRobert to confirm existing bank matchReady for editorial reviewM11Early market engagement and priced RFPMilestone plan with owners and lead-time assumptionsSupplier_question apostrophe fixes only; applies_when made explicit (supplied value was All council refresh projects).
Q24PilotPropose a representative pilot including an essential-service site and a difficult access site where appropriate.Pilot selection rationale and acceptance evidence.A straightforward office pilot can miss the highest risks.All council refresh projects. Difficult-access site only where one exists.Unknown / not suppliedRobert to confirm existing bank matchReady for editorial reviewM11Early market engagement and priced RFPPilot proposal with selection rationaleApplies_when made explicit (supplied value was All council refresh projects).
Q25RollbackState rollback triggers responsible officers and the last reversible point for each cutover.Runbook and witnessed recovery test.Council service owners must know when to stop a change.All council refresh projects.Unknown / not suppliedRobert to confirm existing bank matchReady for editorial reviewM11Priced RFPRunbook extract plus test planWording unchanged.
Q26ExitDescribe configuration and log exports licence ownership access revocation and transition assistance at exit.Exit plan format and priced assistance.The next refresh must not depend on an inaccessible management tenant.All council refresh projects.Unknown / not suppliedRobert to confirm existing bank matchReady for editorial reviewM11Early market engagement and priced RFPExit plan format with priced assistanceWording unchanged.
Q27EvidenceProvide comparable council references distinguishing your contracted scope from partner-delivered work.Named references dates estate scope and permission for checks.A generic public-sector logo does not establish relevant delivery.Priced RFP stage only.Unknown / not suppliedRobert to confirm existing bank matchReady for editorial reviewM12Priced RFPReference list with scope notesApplies_when made explicit (supplied value was All council refresh projects).
Q28SubcontractorsIdentify who supplies and supports the access network and any management subcontractors.Supply chain roles escalation and change notification commitments.Council needs a clear chain of accountability.Co managed or fully managed models (I14), and any incumbent with subcontractors.Unknown / not suppliedRobert to confirm existing bank matchReady for editorial reviewM09Early market engagement and priced RFPSupply chain tableApplies_when made explicit (supplied value was All council refresh projects).
Q29TrainingDescribe handover training, documentation and the council's ongoing staffing responsibilities.Training plan operating documentation and role expectations.A small council team must be able to operate the agreed model.Co managed or fully managed models (I14), and Undecided.Unknown / not suppliedRobert to confirm existing bank matchReady for editorial reviewM09Early market engagement and priced RFPTraining and documentation planSupplier_question apostrophe fixes only; applies_when made explicit (supplied value was All council refresh projects).
Q30TelecareIdentify any affected telecare alarms and building systems and your scope of testing alongside their service owner.Separate dependency assessment and device-owner test approval.Network migration does not prove device compatibility or safety.When telecare or building systems are Yes or Unknown (I13).Unknown / not suppliedRobert to confirm existing bank matchReady for editorial reviewM05Early market engagement and priced RFPDependency list plus testing scopeApplies_when made explicit (supplied value was All council refresh projects).
Q31AccessibilityDescribe accessibility of the management portal reports and support routes used by council staff.Accessibility evidence and known limitations.Council users need usable interfaces and alternative formats.All council refresh projects where staff use a supplier portal.Unknown / not suppliedRobert to confirm existing bank matchReady for editorial reviewM07Early market engagement and priced RFPAccessibility statement and known limitationsApplies_when made explicit (supplied value was All council refresh projects).
Q32SustainabilityState equipment reuse secure disposal energy and site-visit assumptions relevant to this project.Project-specific evidence and priced options.Council sustainability assessment should use actual delivery assumptions.Where the council's sustainability assessment will use this project's data.Unknown / not suppliedRobert to confirm existing bank matchReady for editorial reviewM08Priced RFPAssumptions list with priced optionsApplies_when made explicit (supplied value was All council refresh projects).
Decision rules / 12 records
rule_idtriggershow_actiondo_not_inferreview_ownerrelated_idsrule_statusmessage_copy
R01Nation is unknownAsk the council procurement lead to confirm nation and arrangement.Do not suggest a final route.Procurement leadI01;I18Editorial rule proposedYour nation is unconfirmed. Ask your council procurement lead to confirm your nation and procurement arrangement. No route is suggested until they do.
R02Nation is ScotlandShow Scottish procurement references and request council route approval.Do not default to the Procurement Act route for English councils.Procurement leadI01Editorial rule proposedYou've selected Scotland, so we're showing Scottish procurement references. Ask your procurement lead to confirm the route your council approves.
R03Nation is Wales or Northern IrelandShow the relevant nation-specific review instruction and arrangement caveat.No automatic English notice sequence.Procurement leadI01;I18Editorial rule proposedYou've selected Wales or Northern Ireland, so we're showing the review instruction for your nation. Ask your procurement lead to confirm applicable rules, because an English notice sequence may not apply.
R04PSN dependency is Yes or UnknownAdd retained-services assessment and question Q03.Do not recommend retiring that connection.Service owner and security leadI11Editorial rule proposedConfirm which services still depend on PSN or a restricted partner connection before planning to remove legacy links. Question Q03 has been added to your set.
R05Shared-service or reorganisation dependency is Yes or UnknownAdd ownership transfer separation and contract-change questions.No assumed whole-UK reorganisation requirement.Programme lead and procurementI12Editorial rule proposedA shared service or reorganisation may affect this contract. Questions on ownership, transfer, separation and contract change have been added. Ask your programme lead and procurement team to review them.
R06Telecare dependency is Yes or UnknownRequest device-owner dependency assessment before affected cutover.No assurance that SD-WAN fixes analogue device risks.Relevant service ownerI13Editorial rule proposedTelecare or building systems may depend on this network. Ask the device owner for a dependency assessment before any affected site is cut over. A network change doesn't make an analogue device safe.
R07Contract or notice deadline is missingRequest the relevant contract terms and retain an unconfirmed date.No promised migration completion date.Contract ownerI06;I07Editorial rule proposedYour contract deadline is unconfirmed. Ask the contract owner for the end date, notice period and any extension options.
R08An essential-service site has no acceptable interruption or acceptance testRequest service-owner targets and representative test.No ready-to-issue claim.Service ownerI20;I21Editorial rule proposedAsk the service owner to agree acceptable interruption and a witnessed application test before this site enters a migration wave.
R09A cost quantity rate term or required line is missingShow priced subtotal and missing items separately.No complete budget total or savings percentage.Finance leadI15;I16;I23Editorial rule proposedThis schedule contains unpriced items. Review the missing rates before using a complete project total.
R10Council has not approved supplier-facing summaryKeep private preparation and review actions available.Do not publish or approach suppliers.Authorised council buyerI25;I26Editorial rule proposedKeep preparing your private draft. Review the supplier-facing summary and your council's procurement route before requesting responses.
R11Evidence is search-only missing or out of dateRetain as research lead and request full-page confirmation.Exclude from published factual claims and supplier scoring.Harry and editorS04;S05Editorial rule proposedInternal editorial rule, not shown to users. Keep this item as a research lead and confirm it against the full page before using any detail from it.
R12User has not confirmed an operating modelProduce responsibility comparison questions.No inferred fully managed preference.IT leadI14Editorial rule proposedYou haven't confirmed an operating model. We've added responsibility comparison questions so every bidder answers in the same table.
Delivery tasks / 10 records
task_iddeliverableassignmentscopeacceptanceownerstatusopen_items
T01Page manuscriptWrite complete council-specific copy following M01 to M15.About 6150 words plus structured tool copy; no filler to meet count.All modules present with source references.HarryReady for editorial reviewM02, M12, M13, M14 need verification or product confirmation: OQ01 to OQ03, OQ09, OQ11. Word counts are close to targets, prose plus tables.
T02Planner copyWrite every input label help message unknown state action and output label.26 inputs and all 12 rule messages; extend only for a clear council need.No assumed facts and no automatic compliance verdict.HarryReady for editorial reviewAll 26 inputs and 12 rule messages written. Proposed Decision rules column message_copy. OQ01, OQ19.
T03Evidence recordsRecheck seeded cases and add comparable council primary records.At least 6 fully verified records across 3 nations if available; explain gaps.Distinguish decision tender award and delivered outcome.HarryRequires verification7 council records across England, Scotland and Northern Ireland, no Wales record (OQ11). Enfield primary page not re-opened (OQ09). Cheshire East award verified (S32). East Riding awards verified (S36, S37). Award or outcome unverified for CASE04 and CASE07, and delivery for CASE05 and CASE06 (OQ12 to OQ15).
T04Supplier questionsReview the 32 proposed questions and link each to council purpose.32 complete rows; relevant conditions explicit.No unsupported targets or arbitrary vendor rankings.HarryReady for editorial review32 rows reviewed. Applicability conditions made explicit, stage labels and response formats proposed, apostrophe fixes on 10 rows. Mapping to bank left blank (OQ07).
T05Cost dataComplete category explanations and research usable rates only if available.16 seeded categories; no invented rate defaults.Every real rate carries scope date term VAT and source.HarryReady for editorial review16 categories completed with unit definitions and finance questions. No defensible published unit rates, so all amounts blank (OQ18).
T06Route notesWrite nation-specific procurement research notes.4 nations plus applicable framework and transitional caveats.Council procurement review remains explicit.HarryReady for editorial reviewP01 to P04 written with dated primary references. Council procurement lead review still required. Re-check dates before publication (OQ10, OQ17).
T07Output examplesWrite fictional council scenario and all four planner outputs.One worked 24-site example plus 3 changed-input examples.Clearly illustrative with no fictional market prices.HarryReady for editorial reviewIllustrative council scenario, four outputs and three changed-input examples written in the manuscript. Placement is OQ20.
T08Final handoverReturn Word manuscript and one completed structured workbook.Preserve row IDs and one record per row.All unresolved facts logged; no hidden tabs or merged data cells.HarryReady for editorial reviewWorkbook and manuscript returned. Hidden tabs none, merged data cells none, IDs preserved. Open questions sheet added.
T09Product confirmationConfirm council handoff summary and optional supplier response destination.Current RFP flow and actual supplier access.No promises based on conflicting older copy.RobertNot startedUnknown / not supplied
T10Question mappingMap proposed council questions onto existing governed bank.Existing IDs where exact match; new wording reviewed.Do not invent live question IDs.RobertNot startedUnknown / not supplied
Evidence links / 102 records
link_idrecord_typerecord_idsource_idrelationshippublication_notesource_locationclaim_textclaim_review_status
L001Page moduleM01S19Editorial research basisVerify the specific factual sentence before publication.RFP builder page, project flow and FAQ sectionsNothing is published and no supplier receives anything unless the buyer reviews and approves it; a draft can be downloaded without an account or publication.Verified against full source on 21 Oct 2026. Planner storage behaviour is a product question (OQ19).
L002Page moduleM02S01Editorial research basisVerify the specific factual sentence before publication.Decision record, scope descriptionGreenwich's October 2026 procurement approval covers managed WAN, LAN, WiFi and firewall services.Verified against full source on 21 Oct 2026
L003Page moduleM02S02Editorial research basisVerify the specific factual sentence before publication.Decision record (description carried from brief)Enfield's April 2026 award decision ties its network refresh to legacy architecture and cloud connectivity.Re-check in browser before publication (primary page could not be re-opened)
L004Page moduleM02S14Editorial research basisVerify the specific factual sentence before publication.LGA publication landing page, summary of research focusTransfer and separation terms matter from day one where reorganisation applies.Editorial recommendation, not a source claim. Source supports the continuity-through-transition theme only; PDF report not opened.
L005Page moduleM03S12Editorial research basisVerify the specific factual sentence before publication.CAF for local government page, process stepsLocal Digital's CAF for local government starts by identifying the essential services and critical systems a council relies on.Verified against full source on 21 Oct 2026
L006Page moduleM03S03Editorial research basisVerify the specific factual sentence before publication.Notice description of requirementSouth Oxfordshire and Vale of White Horse's tender replaces the active network components of offices and buildings as part of an SD-WAN transition.Verified against full source on 21 Oct 2026
L007Page moduleM04S03Editorial research basisVerify the specific factual sentence before publication.Notice, price breakdown requirement (items a to d)Bidders were asked to price hardware per site, five-year licence and support, installation and configuration per site, and ongoing annual support separately.Verified against full source on 21 Oct 2026
L008Page moduleM04S14Editorial research basisVerify the specific factual sentence before publication.LGA publication landing pageA reorganisation or split can move sites, contracts and licences between authorities.Editorial recommendation, not a source claim. Source page does not address contracts or licences specifically; PDF report not opened.
L009Page moduleM05S11Editorial research basisVerify the specific factual sentence before publication.PSN compliance page, certificate typesPSN-connected organisations hold compliance certificates for connection, service provision or connectivity.Verified against full source on 21 Oct 2026
L010Page moduleM05S03Editorial research basisVerify the specific factual sentence before publication.Notice, security appliance requirementThe tender requires security appliances to support site-to-site VPN into Microsoft Azure for each site.Verified against full source on 21 Oct 2026
L011Page moduleM06S12Editorial research basisVerify the specific factual sentence before publication.CAF for local government page, process stepsCAF for local government focuses on essential services and critical systems.Verified against full source on 21 Oct 2026
L012Page moduleM06S01Editorial research basisVerify the specific factual sentence before publication.Decision record, delivery descriptionGreenwich's approval combines on-site engineers with back-office monitoring and support.Verified against full source on 21 Oct 2026
L013Page moduleM07S11Editorial research basisVerify the specific factual sentence before publication.PSN compliance pageOrganisations using PSN need a valid compliance certificate and remain responsible for meeting their own obligations.Verified against full source on 21 Oct 2026
L014Page moduleM07S12Editorial research basisVerify the specific factual sentence before publication.CAF for local government pageThe CAF for local government is voluntary, begins with essential services and critical systems, and includes an independent assurance review.Verified against full source on 21 Oct 2026
L015Page moduleM07S13Editorial research basisVerify the specific factual sentence before publication.14 January 2026 news itemBy January 2026, 90 councils had completed a CAF assessment, and the programme is moving to CAF version 4.0 and a web application.Verified against full source on 21 Oct 2026
L016Page moduleM07S15Editorial research basisVerify the specific factual sentence before publication.ICO DPIA guidance, Article 35 sections and review noticeA DPIA is needed where processing is likely to result in high risk, and systematic monitoring of a publicly accessible area on a large scale is listed. The ICO guidance is under review following the Data (Use and Access) Act.Verified against full source on 21 Oct 2026
L017Page moduleM08S03Editorial research basisVerify the specific factual sentence before publication.Notice, value fieldThe South Oxfordshire and Vale of White Horse notice displays a value of GBP0.Verified against full source on 21 Oct 2026
L018Page moduleM08S01Editorial research basisVerify the specific factual sentence before publication.Decision record, value, term and scopeGreenwich's approval carries an estimated GBP16 million over a term of up to ten years and covers managed WAN, LAN, WiFi and firewall services, so it is not an SD-WAN price.Verified against full source on 21 Oct 2026. VAT basis not stated on the page.
L019Page moduleM09S01Editorial research basisVerify the specific factual sentence before publication.Decision record, delivery descriptionGreenwich's approval pairs on-site engineers with back-office monitoring.Verified against full source on 21 Oct 2026
L020Page moduleM09S14Editorial research basisVerify the specific factual sentence before publication.LGA publication landing pageShared-service governance and what happens if a partner leaves need to be set out.Editorial recommendation, not a source claim. Source supports the transition-continuity theme only.
L021Page moduleM10S06Editorial research basisVerify the specific factual sentence before publication.GCA agreement page, lot table and update notesAs at 21 October 2026 Network Services 3 (RM6116) is a PCR2015 framework; lot 1a covers WAN, lot 2a covers LAN; most lots end 17 July 2027 and lots 1c and 1d end 22 May 2027.Verified against full source on 21 Oct 2026 at gca.gov.uk (listed URL redirects)
L022Page moduleM10S07Editorial research basisVerify the specific factual sentence before publication.Cabinet Office guidance, paras 16, 17 and 24Devolved Scottish authorities are generally excluded from the Procurement Act; Northern Ireland authorities are regulated by it with some differences; cross-border arrangements can change which regime applies.Verified against full source on 21 Oct 2026
L023Page moduleM10S08Editorial research basisVerify the specific factual sentence before publication.Cabinet Office PME guidance, notice requirements and unfair advantage sectionsEngagement before a tender must not give any supplier an unfair advantage, and where an authority engages the market above threshold it publishes a preliminary market engagement notice or explains in the tender notice why it did not.Verified against full source on 21 Oct 2026. Guidance updated 13 July 2026.
L024Page moduleM10S09Editorial research basisVerify the specific factual sentence before publication.Welsh Government guidance collectionWelsh authorities should use the Welsh Government's guidance and notice sequencing.Verified against full source on 21 Oct 2026. Page's update date conflicts with some listed guidance dates (OQ17).
L025Page moduleM10S10Editorial research basisVerify the specific factual sentence before publication.Scottish Procurement Policy Handbook, legislation sectionScottish public procurement follows the Procurement Reform (Scotland) Act 2014 and the Public Contracts (Scotland) Regulations 2015.Verified against full source on 21 Oct 2026
L026Page moduleM11S02Editorial research basisVerify the specific factual sentence before publication.n/aNo sentence in M11 relies on S02.Not cited in manuscript copy. Research basis only. Propose removing this link (OQ22).
L027Page moduleM11S03Editorial research basisVerify the specific factual sentence before publication.Notice, price breakdown item cThe tender asks for installation and configuration per site as a priced line.Verified against full source on 21 Oct 2026
L028Page moduleM11S14Editorial research basisVerify the specific factual sentence before publication.LGA publication landing pageContinuity through organisational change is what the LGA's reorganisation research centres on.Verified against full source on 21 Oct 2026 (landing page only)
L029Page moduleM12S01Editorial research basisVerify the specific factual sentence before publication.Decision record, whole pageGreenwich approved procurement of a network managed services contract on 1 October 2026 covering managed inter-building and intra-building networks, internet and wireless services and firewalls, with on-site engineers and back-office monitoring; a WAN and LAN hardware refresh is already in train; the estimated GBP16 million is over up to ten years; it is an approval not an award.Verified against full source on 21 Oct 2026
L030Page moduleM12S02Editorial research basisVerify the specific factual sentence before publication.Decision record (description carried from brief)Enfield awarded a network refresh in April 2026 that addresses legacy architecture and cloud connectivity; no price or delivery outcome is established.Re-check in browser before publication (primary page could not be re-opened)
L031Page moduleM12S03Editorial research basisVerify the specific factual sentence before publication.Notice, whole pageSouth Oxfordshire and Vale of White Horse published a joint tender on 20 December 2024 for LAN, wireless and security refresh supporting a transition to SD-WAN; it is closed with no award shown; the GBP0 value is unusable.Verified against full source on 21 Oct 2026
L032Page moduleM12S04Editorial research basisVerify the specific factual sentence before publication.Decision record, whole pageAdur and Worthing recorded a decision on 29 September 2026 to direct award migration of fibre networking across 22 council sites to SD-WAN over CityFibre using a commercial ISP, under the SBS DWS2 framework.Verified against full source on 21 Oct 2026. Status For Determination with call-in (OQ13).
L033Page moduleM12S05Editorial research basisVerify the specific factual sentence before publication.Tender notice 081392-2025 and 082060-2025East Riding published a tender notice in December 2025 for a Cisco-based SD-WAN solution and separately a WAN connectivity tender.Verified against full source on 21 Oct 2026. Deadline conflict in the notice (OQ14).
L034Page moduleM13S19Editorial research basisVerify the specific factual sentence before publication.RFP builder pageThe builder produces a private draft that can be downloaded without an account or publication, and its checker does not certify that an RFP is ready to issue.Verified against full source on 21 Oct 2026
L035Page moduleM13S08Editorial research basisVerify the specific factual sentence before publication.Cabinet Office PME guidanceProcurement responsibility for notices and approvals stays with the council.Verified against full source on 21 Oct 2026
L036Page moduleM14S19Editorial research basisVerify the specific factual sentence before publication.RFP builder page, fees and FAQ textSuppliers pay Netify when an introduction leads to business, and this does not affect how providers are ordered; optional responses follow review.Verified against full source on 21 Oct 2026. Approved disclosure wording to be confirmed by Robert (OQ06).
L037Page moduleM14S20Editorial research basisVerify the specific factual sentence before publication.n/aNo sentence in M14 relies on S20.Not cited in manuscript copy. Research basis only. Live page conflicts with brief (OQ04).
L038Page moduleM14S21Editorial research basisVerify the specific factual sentence before publication.n/aNo sentence in M14 relies on S21.Not cited in manuscript copy. Research basis only. Conflicts logged (OQ05).
L039Page moduleM15S06Editorial research basisVerify the specific factual sentence before publication.GCA agreement pageAs at 21 October 2026 Network Services 3 is a PCR2015 framework; lot 1a covers WAN and lot 2a covers LAN; most lots end on 17 July 2027.Verified against full source on 21 Oct 2026 at gca.gov.uk
L040Page moduleM15S07Editorial research basisVerify the specific factual sentence before publication.Cabinet Office guidance, para 24Devolved Scottish authorities are generally excluded from the Procurement Act.Verified against full source on 21 Oct 2026
L041Page moduleM15S11Editorial research basisVerify the specific factual sentence before publication.PSN compliance pagePSN is a compliance and connection arrangement and a certificate does not show whether a service still needs a path.Verified against full source on 21 Oct 2026 for certificate types; the inference about legacy circuits is editorial.
L042Page moduleM15S14Editorial research basisVerify the specific factual sentence before publication.LGA publication landing pageReorganisation: ask for transfer, separation and assignment terms and what they cost.Editorial recommendation, not a source claim
L043Page moduleM15S17Editorial research basisVerify the specific factual sentence before publication.DHSC guidance for housing providers in England, introductionAnalogue telecare that is not upgraded may become unreliable or stop working during the digital phone switchover.Verified against full source on 21 Oct 2026. Guidance published 8 October 2026; does not mention local authorities.
L044Page moduleM15S19Editorial research basisVerify the specific factual sentence before publication.RFP builder pageThe RFP builder lets a user download a private draft without an account or publication; optional supplier responses follow review.Verified against full source on 21 Oct 2026
L045Council evidenceCASE01S01Primary project referenceUsable with scope limitationDecision record, whole pageGreenwich procurement approval, 1 Oct 2026, scope and estimated value as recorded.Verified against full source on 21 Oct 2026
L046Council evidenceCASE02S02Primary project referenceUsable with scope limitationDecision record (description carried from brief)Enfield award decision, April 2026, legacy architecture and cloud connectivity.Re-check in browser before publication (primary page could not be re-opened)
L047Council evidenceCASE03S03Primary project referenceUsable with scope limitationNotice, whole pageSouth Oxfordshire and Vale of White Horse joint closed tender, 20 Dec 2024, LAN, wireless and security refresh supporting SD-WAN transition; GBP0 shown.Verified against full source on 21 Oct 2026
L048Council evidenceCASE04S04Primary project referenceHold for full-page verificationDecision record, whole pageAdur and Worthing decision, 29 Sep 2026, 22 sites, SD-WAN over CityFibre, GBP129,918.43 plus VAT over 3 years, SBS DWS2 direct award.Verified against full source on 21 Oct 2026. Confirm implementation (OQ13).
L049Council evidenceCASE05S05Primary project referenceHold for full-page verificationTender notice, whole pageEast Riding tender notice 081392-2025 for a Cisco-based SD-WAN solution, estimated GBP3m excluding VAT.Verified against full source on 21 Oct 2026. Award notices are S36 and S37; deadline conflict logged (OQ14).
L050Page moduleM02S26Claim supportClaim-level link added by Harry.Council report C/6/25-26, shared service and recommendations paragraphsCheshire East's May 2025 report seeks separate contracts so a later split between the two councils does not force a novation.Verified against full source on 21 Oct 2026
L051Page moduleM05S11Claim supportClaim-level link added by Harry.PSN compliance page, whole pageNo PSN closure or transition date is published on the guidance page.Verified against full source on 21 Oct 2026. Page's visible last-updated date is 16 March 2016.
L052Page moduleM08S23Claim supportClaim-level link added by Harry.Article sections on SLAs and hidden costsNetify's contract terms article covers SLA structures and a hidden-cost checklist in general terms.Verified against full source on 21 Oct 2026
L053Page moduleM10S01Claim supportClaim-level link added by Harry.Decision record, procurement routeGreenwich approved an Open Procedure under the Procurement Act 2023.Verified against full source on 21 Oct 2026
L054Page moduleM10S26Claim supportClaim-level link added by Harry.Council report C/6/25-26, para 22Cheshire East's report proposes a mini-competition under Network Services 3 Lot 1a.Verified against full source on 21 Oct 2026
L055Page moduleM10S04Claim supportClaim-level link added by Harry.Decision record, route entryAdur and Worthing's decision is a direct award under the SBS DWS2 framework.Verified against full source on 21 Oct 2026
L056Page moduleM10S05Claim supportClaim-level link added by Harry.Tender notice, procedure sectionEast Riding's tender notice uses a competitive flexible procedure.Verified against full source on 21 Oct 2026
L057Page moduleM11S26Claim supportClaim-level link added by Harry.Council report C/6/25-26, paras 9 and 22Cheshire East's May 2025 report sought approval to procure a replacement for a contract expiring on 3 February 2026 and notes a two-year extension would carry at least 31.9% in inflation costs.Verified against full source on 21 Oct 2026
L058Page moduleM11S05Claim supportClaim-level link added by Harry.Tender notice, scope and duration sectionsEast Riding's tender notice expects the solution to be live by 1 April 2027 against an estimated contract start of 1 June 2026.Verified against full source on 21 Oct 2026
L059Page moduleM12S36Claim supportClaim-level link added by Harry.Award notice 056210-2026East Riding's June 2026 award notice for the SD WAN Solution names the supplier and a value excluding VAT.Verified against full source on 21 Oct 2026
L060Page moduleM12S37Claim supportClaim-level link added by Harry.Award notice 056223-2026East Riding's June 2026 award notice for WAN Connectivity names a separate supplier and value excluding VAT.Verified against full source on 21 Oct 2026
L061Page moduleM12S32Claim supportClaim-level link added by Harry.Award notice 047572-2025Cheshire East's August 2025 award notice follows its May 2025 report and uses Network Services 3 Lot 1a.Verified against full source on 21 Oct 2026
L062Page moduleM12S24Claim supportClaim-level link added by Harry.Tender notice 082060-2025East Riding published a separate Wide Area Network (WAN) Connectivity tender notice on 11 December 2025.Verified against full source on 21 Oct 2026
L063Page moduleM12S26Claim supportClaim-level link added by Harry.Council report C/6/25-26Cheshire East's council report of 14 May 2025 concerns SD-WAN connectivity for a shared ICT service via Network Services 3 Lot 1a, with separate contracts to avoid novation if the partners split.Verified against full source on 21 Oct 2026. Outcome not verified (OQ15).
L064Page moduleM12S27Claim supportClaim-level link added by Harry.Contract notice 009419-2022Ten Northern Ireland councils published a joint contract notice on 7 April 2022 for managed network services including WAN connectivity, firewalls and internet over new fibre, 120 months, open procedure.Verified against full source on 21 Oct 2026
L065Page moduleM12S29Claim supportClaim-level link added by Harry.Council news releaseHighland Council announced on 24 October 2023 a network services agreement under the Scottish Wide Area Network framework covering over 340 sites including some of the most challenging locations in Scotland.Verified against full source on 21 Oct 2026
L066Page moduleM13S22Claim supportClaim-level link added by Harry.Comparison page scope descriptionNetify's UK public sector comparison covers provider evidence.Verified against full source on 21 Oct 2026. Page has no council section.
L067Page moduleM14S08Claim supportClaim-level link added by Harry.Cabinet Office PME guidanceA sourcing request does not replace the council's procurement strategy, statutory notices, framework process or tender portal; preliminary engagement must treat suppliers fairly.Verified against full source on 21 Oct 2026
L068Page moduleM15S26Claim supportClaim-level link added by Harry.Council report C/6/25-26Cheshire East's May 2025 report on a contract expiring in February 2026 notes a two-year extension would carry at least 31.9% in inflation costs; the report seeks separate contracts to avoid novation if the partners split.Verified against full source on 21 Oct 2026
L069Page moduleM15S15Claim supportClaim-level link added by Harry.ICO DPIA guidanceLarge-scale systematic monitoring of public areas is a high-risk processing example in the ICO's DPIA guidance; the DPO decides whether a DPIA is needed.Verified against full source on 21 Oct 2026
L070Page moduleM15S29Claim supportClaim-level link added by Harry.Council news releaseHighland Council's 2023 agreement covers over 340 sites including some of the most challenging locations in Scotland and used the Scottish Wide Area Network framework.Verified against full source on 21 Oct 2026
L071Page moduleM15S16Claim supportClaim-level link added by Harry.DSIT guidanceThe digital phone switchover is due to complete by January 2027.Verified against full source on 21 Oct 2026
L072Page moduleM15S10Claim supportClaim-level link added by Harry.Scottish Procurement Policy HandbookScottish public procurement runs on its own legislation and handbook.Verified against full source on 21 Oct 2026
L073Page moduleM15S01Claim supportClaim-level link added by Harry.Decision recordGreenwich's estimated GBP16 million covers managed WAN, LAN, WiFi and firewall services over up to ten years.Verified against full source on 21 Oct 2026
L074Council evidenceCASE05S36Primary project referenceClaim-level link added by Harry.Contract award noticeEast Riding award notice 056210-2026, SD WAN Solution, Specialist Computer Centres PLC, GBP1,415,000 excluding VAT, 3 tenders.Verified against full source on 21 Oct 2026
L075Council evidenceCASE05S37Primary project referenceClaim-level link added by Harry.Contract award noticeEast Riding award notice 056223-2026, WAN Connectivity, KCOM Group Limited, GBP785,000 excluding VAT, 5 tenders.Verified against full source on 21 Oct 2026
L076Council evidenceCASE05S24Primary project referenceClaim-level link added by Harry.Tender notice, whole pageEast Riding WAN Connectivity tender notice 082060-2025, estimated GBP1.35m excluding VAT.Verified against full source on 21 Oct 2026
L077Council evidenceCASE05S25Primary project referenceClaim-level link added by Harry.Planned procurement noticeEast Riding planned procurement notice 069198-2025 for a Cisco based SD WAN solution.Verified against full source on 21 Oct 2026
L078Council evidenceCASE06S32Primary project referenceClaim-level link added by Harry.Contract award notice, section VCheshire East award notice 047572-2025, Virgin Media Ltd, GBP900,408 excluding VAT, concluded 7 Aug 2025, 3 tenders, Network Services 3 Lot 1a.Verified against full source on 21 Oct 2026
L079Council evidenceCASE06S26Primary project referenceClaim-level link added by Harry.Council report, paras 5, 9, 22, 27Cheshire East report C/6/25-26 of 14 May 2025, scope, route, extension cost, separate contracts.Verified against full source on 21 Oct 2026. Outcome not verified (OQ15).
L080Council evidenceCASE07S27Primary project referenceClaim-level link added by Harry.Contract notice, whole pageTen-council contract notice 009419-2022, 7 Apr 2022.Verified against full source on 21 Oct 2026
L081Council evidenceCASE07S28Supporting referenceClaim-level link added by Harry.Change notice, section IVChange notice 014671-2022 moving tender deadline from 9 to 23 June 2022.Verified against full source on 21 Oct 2026
L082Council evidenceCASE07S31Supplier-attributed leadClaim-level link added by Harry.Article textTrade press report of a supplier-announced ten-year contract for almost 600 sites.Excluded from public claims; council award notice not found (OQ12)
L083Council evidenceCASE08S29Primary project referenceClaim-level link added by Harry.Council news releaseHighland Council news release, 24 Oct 2023.Verified against full source on 21 Oct 2026
L084Route noteP01S06Primary referenceClaim-level link added by Harry.GCA agreement page, lot table and update notesRM6116 is a legacy PCR2015 framework; lot 1a WAN, lot 2a LAN; end dates 17 July 2027 and 22 May 2027; extended 12 March 2025 by 24 months.Verified against full source on 21 Oct 2026
L085Route noteP01S08Supporting referenceClaim-level link added by Harry.Cabinet Office PME guidancePreliminary market engagement notice or explanation in the tender notice above threshold; no unfair advantage.Verified against full source on 21 Oct 2026
L086Route noteP01S26ExampleClaim-level link added by Harry.Council report para 22Cheshire East proposes a mini-competition under Network Services 3 Lot 1a.Verified against full source on 21 Oct 2026
L087Route noteP02S10Primary referenceClaim-level link added by Harry.Scottish Procurement Policy HandbookProcurement Reform (Scotland) Act 2014 and Public Contracts (Scotland) Regulations 2015; handbook is not legal advice.Verified against full source on 21 Oct 2026
L088Route noteP02S07Supporting referenceClaim-level link added by Harry.Cabinet Office guidance para 24Devolved Scottish authorities generally excluded from the Act; joint award with a regulated authority applies the Act in its entirety.Verified against full source on 21 Oct 2026
L089Route noteP02S29ExampleClaim-level link added by Harry.Council news releaseHighland Council 2023 agreement under the Scottish Wide Area Network framework.Verified against full source on 21 Oct 2026
L090Route noteP03S09Primary referenceClaim-level link added by Harry.Welsh Government guidance collectionWelsh guidance collection: notice sequencing 16 June 2025, PME 4 December 2024, transitional arrangements 11 July 2024; Procurement (Wales) Regulations 2024.Verified against full source on 21 Oct 2026. Page dates inconsistent (OQ17).
L091Route noteP03S07Supporting referenceClaim-level link added by Harry.Cabinet Office guidance paras 16 and 17Welsh authorities regulated by the Act; cross-border arrangements follow the rules of the authority that set them up.Verified against full source on 21 Oct 2026
L092Route noteP03S30LeadClaim-level link added by Harry.Notice, archived version of 16 June 2025Welsh Government PSBA3 preliminary market engagement notice, 11 June 2025; later version dated 16 June 2026 not reviewed.Verified against full source on 21 Oct 2026 for the archived version only
L093Route noteP04S07Primary referenceClaim-level link added by Harry.Cabinet Office guidance paras 5 and 16Transferred Northern Ireland authorities are regulated by the Act with some differences.Verified against full source on 21 Oct 2026
L094Route noteP04S27ExampleClaim-level link added by Harry.Contract noticeTen Northern Ireland councils published a joint open-procedure contract notice on 7 April 2022.Verified against full source on 21 Oct 2026
L095Decision ruleR02S07Supporting referenceClaim-level link added by Harry.Cabinet Office guidance para 24Devolved Scottish authorities are generally excluded from the Act.Verified against full source on 21 Oct 2026
L096Decision ruleR02S10Supporting referenceClaim-level link added by Harry.Scottish Procurement Policy HandbookScottish procurement references.Verified against full source on 21 Oct 2026
L097Decision ruleR03S09Supporting referenceClaim-level link added by Harry.Welsh Government guidance collectionWelsh guidance and notice sequencing.Verified against full source on 21 Oct 2026
L098Decision ruleR04S11Supporting referenceClaim-level link added by Harry.PSN compliance pagePSN compliance certificate types; no closure date published.Verified against full source on 21 Oct 2026
L099Decision ruleR05S14Supporting referenceClaim-level link added by Harry.LGA publication landing pageReorganisation continuity and transition considerations.Verified against full source on 21 Oct 2026 (landing page only)
L100Decision ruleR06S17Supporting referenceClaim-level link added by Harry.DHSC guidanceAnalogue telecare may become unreliable if not upgraded; guidance is for housing providers in England.Verified against full source on 21 Oct 2026
L101Decision ruleR06S16Supporting referenceClaim-level link added by Harry.DSIT guidanceIndustry PSTN switch-off by January 2027.Verified against full source on 21 Oct 2026
L102Decision ruleR10S19Supporting referenceClaim-level link added by Harry.RFP builder pageUsers review and approve what suppliers receive; private draft download needs no account or publication.Verified against full source on 21 Oct 2026
Open questions / 23 records
oq_idownerareaquestionwhy_it_mattersrelated_idsstatus
OQ01RobertProductWhich parts of the planner (inputs, live outputs, printable outputs) will exist at launch? The copy is written as a step-by-step planner with live outputs and printable versions.Controls whether M01 buttons and all result labels can go live.M01;Planner inputs;Output templatesOpen
OQ02RobertProductWhat exactly carries forward from the planner into the RFP builder? The page says the builder has no council-specific pack or confirmed prefill. M13 uses a copy-and-paste fallback and does not promise prefill.Avoids promising behaviour that does not exist.M13;RFP handoff H01 to H14Open
OQ03RobertProductWhat is the real destination and workflow for the optional supplier-response step, and is the button wording Discuss supplier responses for my council refresh acceptable? The copy is marked [ROBERT TO CONFIRM] and should not go live until confirmed.The brief says to use this wording only after confirmation.M14Open
OQ04RobertConflictOn 21 Oct 2026 the live Netify board page is headed as a live marketplace, says 18 opportunities are genuinely open and lists recently closed and awarded notices. The brief says it presents a Market Record with no approved outcome records. The manuscript makes no claim about the board either way.Prevents publishing a claim that contradicts the live page.M14;S20Open
OQ05RobertConflictThe how-it-works page describes a private project with work-email sign-in and does not mention downloads, whereas the RFP builder says no account or publication is needed to download a draft. Copy follows the RFP builder only.Older copy conflicts with the current builder.M13;M14;S21Open
OQ06RobertDisclosureConfirm Netify's approved supplier fee disclosure wording. M14 uses the RFP builder line Suppliers pay Netify when an introduction leads to business, which does not affect how providers are ordered.The brief requires approved disclosure and no claim that all providers are available.M14Open
OQ07RobertQuestion bankMap Q01 to Q32 to the governed bank (T10). No live question IDs were invented. Harry proposes applicability conditions, early engagement or priced RFP labels and response formats, and tightened wording on 10 rows (apostrophes only).Existing matches and new wording need review.RFP questionsOpen
OQ08RobertPublicationConfirm the final public title and address (/insights/council-sd-wan-refresh/). The M01 heading in Page modules was changed from SD WAN to SD-WAN for consistency with the H1.Heading text affects cross-checks.Page modules M01Open
OQ09HarryEvidenceEnfield's own decision page could not be re-opened (the council site blocks automated fetching). Manuscript wording is limited to the brief's description. Open it in a browser and confirm the decision date (workbook shows 16 April for the source and 17 April for the case), decision maker, term and route. A third-party mirror of the record was glanced at but is not used or cited.CASE02 and S02 remain re-check before publication.M02;M12;CASE02Closed. Unable to source. Enfield's decision page blocks automated access. Wording stays at the brief's description and the case is marked for a manual check by the council or a browser review before publication
OQ10HarryEvidenceThe listed Network Services 3 URL is blocked to automated fetching and redirects to https://www.gca.gov.uk/agreements/RM6116, where the content was verified. Consider replacing the source URL with the gca.gov.uk address.Manuscript source list links to the working address.S06Open
OQ11HarryEvidence gapReviewed research found no Welsh council WAN or SD-WAN decision or award. Two Welsh items were added as context only. Caerphilly's joint dynamic purchasing system notice (S33) covers all 22 authorities for broad networking and Welsh Government's PSBA 3 planning notice (S34) is an estimate. The research also reports that Bridgend's schools strategy says its schools use PSBA, but that is not a procurement record and we have not opened it. Result, 7 verified council records across England, Scotland and Northern Ireland, and a Wales gap that still needs a council award or call-off record.The brief asks for gaps to be recorded openly.M12;Council evidenceClosed. Unable to source a Welsh council WAN or SD-WAN award or decision. Wales is recorded as an evidence gap
OQ12HarryEvidenceFor the ten Northern Ireland councils no council award notice has been found on Find a Tender (the 2022 contract notice and change notice link to nothing newer). The award is reported only in supplier-attributed trade press (S31), so CASE07 stays at contract notice stage. Check eTendersNI directly.No award claim can be published.CASE07Closed. Unable to source a council award notice. CASE07 stays at contract notice stage and no award claim is made
OQ13HarryEvidenceThe Adur and Worthing decision page, rechecked on 21 Oct 2026, still shows status For Determination with call-in, effective from 7 Oct 2026. It doesn't say whether the call-in period passed, so implementation and signature are not claimed. Confirm with the council. The page does not describe a shared-service arrangement, so it is not used as the shared-service case.Stage description depends on call-in outcome.CASE04;S04Closed. Unable to source confirmation of the call-in outcome or signature. The page still shows For Determination, so no implementation claim is made
OQ14HarryEvidenceEast Riding's award notices are verified (S36, S37), with the supplier and value for each. The tender notice 081392-2025 still shows two deadlines, 23 Jan 2026 in the structured field and 9 Jan 2026 in the procedure text, and the notice gives no reason for the edit, so both are reported. Delivery is not verified.Stage is described as tender notices only.CASE05;S05;S24;S25Closed. Award notices verified (S36, S37). Deadline conflict in the tender notice is reported as shown, with no reason given
OQ15HarryEvidenceCheshire East's award notice 047572-2025 (S32) is verified, Virgin Media Ltd, GBP900,408 excluding VAT, concluded 7 Aug 2025. Still unverified, whether the Capita contract was extended beyond 3 Feb 2026, the matching Cheshire West and Chester outcome and delivery.Outcome not verified.CASE06;S26Closed. Award verified (S32). Unable to source a Capita extension decision, the Cheshire West and Chester outcome or delivery, so none is claimed
OQ16HarryEvidenceThe research read the LGA PDF only to printed page 27 and did not reach the novation passage. Contract transfer and novation points are cited to the separate Local Digital page (S35), not the LGA report. Open the full PDF before attributing network-specific points to it.Claims linked to S14 are limited to the continuity theme.S14Closed. Unable to source the novation passage in the LGA PDF. Transfer and novation points are cited to the Local Digital page (S35)
OQ17HarryRecheckDate-check immediately before handover. Network Services 3 lot dates, PSN page, CAF wording, telecare and landline guidance, the Welsh guidance page (it shows an update date of Aug 2025 but lists some guidance titles dated Sept 2026) and the later PSBA3 notice version dated 16 June 2026.The brief requires a source review date and future review action.SourcesOpen. Next review recommended 1 month before publication
OQ18Finance and HarryCostNo defensible published unit rate was found. Published figures are single contract values (Adur and Worthing decision, Cheshire East and East Riding award notices), a procurement estimate (Northern Ireland councils), a broad service envelope (Greenwich) and a national aggregation estimate (PSBA3). All rate fields are left blank.A tender envelope is not a unit rate.Cost scheduleClosed. No action unless a quote is supplied
OQ19RobertProductDoes the planner store answers, keep them in-session only, or save to a project? M01 says only that the plan is a private draft and that nothing is published or sent to suppliers without approval.Privacy copy cannot say more than the product does.M01Open
OQ20RobertStructureWhere should the Illustrative council scenario sit? It is currently written as a separate section reached from the See what my plan will include button.Layout decision.ScenarioOpen
OQ21RobertAccessibilityThe planner copy follows the no colour-only warnings rule and avoids forced time limits. Netify is not a public body, so no accessibility compliance claim is made. Confirm the build meets WCAG 2.2 AA as an aim.Reference S18 applies to public sector bodies.S18Open
OQ22HarryCitationsThe brief lists S02 against M11 and S20 and S21 against M14. No sentence in the copy relies on them. Propose removing those three links or giving them a supporting claim.Avoids unsupported research-basis links.L026;L037;L038Open
OQ23RobertScenarioConfirm the optional scope-sensitive additions Q08 and Q11 for the worked example, and whether the changed-input examples should appear on the page or only in the manuscript.Brief allows additions where applicable.ScenarioOpen
Planner inputs / 26 records
input_idlabeldata_typeallowed_valuescouncil_purposeunknown_handlingvisibilityrequired_whenhelp_copyunknown_message_copy
I01Council nationenumEngland;Scotland;Wales;Northern Ireland;UnknownSelect the correct procurement research branch.Ask procurement team; never assume England.Private projectOptional to startChoose the nation your council is in. This decides which procurement research we show you, and it never assumes England.Nation unconfirmed. Ask your procurement lead to confirm your nation and procurement arrangement before you rely on any route notes.
I02Council type and responsibilitiestextCouncil suppliedAvoid assigning social care housing or highways duties to the wrong authority.Ask which services are in scope.Private projectOptional to startSay what type of council you are and which services it is responsible for, for example unitary, county, district, Scottish, Welsh or Northern Irish. Don't assume services such as social care, housing or highways. List only what your council delivers.Responsibilities unconfirmed. Ask which services are in scope with your service owners, so the plan doesn't include services another authority delivers.
I03Refresh driversmulti_selectRenewal;End of support;Resilience;Cloud access;Shared services;Reorganisation;Other;UnknownPrioritise the project objective.Retain an objective-confirmation action.Private projectOptional to startSelect every reason behind this refresh. Most councils have more than one. Pick Unknown if the objectives haven't been agreed.Objectives unconfirmed. Agree the reasons for the refresh with your project sponsor. Until then, the plan keeps an objective-confirmation action open.
I04Project stageenumDiscovery;Business case;Market engagement;RFP preparation;Procurement underway;UnknownChoose a draft brief or supplier question output.Use discovery output.Private projectOptional to startTell us where the project is today. We use it to offer you a draft brief or a supplier question set that fits.Project stage unknown. We'll show the discovery output, which is a safe starting point at any stage.
I05Sites in scopeinteger0 or greater; blank means unknownEstimate estate completeness.Do not estimate an unknown site count.Private projectOptional to startEnter the number of sites in scope, or leave it blank if you don't know. A blank means unknown and is never treated as zero.Site count unconfirmed. Leave it blank and add a site inventory action to your list. We won't estimate it for you.
I06Contract end datedateCouncil supplied YYYY-MM-DDIdentify timing dependency.Show deadline not confirmed.Private projectOptional to startEnter the date your current network contract ends, if you know it, as YYYY-MM-DD.Your contract deadline is unconfirmed. Ask the contract owner for the end date, notice period and any extension options.
I07Contract notice datedateCouncil supplied YYYY-MM-DDIdentify an earlier commitment deadline.Request contract notice terms.Private projectOptional to startEnter the last date you can give notice or commit to an extension. This is often earlier than the end date.Notice date unknown. Ask the contract owner for the notice terms, and treat the contract as having an earlier unconfirmed deadline.
I08Existing service and contract scopetextCouncil suppliedSeparate circuits overlay management LAN and security.Ask incumbent for service schedule.Private projectOptional to startDescribe what the current contract covers, such as circuits, the overlay, management, LAN and security. Use plain descriptions and keep contract references out.Contract scope unconfirmed. Ask the incumbent for its service schedule so you can compare like with like.
I09Device support expirydateCouncil supplied YYYY-MM-DDIdentify hardware support risk.Request asset and licence inventory.Private projectOptional to startEnter the date your main network devices go out of vendor support, if you know it.Support end date unknown. Ask for the asset and licence inventory so we can show the hardware risk date.
I10Critical service dependenciesmulti_selectRevenues and benefits;Housing;Adult services;Childrens services;Contact centre;Libraries;Depots;Other;UnknownSet scope by actual council responsibilities.Service owners confirm before design approval.Private projectOptional to startSelect the services that depend on this network. Only pick services your council delivers.Critical services unconfirmed. Ask service owners to confirm what depends on the network before design approval.
I11PSN or restricted partner dependencyenumYes;No;Unknown;Not applicableStop unapproved removal of a required path.Retain dependency assessment task.Private projectOptional to startSay whether any service still relies on PSN or a restricted partner connection. PSN isn't a circuit type, so answer for services and not for links.Confirm which services still depend on PSN or a restricted partner connection before planning to remove legacy links.
I12Shared service or reorganisation dependencyenumYes;No;Unknown;Not applicableCapture ownership and transition constraints.Ask programme and legal leads.Private projectOptional to startSay whether a shared service or a reorganisation affects the network contract, sites or licences. Answer Not applicable if neither applies.Dependency unconfirmed. Ask the programme lead and legal team whether sites, licences or contracts could transfer or separate.
I13Telecare alarm or building system dependencyenumYes;No;Unknown;Not applicableSeparate safety-critical device change from network migration.Require service owner review.Private projectOptional to startSay whether telecare alarms or building systems use the network or rely on analogue lines. Answer Not applicable if your council has none.Dependency unconfirmed. Ask the relevant service owner to assess alarms and building systems before any affected site is cut over.
I14Preferred operating modelenumCouncil managed;Co managed;Fully managed;UndecidedSet responsibilities and scope for comparable proposals.Generate model comparison questions.Private projectOptional to startChoose the model you'd prefer to run after migration. Undecided is a valid answer, and we'll show you how the three compare.Operating model undecided. We'll add comparison questions so suppliers respond to the same responsibility table.
I15Available project budget GBPdecimal0 or greater; blank means unknownDistinguish confirmed budget from incomplete estimate.Keep unknown; do not fill with typical rates.Private projectOptional to startEnter the confirmed project budget in pounds, or leave it blank if there isn't one yet. Never enter a typical or estimated figure here.Budget unconfirmed. Keep it blank. The cost schedule will show a priced subtotal and won't pretend to be a complete total.
I16Evaluation term monthsintegerPositive integer; council suppliedCompare proposals over an equal term.Do not calculate a whole-term total.Private projectOptional to startEnter the term in months you want proposals compared over, so every response covers the same period.Term not set. Without an equal term, no whole-term total or comparison is shown.
I17Funding and VAT basistextCouncil finance suppliedAvoid confusing funding treatment cash cost and procurement valuation.Finance review required.Private projectOptional to startEnter how the project is funded and the VAT basis your finance team will use. Finance decides VAT recovery and accounting treatment.Funding and VAT basis unconfirmed. Ask your finance lead before cost figures are used in a business case.
I18Procurement arrangement and routetextCouncil procurement suppliedConfirm nation framework lot and applicable regime.Show route requires procurement review.Private projectOptional to startRecord the procurement arrangement, framework and lot your procurement lead has agreed, if any. This is a record of their decision and not a legal determination.Route unconfirmed. Procurement review is needed before any route is described in your brief.
I19Council blackout datesdate_listCouncil suppliedProtect elections payments duty and other locally agreed events.Ask service owners for constraints.Private projectOptional to startEnter dates your council wants protected, such as payment runs, billing, elections, duty arrangements or committee periods. Enter only what your service owners have agreed.Blackout dates unconfirmed. Ask each service owner which periods they protect before the migration plan is drafted.
I20Site service tierenumCouncil defined essential;Standard;Low impact;UnknownMake failure tests proportionate to services at the site.Require service owner classification.Private projectOptional to startClassify the site as Council defined essential, Standard or Low impact. The service owner decides, and the class sets how heavily we test failure at the site.Site tier unknown. Ask the service owner to classify the site before it enters a migration wave.
I21Council maximum acceptable interruption minutesinteger0 or greater; council suppliedSet application acceptance criteria independently of provider SLA.Do not invent an uptime target.Private projectOptional to startEnter the longest interruption in minutes the service can accept. This is your council's decision, not a supplier's service level.Ask the service owner to agree acceptable interruption and a witnessed application test before this site enters a migration wave.
I22Site access and power constraintstextCouncil suppliedPlan surveys rural coverage wayleaves and backup power.Add survey action.Private projectOptional to startDescribe access, power or permission issues, such as rural coverage, listed buildings, wayleaves or limited backup power. Keep exact addresses out.Constraints unconfirmed. Add a survey action for the site before design is agreed.
I23Cost line unit rate GBPdecimal0 or greater; blank means unknownCapture council-approved or supplier-quoted rates.Block complete total and show missing line.Private projectOptional to startEnter a unit rate in pounds that your council has approved or a supplier has quoted. Leave it blank if you don't have one.This schedule contains unpriced items. Review the missing rates before using a complete project total.
I24Cost line rate evidencetextQuote reference date scope and VAT basisExplain each rate and expiry.Label unverified assumption until reviewed.Private projectOptional to startRecord the quote reference, date, scope, billing basis, term, inclusions, exclusions and VAT basis for the rate.Evidence missing. The rate is labelled an unverified assumption until someone reviews it.
I25Authority to seek responsesenumNot requested;Pending review;Approved by councilSeparate draft preparation from optional sourcing.Retain private draft.Private projectRequired before sourcing requestSay whether your council has authorised a request for supplier responses. Preparing a draft doesn't need this.Keep preparing your private draft. Review the supplier-facing summary and your council's procurement route before requesting responses.
I26Supplier-facing summary approvalenumNot prepared;Under review;ApprovedConfirm exactly what suppliers will receive.No supplier-facing release.Restricted reviewRequired before releaseSay whether the exact supplier-facing summary has been prepared and approved. Nothing is released until it is Approved.Keep preparing your private draft. Review the supplier-facing summary and your council's procurement route before requesting responses.
Migration tasks / 12 records
milestone_idmilestoneproposed_ownerdependencycouncil_duration_dayscouncil_target_dateacceptance_evidencedraft_help_copyconfidence_note_prompt
MS01Estate discoveryCouncil network leadContract and asset accessUnknown / not suppliedUnknown / not suppliedInventory with missing information recordedGather the contract, circuit list, asset and licence list and site details. Record what's missing as an open item with an owner. Enter a duration or date only if you know it.Prompt for a confidence note: High, Medium or Low, with the reason.
MS02Essential-service requirementsCouncil service ownersService responsibility scopeUnknown / not suppliedUnknown / not suppliedApplication dependencies interruption targets and change windowsWork with service owners to name the applications, agree the interruption each service can accept, and set change windows. These are the council's decisions.Prompt for a confidence note: High, Medium or Low, with the reason.
MS03Business case and fundingCouncil finance and ITComparable cost scheduleUnknown / not suppliedUnknown / not suppliedApproved funding and scope assumptionsBuild the cost schedule from your own figures and supplier quotes. Finance confirms funding, VAT basis and scope assumptions.Prompt for a confidence note: High, Medium or Low, with the reason.
MS04Procurement route reviewCouncil procurement leadNation arrangement and contract regimeUnknown / not suppliedUnknown / not suppliedRecorded route decision and required noticesAsk the procurement lead to record the route and any notices required. The route is their decision.Prompt for a confidence note: High, Medium or Low, with the reason.
MS05Supplier processCouncil procurement leadApproved process and documentationUnknown / not suppliedUnknown / not suppliedComparable responses through the authorised routeRun the process your council has approved and keep responses comparable using the same site list, term and responsibilities.Prompt for a confidence note: High, Medium or Low, with the reason.
MS06Surveys and deliverySupplier and council estatesSite access permissions and access designUnknown / not suppliedUnknown / not suppliedSite delivery dependencies confirmedConfirm access, permissions and any civil works site by site. Flag rural and difficult-access sites for early survey.Prompt for a confidence note: High, Medium or Low, with the reason.
MS07Configuration and stagingSupplier and council network leadDesign and access roles approvedUnknown / not suppliedUnknown / not suppliedConfiguration and documentation reviewedReview configuration and documentation before any site goes live. Confirm who holds which access roles.Prompt for a confidence note: High, Medium or Low, with the reason.
MS08Representative pilotCouncil service owners and supplierTest criteria rollback and dependencies agreedUnknown / not suppliedUnknown / not suppliedWitnessed application failover and recovery resultsTest normal running and failed-link running with the named council applications. Include an essential-service site and a difficult-access site where you have one.Prompt for a confidence note: High, Medium or Low, with the reason.
MS09Migration wavesCouncil change authorityPilot acceptance and site readinessUnknown / not suppliedUnknown / not suppliedPer-wave approval and rollback recordMove sites in waves, each with its own approval, rollback trigger and responsible officer. Avoid your protected dates.Prompt for a confidence note: High, Medium or Low, with the reason.
MS10HypercareSupplier and council operationsWave completionUnknown / not suppliedUnknown / not suppliedIncident ownership monitoring and escalation confirmedAgree who owns incidents, what is monitored and how escalation works while the new service beds in.Prompt for a confidence note: High, Medium or Low, with the reason.
MS11Incumbent cessationCouncil contract ownerService acceptance and dependency sign-offUnknown / not suppliedUnknown / not suppliedApproved stop dates and final overlap costStop the old service only after recorded acceptance and dependency sign-off. Show overlap charges until the stop date.Prompt for a confidence note: High, Medium or Low, with the reason.
MS12Handover and exit readinessCouncil operationsAccepted service and documentationUnknown / not suppliedUnknown / not suppliedAccess training exports and next review dateConfirm access, training, exports and the next review date so the next refresh doesn't depend on an inaccessible management tenant.Prompt for a confidence note: High, Medium or Low, with the reason.
Council evidence / 8 records
case_idcouncilnationstagedatescopesite_countpublished_value_gbpvalue_basislessonsource_idpublish_statusverification_note
CASE01Royal Borough of GreenwichEnglandProcurement approval2026-10-01T12:00:00Managed network service covering inter-building and intra-building networks, internet and wireless services and firewalls, with a WAN and LAN hardware refresh described as in trainUnknown / not supplied16000000Estimated broad contract envelope over an initial 5 years with options to extend up to a further 5; VAT not stated. Not an SD-WAN priceSeparate management, hardware and access scope before comparing prices. Do not use as a per-site benchmark.S01Usable with scope limitationRecheck 21 Oct 2026. Approval, not award. Open Procedure under the Procurement Act 2023. No supplier or site count shown.
CASE02London Borough of EnfieldEnglandAward decision2026-04-17T12:00:00WAN infrastructure modernisation addressing legacy architecture and distributed cloud connectivityUnknown / not suppliedUnknown / not suppliedNot published in reviewed decisionLink the refresh business case to architecture dependencies and resilience.S02Usable with scope limitationPrimary page could not be re-opened on 21 Oct 2026 (automated fetch blocked). Wording limited to the brief's description. Confirm date, decision maker, term and route in a browser before publication.
CASE03South Oxfordshire and Vale of White HorseEnglandClosed tender2024-12-20T12:00:00LAN, wireless and security refresh supporting SD-WAN transition, joint tender with Vale of White HorseUnknown / not suppliedUnknown / not suppliedNotice displays GBP0; excluded as unusable price evidenceCapture hardware, licences, installation and ongoing support as separate priced lines.S03Usable with scope limitationRecheck 21 Oct 2026. Open procedure below threshold, closed, no award shown, term 10 Feb 2025 to 9 Feb 2030.
CASE04Adur and WorthingEnglandDecision to direct award under a framework2026-09-29T12:00:00Migrate fibre networking across 22 council sites to SD-WAN over CityFibre using a commercial ISP22129918.43GBP129,918.43 plus VAT over 3 years, single contract value via SBS DWS2 direct award. Not a unit rate or per-site benchmarkSeparate the SD-WAN service from the underlying access network when comparing scopes.S04Usable with scope limitationFull page reviewed 21 Oct 2026. Supplier KHIPU Networks Ltd. Page rechecked 21 Oct 2026 and still shows status For Determination with call-in, effective from 7 Oct 2026. It does not say whether the call-in period passed, so implementation and signature are not claimed. Shared-service arrangement not described. Stated cost reduction is the council's reasoning, not a verified saving.
CASE05East Riding of YorkshireEnglandContract award notices (two linked procurements)2026-06-15T12:00:00Cisco-based SD-WAN solution awarded to Specialist Computer Centres PLC and separate WAN connectivity awarded to KCOM Group Limited, both 26 June 2026 to 31 July 2031Unknown / not suppliedUnknown / not suppliedTwo separate award values excluding VAT, GBP1,415,000 for the SD WAN Solution (3 tenders) and GBP785,000 for WAN Connectivity (5 tenders). They are contract values, not unit rates, and are not summed or divided per site. Value cell left blank because two contracts existDecide whether platform and connectivity are bought together or separately.S05Usable with scope limitationAward notices 056210-2026 and 056223-2026 (S36, S37) reviewed 21 Oct 2026, published 15 Jun 2026, contract details notice 063312-2026 published 6 Jul 2026. Tender notice 081392-2025 still shows two deadlines, 23 Jan 2026 in the structured field and 9 Jan 2026 in the procedure text, with no stated reason, so both are reported. Award notices do not show delivery.
CASE06Cheshire East CouncilEnglandContract award notice2025-08-07T12:00:00SD-WAN connectivity for all council sites in a shared ICT service, via Network Services 3 Lot 1a, with separate contracts to avoid novation if the two partner councils separateUnknown / not supplied900408GBP900,408 excluding VAT is the total value of the contract shown in the award notice (3 tenders received, options 2 x 12 months or 24 months). It is a single contract value, not a unit rate or per-site benchmark. The earlier GBP1m to GBP3.4m range in the May 2025 report was a joint estimate and is a different measureDefine shared-service ownership and contract transfer before the contract starts, and price extension against delivery time.S26Usable with scope limitationAward notice 047572-2025 (S32) reviewed 21 Oct 2026, contract concluded 7 Aug 2025, supplier Virgin Media Ltd. Notice does not show a signed contract or delivery. Capita extension beyond 3 Feb 2026 and the Cheshire West and Chester outcome are not verified.
CASE07Armagh City, Banbridge and Craigavon Borough Council and nine partner councilsNorthern IrelandJoint contract notice2022-04-07T12:00:00Managed network services including WAN connectivity, network management, content filtering, firewalls and internet over new fibre, 120 months, open procedureUnknown / not suppliedUnknown / not suppliedEstimated GBP8,000,000 excluding VAT in the notice. Estimate only. Left blankTen authorities can define one shared service, so write the governance down at the start.S27Usable with scope limitationNotice and change notice reviewed 21 Oct 2026 (S27, S28). Award is reported only by supplier-attributed trade press (S31), so no award claim is made.
CASE08The Highland CouncilScotlandAgreement announced2023-10-24T12:00:00Network services agreement with BT under the Scottish Wide Area Network framework covering over 340 sites, nearly 200 schools and new fibre at over 100 sites, including some of the most challenging locations in ScotlandUnknown / not suppliedUnknown / not suppliedValue and term not statedScope remote and difficult-access sites explicitly, and measure what each can support.S29Usable with scope limitationCouncil news release reviewed 21 Oct 2026. SD-WAN is not mentioned. Site count is stated as over 340, so the integer field is left blank. Cited benefits are expectations, not outcomes.
Field dictionary / 124 records
datasetfield_namefield_typerequired_for_importmeaningvalidation_ruleexample
Page modulesmodule_idtextYesModule idStable key or linked key; never renumber existing records.M01
Page modulesheadingtextYesHeadingOne value per field; no merged cells or hidden assumptions.Plan your council SD WAN refresh
Page modulestarget_wordsintegerConditionalTarget wordsOne value per field; no merged cells or hidden assumptions.180
Page modulescouncil_decisiontextConditionalCouncil decisionOne value per field; no merged cells or hidden assumptions.Where do I start and what will I leave with?
Page moduleswriting_assignmenttextConditionalWriting assignmentOne value per field; no merged cells or hidden assumptions.Write the opening around contract expiry, legacy equipment and continuity of resident services. Name heads of IT, network managers and procurement leads. Promis
Page modulesrequired_assettextConditionalRequired assetOne value per field; no merged cells or hidden assumptions.Opening copy, 3 result labels, primary button and short privacy explanation.
Page modulesuser_outputtextConditionalUser outputOne value per field; no merged cells or hidden assumptions.Start a council refresh plan.
Page modulessource_idstextConditionalSource idsLink through Evidence links; semicolon list here is a reader aid, not an import join.S19
Page moduleseditorial_statustextConditionalEditorial statusUse the documented status values; do not treat editorial proposal as published fact.Brief supplied
Page modulesmanuscript_copytextConditionalManuscript copyOne value per field; no merged cells or hidden assumptions.Leave blank until known
Planner inputsinput_idtextYesInput idStable key or linked key; never renumber existing records.I01
Planner inputslabeltextConditionalLabelOne value per field; no merged cells or hidden assumptions.Council nation
Planner inputsdata_typetextConditionalData typeOne value per field; no merged cells or hidden assumptions.enum
Planner inputsallowed_valuestextConditionalAllowed valuesOne value per field; no merged cells or hidden assumptions.England;Scotland;Wales;Northern Ireland;Unknown
Planner inputscouncil_purposetextConditionalCouncil purposeOne value per field; no merged cells or hidden assumptions.Select the correct procurement research branch.
Planner inputsunknown_handlingtextConditionalUnknown handlingOne value per field; no merged cells or hidden assumptions.Ask procurement team; never assume England.
Planner inputsvisibilitytextConditionalVisibilityOne value per field; no merged cells or hidden assumptions.Private project
Planner inputsrequired_whentextConditionalRequired whenOne value per field; no merged cells or hidden assumptions.Optional to start
Planner inputshelp_copytextConditionalHelp copyOne value per field; no merged cells or hidden assumptions.Leave blank until known
Planner inputsunknown_message_copytextConditionalUnknown message copyOne value per field; no merged cells or hidden assumptions.Leave blank until known
Decision rulesrule_idtextYesRule idStable key or linked key; never renumber existing records.R01
Decision rulestriggertextConditionalTriggerOne value per field; no merged cells or hidden assumptions.Nation is unknown
Decision rulesshow_actiontextConditionalShow actionOne value per field; no merged cells or hidden assumptions.Ask the council procurement lead to confirm nation and arrangement.
Decision rulesdo_not_infertextConditionalDo not inferOne value per field; no merged cells or hidden assumptions.Do not suggest a final route.
Decision rulesreview_ownertextConditionalReview ownerOne value per field; no merged cells or hidden assumptions.Procurement lead
Decision rulesrelated_idstextConditionalRelated idsOne value per field; no merged cells or hidden assumptions.I01;I18
Decision rulesrule_statustextConditionalRule statusUse the documented status values; do not treat editorial proposal as published fact.Editorial rule proposed
RFP questionsquestion_idtextYesQuestion idStable key or linked key; never renumber existing records.Q01
RFP questionsareatextConditionalAreaOne value per field; no merged cells or hidden assumptions.Estate
RFP questionssupplier_questiontextYesSupplier questionOne value per field; no merged cells or hidden assumptions.Confirm coverage and delivery dependencies for each council site without substituting assumed access availability.
RFP questionsevidence_requestedtextConditionalEvidence requestedOne value per field; no merged cells or hidden assumptions.Site-by-site coverage and survey exceptions.
RFP questionscouncil_reasontextConditionalCouncil reasonOne value per field; no merged cells or hidden assumptions.Rural depots and civic buildings can have different access constraints.
RFP questionsapplies_whentextConditionalApplies whenOne value per field; no merged cells or hidden assumptions.All council refresh projects
RFP questionsexisting_question_idtextYesExisting question idStable key or linked key; never renumber existing records.Leave blank until known
RFP questionsmapping_statustextConditionalMapping statusUse the documented status values; do not treat editorial proposal as published fact.Robert to confirm existing bank match
RFP questionsauthor_statustextConditionalAuthor statusUse the documented status values; do not treat editorial proposal as published fact.Proposed question for council review
Cost schedulecost_item_idtextYesCost item idStable key or linked key; never renumber existing records.C01
Cost schedulecategorytextConditionalCategoryOne value per field; no merged cells or hidden assumptions.Discovery and design
Cost schedulecharge_basistextConditionalCharge basisOne value per field; no merged cells or hidden assumptions.one_off
Cost schedulequantity_unittextConditionalQuantity unitOne value per field; no merged cells or hidden assumptions.Project
Cost schedulequantitydecimalConditionalQuantityBlank means unknown, not zero. Quantities and periods require explicit units.Leave blank until known
Cost scheduleunit_rate_gbpdecimalConditionalUnit rate gbpBlank means unknown, not zero. Quantities and periods require explicit units.Leave blank until known
Cost schedulemonths_or_yearsdecimalConditionalMonths or yearsBlank means unknown, not zero. Quantities and periods require explicit units.Leave blank until known
Cost schedulevat_basistextConditionalVat basisOne value per field; no merged cells or hidden assumptions.Unknown
Cost schedulerate_source_reftextConditionalRate source refOne value per field; no merged cells or hidden assumptions.Leave blank until known
Cost schedulecouncil_notetextConditionalCouncil noteOne value per field; no merged cells or hidden assumptions.Include council and supplier effort separately.
Cost schedulerecord_statustextConditionalRecord statusUse the documented status values; do not treat editorial proposal as published fact.Unpriced template
Council evidencecase_idtextYesCase idStable key or linked key; never renumber existing records.CASE01
Council evidencecounciltextConditionalCouncilOne value per field; no merged cells or hidden assumptions.Royal Borough of Greenwich
Council evidencenationtextConditionalNationOne value per field; no merged cells or hidden assumptions.England
Council evidencestagetextConditionalStageOne value per field; no merged cells or hidden assumptions.Procurement approval
Council evidencedatedateConditionalDateOne value per field; no merged cells or hidden assumptions.2026-10-01
Council evidencescopetextConditionalScopeOne value per field; no merged cells or hidden assumptions.Managed WAN LAN WiFi and firewall support with hardware refresh dependency
Council evidencesite_countintegerConditionalSite countOne value per field; no merged cells or hidden assumptions.22
Council evidencepublished_value_gbpdecimalConditionalPublished value gbpBlank unless a defensible published amount exists; retain envelope and VAT basis.16000000
Council evidencevalue_basistextConditionalValue basisOne value per field; no merged cells or hidden assumptions.Estimated broad contract envelope over up to 10 years; VAT not verified
Council evidencelessontextConditionalLessonOne value per field; no merged cells or hidden assumptions.Separate management hardware and access scope before comparing prices.
Council evidencesource_idtextYesSource idStable key or linked key; never renumber existing records.S01
Council evidencepublish_statustextConditionalPublish statusUse the documented status values; do not treat editorial proposal as published fact.Usable with scope limitation
RFP handoffhandoff_idtextYesHandoff idStable key or linked key; never renumber existing records.H01
RFP handofffield_nametextConditionalField nameOne value per field; no merged cells or hidden assumptions.project_title
RFP handoffwhat_to_supplytextConditionalWhat to supplyOne value per field; no merged cells or hidden assumptions.Council SD-WAN refresh plus council-approved descriptor
RFP handoffdisclosure_ruletextConditionalDisclosure ruleOne value per field; no merged cells or hidden assumptions.Can appear in reviewed summary
RFP handoffdestinationtextConditionalDestinationOne value per field; no merged cells or hidden assumptions.https://netify.co.uk/sase-sd-wan-rfp-builder/
RFP handoffcarry_forward_statustextConditionalCarry forward statusUse the documented status values; do not treat editorial proposal as published fact.Proposed mapping for product confirmation
Sourcessource_idtextYesSource idStable key or linked key; never renumber existing records.S01
SourcestitletextYesTitleOne value per field; no merged cells or hidden assumptions.Council network managed services procurement
SourcespublishertextConditionalPublisherOne value per field; no merged cells or hidden assumptions.Royal Borough of Greenwich
SourcesurltextConditionalUrlOne value per field; no merged cells or hidden assumptions.https://greenwich.moderngov.co.uk/mgDecisionDetails.aspx?IId=7504&Opt=1
Sourcespublished_datedateConditionalPublished dateOne value per field; no merged cells or hidden assumptions.2026-10-01
Sourceschecked_datedateConditionalChecked dateOne value per field; no merged cells or hidden assumptions.2026-10-20
Sourcesreview_basistextConditionalReview basisOne value per field; no merged cells or hidden assumptions.Full page reviewed
Sourcesusable_scopetextConditionalUsable scopeOne value per field; no merged cells or hidden assumptions.Decision approves procurement covering WAN LAN WiFi and firewalls; associated hardware refresh. Estimated GBP16m over maximum 10 years is a broad service envelo
Output templatesoutput_idtextYesOutput idStable key or linked key; never renumber existing records.O01
Output templatesoutput_nametextConditionalOutput nameOne value per field; no merged cells or hidden assumptions.Council refresh brief
Output templatescontentstextConditionalContentsOne value per field; no merged cells or hidden assumptions.Council context objectives estate services dependencies dates operating model and procurement review.
Output templatesunknown_statetextConditionalUnknown stateOne value per field; no merged cells or hidden assumptions.List unknowns with owner and next evidence request.
Output templatesnext_steptextConditionalNext stepOne value per field; no merged cells or hidden assumptions.Create my council refresh RFP
Output templatessource_recordstextConditionalSource recordsOne value per field; no merged cells or hidden assumptions.Planner inputs;Decision rules;RFP handoff
Output templatesdraft_copytextConditionalDraft copyOne value per field; no merged cells or hidden assumptions.Leave blank until known
Migration tasksmilestone_idtextYesMilestone idStable key or linked key; never renumber existing records.MS01
Migration tasksmilestonetextConditionalMilestoneOne value per field; no merged cells or hidden assumptions.Estate discovery
Migration tasksproposed_ownertextConditionalProposed ownerOne value per field; no merged cells or hidden assumptions.Council network lead
Migration tasksdependencytextConditionalDependencyOne value per field; no merged cells or hidden assumptions.Contract and asset access
Migration taskscouncil_duration_daystextConditionalCouncil duration daysOne value per field; no merged cells or hidden assumptions.Leave blank until known
Migration taskscouncil_target_datedateConditionalCouncil target dateOne value per field; no merged cells or hidden assumptions.Leave blank until known
Migration tasksacceptance_evidencetextConditionalAcceptance evidenceOne value per field; no merged cells or hidden assumptions.Inventory with missing information recorded
Migration tasksdraft_help_copytextConditionalDraft help copyOne value per field; no merged cells or hidden assumptions.Leave blank until known
Route notesroute_idtextYesRoute idStable linked ID where applicable. Preserve scope and council review status.P01
Route notesnationtextConditionalNationStable linked ID where applicable. Preserve scope and council review status.England
Route notesresearch_notetextConditionalResearch noteStable linked ID where applicable. Preserve scope and council review status.Confirm whether the procurement uses the Act or a legacy framework. RM6116 is a legacy framework; identify relevant lot eligibility and method.
Route notesreview_ownertextConditionalReview ownerStable linked ID where applicable. Preserve scope and council review status.Council procurement lead
Route notessource_idtextYesSource idStable linked ID where applicable. Preserve scope and council review status.S06
Route notesstatustextConditionalStatusStable linked ID where applicable. Preserve scope and council review status.Draft research note
Evidence linkslink_idtextYesLink idStable linked ID where applicable. Preserve scope and council review status.L001
Evidence linksrecord_typetextConditionalRecord typeStable linked ID where applicable. Preserve scope and council review status.Page module
Evidence linksrecord_idtextYesRecord idStable linked ID where applicable. Preserve scope and council review status.M01
Evidence linkssource_idtextYesSource idStable linked ID where applicable. Preserve scope and council review status.S19
Evidence linksrelationshiptextConditionalRelationshipStable linked ID where applicable. Preserve scope and council review status.Editorial research basis
Evidence linkspublication_notetextConditionalPublication noteStable linked ID where applicable. Preserve scope and council review status.Verify the specific factual sentence before publication.
Evidence linkssource_locationtextConditionalSection clause paragraph or page supporting the exact claimHarry completes for each final factual claim. Research-basis links alone do not establish sentence-level verification.Leave blank until the specific manuscript claim is reviewed
Evidence linksclaim_texttextConditionalFinal factual statement supported by this sourceHarry completes for each final factual claim. Research-basis links alone do not establish sentence-level verification.Leave blank until the specific manuscript claim is reviewed
Evidence linksclaim_review_statustextConditionalReview status for the individual factual statementHarry completes for each final factual claim. Research-basis links alone do not establish sentence-level verification.Leave blank until the specific manuscript claim is reviewed
Decision rulesmessage_copytextNoVisible message shown when the rule firesProposed addition. Robert to confirm mapping.Your contract deadline is unconfirmed. Ask the contract owner for the end date, notice period and any extension options.
RFP questionsplanner_sectiontextNoPage module where the question is introducedProposed addition. Robert to confirm mapping.M06
RFP questionsrfp_stage_usetextNoWhether the question suits early market engagement, a priced RFP or bothProposed addition. Robert to confirm mapping.Early market engagement and priced RFP
RFP questionsresponse_formattextNoFormat the supplier is asked to respond inProposed addition. Robert to confirm mapping.Per-site survey result and load test
RFP questionsharry_review_notetextNoWhat was changed in reviewProposed addition. Robert to confirm mapping.Wording unchanged.
Cost scheduleunit_definitiontextNoWhat one unit means for the categoryProposed addition. Robert to confirm mapping.One charge per affected site
Cost schedulefinance_questiontextNoQuestion for the finance teamProposed addition. Robert to confirm mapping.Which sites have access constraints?
Cost schedulerate_evidence_notetextNoEvidence needed before a rate can be enteredProposed addition. Robert to confirm mapping.Record date, scope, billing basis, term, inclusions, exclusions and VAT basis.
Council evidenceverification_notetextNoWhat was verified, when, and limitationsProposed addition. Robert to confirm mapping.Full page reviewed 21 Oct 2026.
Route notesdate_checkeddateNoDate the cited references were last checkedProposed addition. Robert to confirm mapping.2026-10-21
Route notesnext_review_actiontextNoReview action and timingProposed addition. Robert to confirm mapping.Re-check dated references one month before publication.
RFP handoffdraft_contenttextNoScenario content for the handoff fieldProposed addition. Robert to confirm mapping.24-site council SD-WAN refresh, co-managed
RFP handoffresearch_blockertextNoOpen product or research dependencyProposed addition. Robert to confirm mapping.Robert to confirm carry-forward behaviour.
Migration tasksconfidence_note_prompttextNoPrompt for the council's confidence noteProposed addition. Robert to confirm mapping.High, Medium or Low, with the reason.
Open questionsoq_idtextYesStable key for an outstanding questionProposed addition. Robert to confirm mapping.OQ01
Open questionsownertextNoWho needs to answerProposed addition. Robert to confirm mapping.Robert
Open questionsareatextNoTopicProposed addition. Robert to confirm mapping.Product
Open questionsquestiontextNoThe question or conflictProposed addition. Robert to confirm mapping.Which parts of the planner exist at launch?
Open questionswhy_it_matterstextNoEffect on publicationProposed addition. Robert to confirm mapping.Controls which buttons go live.
Open questionsrelated_idstextNoLinked record IDsProposed addition. Robert to confirm mapping.M01;M13
Open questionsstatustextNoOpen or closed, with noteProposed addition. Robert to confirm mapping.Open
Output templates / 4 records
output_idoutput_namecontentsunknown_statenext_stepsource_recordsdraft_copy
O01Council refresh briefCouncil context objectives estate services dependencies dates operating model and procurement review.List unknowns with owner and next evidence request.Create my council refresh RFPPlanner inputs;Decision rules;RFP handoffCouncil refresh brief. Contents, council context, objectives, estate, services, dependencies, dates, operating model and procurement review status. Unknowns appear in a list with an owner and the next evidence request. Closing line, "Use this brief in my council refresh RFP." Button, Create my council refresh RFP. Example output is the 24-site brief in the Illustrative council scenario.
O02Information to confirmOutstanding input evidence owner and decision affected. No aggregate readiness score.Retain open items even if the user continues with a private draft.Add this information to my draftPlanner inputs;Decision rulesInformation to confirm. A table with Missing item, Owner and Effect on the plan. There is no readiness score and no percentage. Open items stay on the list even if the user carries on with a private draft. Button, Add this information to my draft. Example output is the five-row evidence action list in the Illustrative council scenario.
O03Council refresh cost scheduleItemised one-off recurring overlap and exit costs with term units rate evidence and VAT basis.Show priced subtotal and missing items; no complete total while required rates are unknown.Use this cost schedule in my RFPCost scheduleCouncil refresh cost schedule. Itemised one-off, recurring, overlap and exit costs with unit, rate evidence and VAT basis. If any required rate is missing the schedule shows "Priced subtotal" with the missing lines listed, plus the message "This schedule contains unpriced items. Review the missing rates before using a complete project total." No complete total or savings percentage is shown while required rates are unknown. Whole-term nominal calculation, one-off costs plus monthly rates times chargeable months plus annual rates times chargeable years plus explicitly priced overlap and exit items. Indexation only with a stated method and date. Staff time and contingency are shown separately. Button, Use this cost schedule in my RFP.
O04Supplier question packSelected questions council reason supplier response format and supporting evidence requested.Keep unresolved requirements visible. Do not invent existing bank IDs.Create my council refresh RFPRFP questions;RFP handoffSupplier question pack. The selected questions, each with the council reason, the supplier response format and the evidence requested, labelled Early market engagement or Priced RFP. Unresolved requirements stay visible, and no live question-bank IDs are shown unless Robert confirms a match. Button, Create my council refresh RFP.

Data and assistant access

Data source: neon-postgres. Version 2026-11-04.1. The page and tools use the same workbook and planner rules.

Complete article and workbook data · Research tool specification · Planner tool specification · MCP server

  • Original manuscript and workbook retained in full. Editorial and delivery notes describe the supplied research, not current instructions or supplier commitments.
  • Planner answers stay in memory in the visitor’s browser. Downloads are local. The stateless MCP/REST planner returns a draft without saving it or contacting suppliers.
  • Working Q references are council question-pack references, not governed RFP question-bank IDs. Copy/download the plan into the existing builder; automatic prefill is not claimed.
  • Prices are council-entered or supplier-quoted only. No benchmark rates, complete totals with missing lines, automatic procurement decisions or compliance certifications.
  • Enfield source verification remains unresolved; its April 2026 example is a research lead for manual confirmation, not a verified award endorsement.